1 (ONE)

1.00 1 copy of complete CD for the Contractor


2.00 1 year from Final Acceptance of Work coverage of Guarantee Bond 30% submitted before Final Payment
3.00 1 (once) a month Request of Payment Limitation

2 (TWO)
1.00 2 copies of shop drawings for architect approval by contractor (construction methodology including sub-contractors)

2.00 2 months after Acceptance of Work release of Performance Bond and Payment Bond
3.00 2 weeks after demand of such drawings no claim of delay shall be made

3 (THREE)
1.00 3 copies of shop drawings for architect approval by contractor for corrections, changes and variations
2.00 3 sets of CD by the Owner for Contractor
3.00 2 weeks after demand of such drawings no claim of delay shall be made
4.00 3 sets of As-built drawings + Original submitted by the Contractor before Final Payment
5.00 3 copies of diretory of Panel Boards (+list of circuits, submitted by the Contractor before Final Payment
instruction & manual of fixtures & equipment, keying
schedule)
6.00 3 monts after the date of Final Payment Release of Retention
7.00 3 years Renewal of license
5 (FIVE)
1.00 5 days "means immendiate"
2.00 5 copies of CD to be signed by the Owner
1 - office of the building official
1 - contractor
1 - owner
1 - fire department
1 - site
7 (SEVEN)
1.00 7th day Contract Time starts on the ____day upon receipt of NTP
10 (TEN)
1.00 10 days before beginning, suspending resuming work Contractor must notify Architect
2.00 10 days before they are needed Contractor writes request for supply of Owner-supplied materials
3.00 10 days notice to the Owner if the Insurance Company intends to cancel Insurance policy: Contract Liability
Insurance
4.00 10 days notice must be submitted for extension of work to avoid liquidated damages
15 (FIFTEEN)
1.00 15 years Liability
2.00 15 days written notice to the Owner & Architect If contractor will suspend / terminate work
3.00 15 days the period that the architect failed to act upon Work will be suspended by Contractor
Request for Payment by Contractor
4.00 15 days after certification of Architect Owner failes to act upon Request of Payment: work willl be suspended by Contractor
5.00 15% of Contract Amount Contractor's Performance Bond: Released after 2 months from acceptance of Work and after
submission of Guarantee Bond
6.00 15% of Contract Price Contractor's Payment Bond: Released after 2 months from acceptance of Work and after submission
of Guarantee Bond
7.00 15 days from receipt of NTP Submit Contract Sum Breakdown
8.00 15 days of duration notice to the architect for the claim for extra cost
9.00 15 days from the receipt of request for payment architect must act on payment request
10.00 15 days from the date of Approval of Architect of payment owner must act on payment request
request
11.00 15 days after written notice by the owner Correction after final payment
12.00 15 days after parties have presented evidences If architect fails to render a decision within such duration, both parties will demand arbitration

30 (THIRTY)
30% of Contract Price the guarantee bond to be given before final payment equivalent to one year from the Final
Acceptance of Work
30 days after the award of a sum by arbitration Owner fail to pay contractor the sum: Work will be suspended by Contractor
60 (SIXTY)
Up to 60 calendar days Period of rectification of defects and faults; will be at the contractor's expense; but if fault is non-
contractor, it will be shouldered by the Architect