JADWALPELAKSANAAN

PEKERJAANWIDENING
PAKETPEKERJAANPEMBANGUNANJALANTOLJAKARTACIKAMPEKII
ELEVATEDRUASCIKUNIRKARAWANGBARAT
ZONA6(STA40+00037+500)

JadwalPelaksanaan(2017)

######
######
######
######
######
######
######
######
######
######
######
######
######
######
######
######
######
######
######
######
######
######
10Apr
11Apr
12Apr
13Apr
14Apr
15Apr
16Apr
17Apr
18Apr
19Apr
20Apr
21Apr
22Apr
23Apr
24Apr
25Apr
26Apr
27Apr
28Apr
29Apr
30Apr
No Pekerjaan Satuan Volume Bobot(%)

1May
2May
3May
4May
5May
6May
7May
8May
9May
1Apr
2Apr
3Apr
4Apr
5Apr
6Apr
7Apr
8Apr
9Apr

1Jun
2Jun
3Jun
4Jun
5Jun
6Jun
7Jun
BAB1 UMUM
1 Mobilisasi Ls 1.00 3.13% 0 0 0 0 0 0 0
2 PemeliharaandanPerlindunganLaluLintas Ls 1.00 0.80% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3 APD Ls 1.00 0.27% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
BAB2 PEMBERSIHANTEMPATKERJA
2.01 PembersihanTempatKerja m2 15,250.00 0.57% 0 0 0 0 0 0 0 0 0
BAB3 PEMBONGKARAN
3.01.2 PembongkaranGuardRail m' 1,287.22 1.06% 0 0 0 0 0 0 0
PembongkaranPerkerasan m2 6,250.00 6.88% 1 1 1 1 1 1 1 1 1
BAB4 PEKERJAANTANAH
4.03(2) GalianBiasauntukDibuang m3 4,098.44 1.54% 0 0 0 0 0 0 0 0 0
4.05(1) BorrowMaterial m3 7,075.00 10.35% 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Limestone m3 610.00 1.39% 0 0 0 0 0
BAB6 DRAINASE
6.06(1)b Saluran,TipeDS1 m' 1,125.00 0.64% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
6.06(1)d Saluran,TipeDS2 m' 1,125.00 25.80% 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
ExtensionRCPipeD1000 m' 12.33 0.55% 0 0 0 0 0 0 0 0 0 0 0 0
BAB7 SUBGRADE
7.01 PersiapanTanahDasar m2 15,250.00 0.75% 0 0 0 0 0 0 0 0 0
BAB8 LAPISPONDASIAGREGAT
8.01(1) LapisPondasiAgregatKelasA m3 2,287.50 8.28% 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
BAB9 PERKERASAN
9.05 BituminousTackCoat m2 6,100.00 0.59% 0 0 0 0 0 0 0
9.07(3) AsphalticConcreteWearingCourse(ACWC) ton 1,318.82 7.71% 1 1 1 1 1 1 1
9.07(4) SemenAspal ton 84.18 5.36% 1 1 1 1 1 1 1
9.08(1) PerkerasanBeton(t=30cm) m2 15,250.00
9.09(1) LeanConcrete(t=10cm) m2 15,250.00 12.06% 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
BAB10 STRUKTURBETON
10.01(4) BetonKelasB1,fc'=30Mpa(BoxCulvert) m3 18.29 0.28% 0 0 0 0 0 0 0 0 0 0 0 0
10.01(8) BetonKelasE,fc'=10Mpa m2 11.25 0.01% 0 0 0 0 0 0 0 0 0 0 0 0
10.02(2) BatangBajaTulanganUlir(BJTD40) kg 3,711.10 0.38% 0 0 0 0 0 0 0 0 0 0 0 0
PengadaandanPemasanganConcreteSheetPile m' 1,000.00 11.61% 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
ProgressMingguan 100.00% 0.463 7.125 9.169 21.811 24.829 17.188 4.820 0.660 0.112 7.920 5.904
AkumulasiProgress 0.463 7.587 16.756 38.567 63.396 80.584 85.405 86.064 86.176 94.096 100.000