Anda di halaman 1dari 6

2013 3rd International Conference on Electric Power and Energy Conversion Systems, Yildiz Teclmical University, Istanbul, Turkey,

October 2-4,2013

Sensitivity Analysis for the IEEE 30 Bus System


using Load-Flow Studies

Ibrahem Totonchi, Hussain Al Akash, Abdelhadi Al Akash and Ayman Faza


Ibrahem tot@yahoo.com, h-u-s-s-a-i-n-@hotmail.com, Abdelhadi.akash@students.psut.edu.jo, a.faza@psut.edu.jo.
King Abdullah II School for Electrical Engineering
Princess Sumaya University for Technology
Amman-Jordan

Abstract- Load flow analysis is the backbone of the power to improve the reliability of the IEEE30 bus system, and
system studies and design, and through it the voltage magnitude further generalize it to any other power system, using
and phase angle at each bus and the complex power flowing in methodologies such as capacity planning, the use flow control
each transmission line can be obtained. In this paper, we use the
devices such as FACTS devices, and the use of distributed
load-flow to perform a sensitivity analysis of the IEEE 30 bus
generation (DG) methods, including renewable energy
system. We find the maximum complex power flowing in each
transmission line in case of no fault and in case of a single
methods such as solar and wind to gradually convert the
transmission line fault in the steady state condition. The results of power system from a radially connected network to a meshed
this analysis helps identify the most critical lines in the system, network with generation occurring at both sides of the system.
which can help better plan the capacities of such lines, and Some of the suggestions that we will present at the end of
minimize the probability of potential cascading failures. this paper will include raising the capacities of some of the
transmission lines in the system. Raising the capacity of all the
Keywords: load flow; reliability; sensitivity anal ysis; cascading transmissions lines in the system may not be very efficient or
failures
may be a bit hard to accomplish, but we could raise the
capacity of some critical transmission lines to minimize the
I. INTRODUCTION occurrence of cascading failure. The main contribution in this
Capacity planning for power systems is very important to paper is to determine the most critical transmission lines in
ensure proper and reliable operation of the grid. Proper the IEEE 30 bus system, whose failure can have catastrophic
planning ensures that a system is capable of generating, effect on the system. We further provide suggestions on how to
transmitting and delivering electric power to everyone, improve the operation ofthe grid by providing suggestions on
without interruption. However, it is also desirable that the improving the operation of such lines. Those critical
system be capable of providing those services when one or transmission lines will be revealed after studying the results
more lines in the system have failed. obtained from the load flow analysis.
Many of the failures that randomly occur in a transmission The rest of the paper is organized as follows. Section II
line can have a catastrophic effect. A failure of one line forces provides a literature review of the studies performed on the
the flow of power to be rerouted through the other lines in the IEEE30 bus system, in addition to other relevant studies.
system, potentially causing some of them to overload, in order Section III presents the IEEE 30 bus system in more details.
to compensate for the loss of the initial line. The overloads Section IV introduces the load flow analysis and the initial
that occur in the other transmission lines cause them to be results obtained in a fault free system. Section V presents the
disconnected from the system by the action of the protective sensitivity analysis performed and shows the results, and also
devices. This in turn can cause similar overloads and presents a few examples of cascading failures that can occur in
disconnections in other lines in the system in a cascading the system. Section VI concludes the paper and provides a
fashion, eventually leading to a system blackout. vision of the expected future work in this project.
In this paper, we present a sensitivity analysis of the IEEE
30 bus system, which aims to reduce the probability of a
II. LITERATURE REVIEW
cascading effect in the system. In order to do that, we perform
a load flow analysis on the initial fault free system, and
additionally perform a similar analysis when at least one Many studies has been conducted on the IEEE 30 bus
transmission line has failed, enumerating all the possible system tackling various subjects. In this section we present a
cases. The goal of this study is to find the worst case flow number of such studies that are relevant to this work. The
scenario; that is, the maximum flow in the system's remaining authors of [2] present a basic load flow analysis, which aims
transmission lines, for each transmission line failure, and look to find the converged bus voltages using both the Gauss-Siedel
for potential cascading failures in the system. The overarching and Newton-Raphson methods and compare the two numerical
objective of this work is to develop ideas and methodologies methods in terms of complexity and convergence rate among

