Stator TABLE 3
70 cm Initial investment for gharo tidal project
S .no Equipment Estimated cost
1 Hydro graphic survey 10,00,000
2 Dredging and cleanining 80,00,000
3 Break water 100,00,000
Fig.10: Generator dimensions 4 Bulb turbine 87,00,000
5 Grid station 8,00,000
6 Transmission line 60,00,000
7 Transportation cost 40,00,000
8 Miscellaneous 15,00,000
Total cost 400,00,000
A. Alternative design
There is an alternative method which can be much more cost
effective. By using worm gear instead of bulb turbine, turbine
shaft can be changed from horizontal to vertical shaft and
connected to the generator.
Fig.11:3d design for Bulb type turbine with holding assembly
V. RECOMMENDED DESIGN Generator mounted vertically downward
In future we can upgrade our system to improve the output
from this tidal creek by increasing the number of poles of
generator to 24 or an alternative method can be adopted to
increase the number of generators. When we increase the Bridge
number of generator in the bulb type turbine the required
torque will be increased and the number of RPM will reduced
to half. It is very good to increase the diameter of bulb so can
a 48 pole generator can work properly.
VII. CONCLUSION
The available power output from gharo creek is 1 MW.
This potential is enough for gharo city .Assuming the average
power consumption of single house is 1 kilo Watt hour. The
consumption for one house is 0.28 watt/sec. Gharo creek can
fulfil the requirements of 3,500,000 houses. Assuming Per
unit cost in Pakistan is 9 Rs. The consumption of one kilowatt
for 18 hours so the average consumption for one house will be
18 kilo watt hour. The bill for single house will be 48600 Rs
per year. The expected annual output from gharo creek will be
170 billion Rs. This will be great achievement for Pakistan.
We can increase the efficiency of mechanical to electrical
conversion up to 70 %. There are some modern design
implementation of bulb turbine. By using different generator
and turbine configuration.