Index-code S No Description Unit Quantity Rate Rs. Amount Rs.


Worked Out 29 Removing old grading plaster from roof slab, cleaning the surface, lowering and removing the debris within 50m lead
Data
Rate for 10 Sqm
Labour
Men Mazdoor Nos 0.261 295.00 77.00
Woman Mazdoor Nos 0.04 295.00 11.80
88.80
Add 20% Extra for Municipal Limits 0.20 88.80 17.76
106.55
Add contractor Profit 13.615% 0.13615 106.55 0.00
Cost for 10 Sqm 106.55
Cost for 1 Sqm 10.66

Datas Page 1