DISEO DE CANOAS
Proyecto : MEJORAMIENTO DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO WINCOCOCHA - ANTILLA - SABAINO, DISTRITO DE SABAINO ANTABAMBA APURMAC
Obras de Arte: Canoa
CUENCA m2 km2
Area Total 23,600.00 0.02
Longitud 206.00 0.21
TIEMPO DE CONCENTRACION
0 .385
L3
t C=0.871 ( c
C 1C 2 )
tc = 1.063 hr M(-) = 1/24 1/24
INTENSIDAD DE LA LLUVIA
Periodo de Retorno
T= 50.000 aos
Duracin de la tormenta
M(+) = 1/14
t= tc * 60 A B
t= 63.768 min
Bt = `0.150485+0.542754*Lnt-0.15447*Lnt^2+0.0299766*Lnt^3-0.00298499*Lnt^4+0.000109265*Lnt^5
Bt = 0.804
Ln I (T) = `- 0.55465 * Ln t + Bt PARAMETROS DE DISEO
Ln I (100) = -1.500 Peso Volumetrico del Concreto 2400 Kg/m3
I (100) = 0.223 mm/min fy 4200 Kg/cm2
fc 175 Kg/cm2
PRECIPITACION CRITICA Recubrim. ( r ) 2.5 cm
Pt = I(T) * t mm/t Espesor losa (el) 0.15 m
Pt = 14.224 mm/16.70 hr Para Flexin Sin Carga Axial: Fact. Reduc.() 0.9
Para esfuerzo cortante c/s torsin: Fact. Reduc.() 0.85
DESCARGA MAXIMA DE 100 AOS Def. Mx. aceptable en el C antes de la falla: (c) 0.003
Q(T) = C * Pt * A / 3.6 * t Coeficiente de deformacin del acero: (y) 0.0025
Q(T) = 0.066 m3/seg Sobrecarga o Carga Viva por 1m de ancho: (W) 800 Kg/m
Altura til (d) 12.5 cm
CALCULO DE LA DESCARGA MAXIMA
Cota Cota Dif. Area Longitud Dif. Tiempo Precip. Desc.
Area Longitud Intensidad de lluvia (para 100 aos)
Mayor Menor Niveles Cuenca Cuenca Cotas Concent. Critica Max.
Nro Prog
I (100) Pt Q(t)
(m2) (m) (m) (m) (Km) (Km2) (Km) (Km) (hr) t (min) (Bt) Ln I (100)
mm/min (mm/hr) (m3/seg)
1 00+430 23,600.00 206.00 3,280.00 3,207.00 0.07 0.02 0.21 0.07 0.42 25.13 0.80 -0.98 0.37 9.40 0.110
2 00+300 24,500.00 230.00 3,272.00 3,201.00 0.07 0.02 0.23 0.07 0.48 28.85 0.80 -1.06 0.35 9.99 0.106 SEC. PALCCA
3 01+515 32,554.44 240.00 3,120.00 3,077.00 0.04 0.03 0.24 0.04 0.61 36.76 0.80 -1.19 0.30 11.13 0.123
4 00+031 24,054.53 219.68 3,173.00 3,055.00 0.12 0.02 0.22 0.12 0.37 22.50 0.80 -0.92 0.40 8.94 0.120
5 00+216 25,038.15 146.75 3,358.00 3,051.00 0.31 0.03 0.15 0.31 0.16 9.77 0.80 -0.46 0.63 6.17 0.198
AGRORURAL - AGENCIA APURIMAC
DISEO DE CANOAS
PROYECTO: MEJORAMIENTO DEL SERVICIO DE AGUA DEL SISTEMA DE RIEGO WINCOCOCHA - ANTILLA - SABAINO, DISTRITO DE SABAINO ANTABAMBA APURMAC
Obras de Arte: Canoa
1 00+430 3620.00 0.40 0.70 0.10 0.110 I 2.00 0.15 0.06 0.017 0.01 0.25 2.30 0.40 0.90 1.80 1.60 2.60 2.40 0.21
1 00+430 720.00 2520.00 85.05 145.80 1020.60 3.75 1.06 1696.83 Bien! 3.75 18.93 17.50 3.13 22.72 20.00 5.62 7027.78 Bien!
2 00+300 720.00 2520.00 85.05 145.80 1020.60 3.75 1.06 1696.83 Bien! 3.75 18.93 17.50 3.13 22.72 20.00 5.62 7027.78 Bien!
3 01+515 720.00 2520.00 85.05 145.80 1020.60 3.75 1.06 1696.83 Bien! 3.75 18.93 17.50 3.13 22.72 20.00 5.62 7027.78 Bien!
4 00+031 720.00 2520.00 85.05 145.80 1020.60 3.75 1.06 1696.83 Bien! 3.75 18.93 17.50 3.13 22.72 20.00 5.62 7027.78 Bien!
SEC. MANZANAPATA
5 00+216 720.00 2520.00 85.05 145.80 1020.60 3.75 1.06 1696.83 Bien! 3.75 18.93 17.50 3.13 22.72 20.00 5.62 7027.78 Bien!
METRADOS DE CANOAS
0.23 0.14 0.71 0.92 1.17 4.42 0.46 0.31 0.03 1.11 14.01 1.96 2.07 0.72 4.15 2.72 2.24
CANOAS
CONCRETO CICLOPEO FC=140 KG/CM2 + 70 % PG. 2.23 m3
CONCRETO SIMPLE FC=175 KG/CM2 (PREP. MANUAL) 0.80 m3
ACERO Fc=4200 KG/CM2 15.96 kg
TARRAJEO CON MORTERO C:A MEZCLA 1:5; E=2.0 CM 9.66 m2