978-1-4799-0688-8/13/$31.00 2013 IEEE


2013 3rd International Conference on Electric Power and Energy Conversion Systems, Yildiz Teclmical University, Istanbul, Turkey, October 2-4,2013

others. In another study [3], the Total Transfer Capability collapse prediction problem for interconnected power systems
(TTC) and Available Transfer Capability (ATC) have been which is a steady state analysis applied to study the voltage
studied [3] which give a general feeling of the amount of collapse problems. In this paper, a modal analysis method is
complex power generated into the system. According to the used to investigate the stability of the power system. Q-V
authors, with the recent trend towards deregulating power curves are used to confirm the obtained results and to predict
systems around the world, transfer capability computation the stability margin or distance to voltage collapse based on
emerges as the key issue to a smoothly running power market reactive power load demand. The analysis in this paper is
with multiple transactions. A key concept in the restructuring performed for three well-known systems; the Western System
of the electric power industry is the ability to accurately and Coordinating Council (WSCC) 3-Machines, 9-Bus system, the
rapidly quantify the capabilities of the transmission system. IEEE14 Bus system, and the IEEE30-bus system.
Total Transfer Capability (TTC) is defmed as the amount of Our work is different from these studies in that it focuses on
electric power that can be transferred over the interconnected understanding the effect of a single transmission line failure
transmission network in a reliable manner while meeting all of on the overall operation of the system. We study the
a specific set of defmed pre- and post-contingency system sensitivity of the system to the occurrence of a single line
conditions. Available Transfer Capability (ATC) is a measure fault, and provide a capacity planning method for such a
of the transfer capability remaining in the physical scenario. In addition, we explore the notion of a cascading
transmission network for further commercial activity over and failure in the IEEE 30 bus system, in preparation of a further
above already committed uses. In [3], MATLAB software is investigation into methods to mitigate such failures and reduce
used to determine the TTC of power transfers between the probability of their occurrence.
different control areas in deregulated power systems without
violating system constraints such as thermal, voltage, and III. LOAD FLOW AND THE IEEE 30 BUS SYSTEM
stability constraints. The main aim of the paper is to calculate The IEEE 30 bus system consists of 30 buses, 41
total transfer capability and capacity benefit margin of IEEE transmission lines and a number of transformers and
3D-bus Reliability Test System (RTS) for calculation of ATe. synchronous condensers. It represents a portion of the
In another project [4], the authors study the performance of American electrical power system in the Midwest region.
indirectly controlled STATCOM; a Flexible AC Transmission Figure 1 below depicts the system. The bus generation and
System (FACTS) device primarily used for reactive power loads data were obtained from [6].
compensation and improvement of voltage profile in the For the analysis of this paper, we performed load flow for
system, is used with IEEE 3D-bus system. In this article a the IEEE30 bus system using the Gauss-Seidel method. The
Cascade Multilevel Inverter (CMU) based on the indirectly load flow was performed for the initial case where all
controlled STATCOM has been placed in IEEE30-bus system transmission lines are functioning in the system. Additionally,
for its performance evaluation in regulating the voltages of we run load flow after removing one transmission line at a
different buses. Other studies such as [5] tackled the voltage time for the total of 41 transmission lines, and we documented

Figure 1 - The IEEE 30 Bus System


2013 3rd International Conference on Electric Power and Energy Conversion Systems, Yildiz Teclmical University, Istanbul, Turkey, October 2-4,2013

the results. The main purpose of this study was to determine


Pisch
the worst case flow values in each transmission line in the
system, when one line fails; that is a sensitivity analysis of the
IEEE30 bus system to a failure in a single transmission line. In Pid
addition, if we know the line capacities in the IEEE30 bus
system, we can simulate the effect of cascading failures, by
taking out the lines that overload when a single line failure Qiisch
occurs, and repeating the process. To run the simulations, we
used a MATLAB based load flow simulator, and we simulated
a total of 41 failure cases, in addition to the case were all lines Oid

are working. In the following section, we present the results of -t- Vi L0


the load flow analysis and further discuss their implications.
Figure 2 - A Snapshot of Bus i and its Parameters.

