engineering
CE400
Student No:20103045
Date: 14/10/2009
TABLE OF CONTENTS
1-INTRODUCTION
.1
2-COMPANY profile.
.. 2
3-EXCAVATION
.. 3-4
4-CONCRETE
... 5
5-REINFORCEMENT
..6-7
6-FORMWORK
.8-11
7-FOUNDATION
..12-14
8-COULUMNS
15-16
9-BEAMS
.17-18
10-STAIRS
.19
11-
SLABS ...................................................
.......20-21
12-CONCLUSION
22-23
INTRODUCTION
Civil engineering department offer a unique opportunity
for its student to realize the importance of field work by
offering two important courses for undergraduate students
which are CE-300 and CE-400. These are the summer
trainings compromising of 1 month each. CE-300 is the
initial step or the first training.
It is important to perform this summer practice to be able
to understand the relation between the studies and the
field. This will help us a lot in better understanding of the
future subjects in our undergraduate studies.
During the summer practice students get an idea of the actual
constructions steps undertaken by the contractors. E.g.
excavation, foundations, columns, beams, slabs and walls etc.
1
COMPANY INFORMATION
NAME OF COMPANY:
M/S MOON BUILDER
ADDRESS OF COMPANY:
11-NASHAMAN PARK HOUSING
COLONY SHEIKHUPURA
CONTACT INFORMATION:
TEL-0092336-7193608
ENGINEER:
ALI ZAIN
EXCAVATION
2
To get optimum result from the excavation, cleaning &
marking of the construction site is an important step. After
these steps excavation is started either with the help of
machinery or with the help of labors (depending on the
size of the construction).
Each construction has a different quantity of
excavation, which is done to construct the structure
foundations.
In general there are two types of excavations:
- Trench excavation.
- Bulk-pit excavation.
Trench excavation is used for wall footing.
Bulk-pit excavation is used for the basement of the
buildings and also for raft foundations.
CONCRETE
Concrete is composed of sand and gravel held
together by a hardened paste of Portland, cement and
4
water. The mixed ingredients when properly proportioned
make a plastic mass, which can be or molded into a
predetermined size and shape. Water is necessary for the
chemical reaction of cement and the extra water is
necessary for workability of the mixture.
REINFORCEMENT
6
FORMWORK
7
20% is found satisfactory for timber to be used in
formwork
1. Column formwork:
8
Column formwork is made usually with either
timber or metal panels. The principle is to create an
enclosed box with forms at the exact size of the column
and fix it tightly. On the kicker left from base or at least
stage of column concreting. The box is held in position by
steel column clamps or bolted yokes and supported by
timber studs or props.
2. Beam formwork:
Beam formwork consists of an open through section
and because it is not closed at the top requires more
supported formwork to restrain the side. The supports
need to be maintained to the so fit and also provide lateral
supports to the side. In timber this is done by the use of a
head tree across the top of a vertical member.
metal banal are used with corner pieces and can be
supported by tabular steel to which panels are clipped, but
timber head trees are needed for vertical support.
9
3. Slab formwork:
Floor requires a large area of formwork to be
provided usually from beam to beam. Mostly beam are
cast at the same time as the floor.
Timber floor formwork consists of timber board or
plywood sheet supported on a frame-work and resting on
a series of timber joists. Again timber and metal props can
be used for vertical supported.
Metal panels can be used and bolted or clipped together
and held in place by a system of metal beams or a tabular
scaffold system. Again timbre adjustable props need for
levelling purposes.
4. Wall formwork:
Wall form is simpler than for to other concrete unit as
the actual forces against it less, most of the load being
carried vertically down words the panels at both sides is
held in position by ties.
The type of ties are coil ties or through bolt ties.
10
FOUNDATION
11
as nearly as possible to limit settlement as indicate it is
necessary (1) to transmit the load of the structure to soil
stratum of sufficient large area of that stratum to minimize
banning pressure.
1. Spread footing:
Spread footing can be classified as wall and column
footing. A wall footing is simply a strip of reinforced
concrete, wider than the wall that distributes its pressure.
Single column footings are usually square, sometimes
rectangular, and represent the simplest and the most
economical type.
2. Wall footing:
12
footing with the formwork on it. If the bending moments
were computed from the forces acting below the footing,
the maximum moment would be found to accrue at the
middle of the width. For footing supporting masonry
walls, the maximum moment is computed midway
between the middle and the face of the wall, because
masonry is generally less rigid than concrete.
3. Column footing:
In plane single column footing are usually square.
Rectangular footings are used if space restrictions dictate
this choice.
In the simplest form, they consist of a single slab as
shown; sometimes we make this foundation directly
inside the ground and other type in side formwork. The
weight of the footing dose not causes moments or shears.
4. Combined footings:
Spread footings that support more than one column or
13
wall are known as combined footings. They can be
divided into categories: those that support two columns
and those that support more than (generally large number
of) columns.
COLUMNS
14
surrounding concrete.
To avoid this, circumferential or lateral reinforcements
called stirrups were used to form ties.
The distance between ties formed by stirrup can change
from 15 cm to 30 cm according to the project.
15
Stirrups can make the column more ductile. Column
gains additional energy absorption capacity, this may be
by means of stirrups. For this reason, stirrups play very
important role in concrete columns.
Length of the longitudinal bars exceeded the column
length about 80 cm to tie the upper floor column bars.
BEAMS
In beams, bent-up bars are used to provide resistance
to bending and shearing. They have much more important
voter in the changing place of compression and tension
region.
Concrete resists compression stresses and steel bars
resists tension ones. Of course, concrete has a tension
stresses and steel bar have compression strength but it is
to be saved side not to consider these strengths. Thats
why main steel bars are placed at the bottom of the
beams. Stirrups resist to shearing with bent- up bars in
16
beams. Above the column, beam structures continue. At
this part, there were no stirrups I columns. Number of
bent-up bars and their diameter are calculated according
to the reinforcement data.
Two stirrups bench were placed opposite to each other
according to the length of the beam. Tie bars were placed
on bench. Their books were turned down. Inside the
stirrups straight bars with up turned hooks were laid.
Bent-up bars were tied to stirrups.
17
STAIRS
18
constructed but the construction is affected by the right
choice of materials that plays a very important role,
because the shape and the structure of a stair must be
compatible with the materials and placing of the stair.
SLABS
20
CONCLUSION
Firstly I was thinking about the summer practice as a
secondary formality but when I performed it I realized its
importance. It also aided to understand the courses which
I have covered and also those which I have to take. In the
university the student generally takes a significant amount
of knowledge about the Civil Engineering, but progress is
not put into application until practical life takes place.
Thus summer practice is a good opportunity to be in
contact with the site works, theoretical-practical
differences and the workers-engineers relationship.
I have learned a lot of things like some technical details
in specialized construction works, relation with engineers,
directors and workers, administration and coordination of
21
a company and preliminary works which are done before
construction.
22