Introduction to Tangguh
Conclusions
2
IAFMI 2015
Introduction to Tangguh
Introduction to Tangguh
Location
4
Introduction to Tangguh
5
Introduction to Tangguh
Offshore
Vorwata field: 14 wells
2 identical platforms (NUIs)
2 sub-sea, 24 pipelines
6
Introduction to Tangguh
Onshore facilities
7
Introduction to Tangguh
Onshore process
8
Introduction to Tangguh
Heat integration
9
Introduction to Tangguh
10
IAFMI 2015
Benefits include:
Lower fuel consumption (hence more gas available for liquefaction & export)
Fewer, larger GTs, all running at base load & optimum efficiency, compared to
conventional gas turbine power station which has part-loaded turbines
Reduced air emissions (combustion CO2, NOx, particulates)
Lower site footprint, reduced power balance & less electrical infrastructure, all
contribute to reduced capital cost
Lower maintenance burden (due to fewer maintenance-intensive gas turbines)
as well as lower fuel use, contribute to reduced operating cost
12
Efficient liquefaction the benefits
4.38 MMBtu per tonne LNG exported achieved during 24hr performance test
(equivalent to 0.23 tonne CO2 from combustion gas per tonne LNG)
Similar average performance, in normal operation over longer period
13
IAFMI 2015
Project development:
Traditional concept can largely be engineered sequentially:
Integrated concept has greater degree of recycle and redesign, for example:
electrical load list impacts steam balance
steam balance impacts train power available and operability
steam system dynamics can cause process transients
process controls need to manage process and utility integration
These design iterations impact project schedule
15
Efficient liquefaction the challenges
16
Efficient liquefaction the challenges
Operation:
High integration gives the potential for increased common-mode failures
However, our experience is that plant stability & trip response are similar to open-
cycle LNG design, thanks to control system design and features such as electrical
load shedding to mitigate trip escalation
Load management of the refrigeration compression strings is complex, and
control systems are designed to manage the transient impacts of integrated
design
e.g. compressor trip to recycle demands rapid HP steam increase to maintain
speed, simultaneous with decreased LP steam demand from the AGRU
Greater coordination between LNG process & utility operations team required
17
IAFMI 2015
Conclusions
Conclusions
19
IAFMI 2015