IV. LOAD FLOW ANALYSIS RESULTS 2) Constructing the Admittance Matrix(the Y-bus Matrix)
The second important step in performing the load flow is to
1) The Load Flow Problem [IJ
construct the Y-bus matrix. The Y-bus matrix is an
The load flow problem or the power flow problem is the
N X N matrix, where N is the total number of buses, and it
computation of voltage magnitude and phase angle at each bus
in a power system under balanced three-phase steady state can generally be constructed by inspection, by systematically
conditions. evaluating its parameters based on the transmission line data
As a byproduct of this calculation, real and reactive power given in the problem. In general, and entry in the matrix at
flows in equipment such as transmission lines and row i and column j; / is equal to the negative sum of the
transformers, as well as equipment losses, can be computed. parallel admittances connected between buses i and j. The
The starting point for a power-flow problem is a single line
diagram of the power system, from which the input data for
diagonal elements; i is the sum of the admittances connected
computer solutions can be obtained. Input data consist of bus to bus i, regardless of which bus the other side of the
voltage, real and reactive power generated, and real and admittance is connected to . With that in mind, finding all the
reactive power demand at each bus, in addition to the elements in the Y-bus matrix becomes straightforward.
transmission line parameters.
As shown in Figure 2, for any bus i the following eight After constructing the v-bus matrix, and using the Gauss
variables are associated with each bus; Seidel method, the voltage at each bus can be found by
iteratively solving the following equations:
: The voltage at bus i
8i The phase angle at bus i,
: For a load bus, the kth iteration of the voltage at bus i can be
found as follows:
g : The generated real power
Q gi : The generated reactive power V(k) = [ V*(k-I)
SCh- jQ\ch
..

Y
I
d : The real power demand It l
Qd : The reactive power demand (3)
From these parameters, the scheduled real and reactive powers
For a generator bus, we first need to get an estimate of
are calculated as follows:
Q to be used in place of Qsch . We use the following

sch g - d (1) equation:

Q(k) = {V*Ck-l) [-l V(k)


=

Q,ch Qg - Qd (2)
=
1
_ 1m
I
11=1
Y
111 1
+ . Y

n=1
111
V(k-I)]}
1
(4)

Depending on the type of bus; slack, generator, or load Then the voltage at bus I can be found by using a modified
bus, the known variables and the unknown could be anything version of equation (3) as follows:
among the voltage magnitude, the voltage angle, and the real
power generated, and the reactive power generated.
V(k) = [ V*(k-IQ) Ck) ( VCk)
I
_
1
..

Y"
Plsch- J

I
I

n=1
Y
m n
+ "N Y
. m
.
n=z+1
VCk-l) Jl
n

(5)
2013 3rd International Conference on Electric Power and Energy Conversion Systems, Yildiz Teclmical University, Istanbul, Turkey, October 2-4,2013

3.Results o{The Load Flow Analysis, for a normally is the currents carried by the transmission line connecting bus
running system with no failures. i and bus j.
Running the load flow simulation for the normal fault free Given the previous analysis, we removed one line from the
IEEE 30 bus system resulted in the following bus voltage system at a time, and found the amount of power flow in each
results as shown in Table 1. Simulation was performed using transmission line. Then we took the maximum power flow in
Matlab and the results were confirmed using the Power World each line that could occur due to the failure of one
Simulator (PWS). The simulation parameters were set such transmission line. The results of this simulation are
that the error tolerance in the voltage was set to 0.01 per unit. documented in Table 2 below.

Table 1 - Load Flow Results for the Fault-Free IEEE118 Bus Table 2 - Maximum Power Flow in Each Transmission Line,
System Due to a Single Transmission Line Failure
Bus Voltage Bus Voltage TL TL Max TL TL Max
number (from Flow number (from Flow
1 1.06LO 2 1.04L-5Z bus to bus to
3 1.03L-7.4 4 1.02L-9T bus) bus)
1 1-2 2.6428 22 15-18 0.1582
5 1.0 1L- 1 3X 6 1.02L- 1 0X
2 1-3 2.9309 23 18-19 0.1221
7 LOlL- 1 2.6 8 1.01L- 1 1.3 3 2-4 0.8224 24 19-20 0.1726
9 1.04L- 1 3.So 10 1.03L-15.4 4 3-4 2.7255 25 10-20 0.1986
5 2-5 1.2383 26 10-17 0.2585
11 1.0SL- 1 3X 12 1.04L- 1 4.T
6 2-6 0.9997 27 10-21 0.2653
13 1.07L- 1 4.T 14 1.02L- 15.6 7 4-6 1.7064 28 10-22 0.2412
15 1.02L- 15.T 16 1.03L- 15.3 8 5-7 1.0603 29 21-22 0.2034
9 6-7 1.2994 30 15-23 0.1215
17 1.02L- 15S 18 1.01L- 16.3 10 6-8 0.3160 31 22-24 0.2099
19 LOlL-16.4 20 1.0 1L- 16Z 11 6-9 0.5078 32 23-24 0.1103
12 6-10 0.2810 33 24-25 0.1940
21 1.02L- 15X 22 1.02L- 15X
13 9-11 0.1771 34 25-26 0.0428
23 1.0 1 L-16 24 1.00L- 16Z 14 9-10 0.4983 35 25-27 0.1415
25 1.00L- 15.So 26 O.9SL- 16Z 15 4-12 0.6202 36 27-28 0.2480
16 12-13 0.3310 37 27-29 0.1443
27 1.00L-15.3 28 1.02L- 1 1.4
17 12-14 0.1714 38 27-30 0.1424
29 O.9SL- 16S 30 O.97L- 17S 18 12-15 0.2579 39 29-30 0.1122
19 12-16 0.1584 40 8-28 0.3083
The system needed 123 iterations to converge. Note that all 20 14-15 0.1029 41 6-28 0.4734
the above values are in per unit with 1OOMV A base complex 21 16-17 0.1779
power.
Note that the above values are in per unit with 1OOMV A base
V. SENSITIVITY ANALYSIS AND THE CASCADING FAILURE
complex power.
EXAMPLES
For the sensitivity analysis the resultant maximum
1) The Sensitivity Analysis complex power flowing in each transmission line was caused
by removing or a failure in a specific transmission line. For
The main purpose of the sensitivity analysis in this paper, is example, the maximum power flowing in transmission lines
to determine the worst case scenario that could occur due to number 2, 4, 7 and 10 is caused by failure in transmission line
the failure of one transmission line. To do that, we obtain the number 1, and the maximum power flowing in transmission
maximum complex power going through each transmission lines number 11, 12, 14, 16, 21, 24, 25, 26, 32 and 36 is
lines in the case of no faults and in case of a one transmission caused by the failure in transmission line number 15. In
line fault. This is performed for all 41 transmission lines. addition, the maximum power flowing in transmission lines
The complex power between bus i and bus j can be found as number 27, 30, 31, 33, 34 and 35 is caused by the failure in
follows: transmission line number 36.
It is obvious from this analysis that transmission line 1, 15

Slj = VJ,; (6) and 36 are the most critical lines in the grid; therefore, raising
the capacity of those three lines only we can help reduce or the
Where, number of cascading failures (to be explained in the following
section) that can occur in the system.
2013 3rd International Conference on Electric Power and Energy Conversion Systems, Yildiz Teclmical University, Istanbul, Turkey, October 2-4,2013

2) Cascading Failure Examples Table 3 - Transmission Line Failures, and Worst Case
In addition to the sensitivity analysis presented above, it is of Scenarios
great value to try and discover potential cascading failures in TL in which Initial failure TL at which maximum power
the system. A cascading failure occurs when the failure of one occurs flows due to this failure
transmission line causes the other lines to overload, which in 2 1
turn causes these overloaded lines to be disconnected from the 3 4
system using protective devices, which then causes further 9 5
overloads and failures leading eventually to a complete system 5 6, 8, 9
blackout. 11 13
To simulate cascading failures, we set the capacity of each 18 17, 20
transmission line to 120% of the rated complex power value 7 15, 18, 19
flowing in the line, which was obtained from the initial case of 25 22, 23
no transmission line failures presented in Section IV above.
27 28, 29
We analyzed three interesting cascading failure cases in
38 37, 39
this system.
37 38
In the first case, we remove transmission line number 1
10 40, 41
which connects bus I and bus 2. This will cause an overload at
transmission lines 2, 3, 4, 7, 8, 9, 15, 16, 19, 20, 21, 22, 23, 30
and 32. The failure of these transmission lines causes an VI. COCLUSION AND FUTURE WORK
overload at lines 5, 6, 13, 14, 26, 27, 29, 31, 33 and 35, and
Power flow or load-flow studies are important for planning
after that all of these failures cause an over load at
future expansion of power systems as well as in determining
transmission lines 26, 25, 15, 14, 13 and 12, eventually
the best operation of existing systems. The principal
leading to a total blackout.
In the second case, we remove transmission line number 8. information obtained from the power flow study is the
magnitude and phase angle of the voltage at each bus, and the
This will cause a failure in transmission line number 5 and
real and reactive power flowing in each line. We performed a
those two failures will then isolate bus number 5 with bus
sensitivity analysis which aims to have a general feeling of the
voltage magnitude and angle of O .
I n the third case, w e remove transmission line number 39, system by finding the maximum complex power flowing in
which will cause an overload and then failure in transmission each transmission line in the case of no faults and in the case
line number 38, then that will cause an overload at of one transmission line fault in the steady state condition.
Results show that a few of the lines are significantly more
transmission lines number 40, 35, 33, and 29. In this case bus
critical than the others when it comes to their failure. Our
number 30 will be isolated (islanding) with no power flowing
study helped us identify the lines that are most critical to the
towards it.
operation of the system, which can help better plan for their
capacities to reduce the effects of failures in the system, and
3) Further Analysis
decrease the probability of occurrence of a cascading failure.
In addition to the previous analysis, we have two buses in
Future work in this project will include implementing
the system which generate real power; that is bus number 1
methods to improve the reliability of the system by using
and 2 with four transmission lines connecting them to the rest
intelligent devices such as FACTS devices, in addition to
of the system; transmission lines number 3, 5, 6 and 8. This
implementing distributed generation and renewable energy
shows that these lines can be considered critical transmission
sources into the grid. Our objective is to make the grid more
lines and raising their power capacity would help improve the
intelligent, and convert the traditional IEEE 30 bus system
system's reliability and reduce the possibility of system
from the conventional radial scheme to a more intelligent
blackouts.
meshed network as we gradually move the existing power
The rest of the transmission line failure effects can be
systems from the conventional power grid to the more
summarized in Table 3 below.
advanced Smart Grid.
Table III shows the effect of a failure in each line, and
specifies which transmission line gets the maximum amount REFERENCES
of flow due to this failure.
[I] Duncan. G, Mulukutla. S and Thomas.O, "Power flows"
The results shown in Table III above help grasp the cause in "Power Svstem Analvsis And Desi!m" :)th
effect scenarios for transmission lien failures, which can Ed. Stanford, California, USA, Cengage Learning 2008,
further help us in better planning for the line capacities in the Ch6.
IEEE 30 bus system. [2] Dharamiit and D.K.Tanti. "Load Flow Analvsis on TRER
30 hus Svstem" . International .Journal of Scientific and
R ese arch Publications, Vol 2, No 11, ISSN 2250-3153,
2012.
[3] Priti.K, and Paladurkra. M, "TTC and CBM Calculation
of TERF-30 Hils Svstem". Washin!>ton DC lJSA. Tn
Proceedings of the 2009 Second International Conference
2013 3rd International Conference on Electric Power and Energy Conversion Systems, Yildiz Teclmical University, Istanbul, Turkey, October 2-4,2013

on Emerging Trends in Engineering & Technology [5] Amer. H. Thesis "VoJtm:re Collanse Prediction for
[CETET '09. Tnterconnected Power Systems", West Virginia
[4] Jagdish Kumar, "Performance of Indirectlv Controlled University, (2000).
STATCOM with IEEE 30-hus Svstem". International [6] Power Svstems Test Case Archive. llniversitiv of
Journal of Advanced Electrical and Electronics Washington. Website:
Engineering (IJAEEE) [SSN 2278-8948, Vol. 1, No. 2, http://www.ee.washington.edulresearch/pstca
2012

Anda mungkin juga menyukai