LV CABLE INSPECTION AND TEST PLAN

PROJECT NAME: PROJECT NO: ITP NO: REV:


APPROVALS ERGON ENERGY CUSTOMER
NAME
SIGNATURE
DATE
LEGEND: A = Action; H = Hold; W = Witness, V = Verify, N/A = not required Delete or add items as required to comply with scope of works

ITEM ITEM ACCEPTANCE VERIFYING ACTION / INSPECTION REQUIREMENT


NO. DESCRIPTION CRITERIA DOCUMENT Code By who? Comment
1 Core Continuity Minimum variation SP0405C01 A Secondary Systems
between phases
2 Insulation Resistance (IR) > 100 M, (new) SP0405C01 A Secondary Systems
> 1 M, (aged)
3 Sheath Integrity (SI) > 10 M SP0405C01 A Secondary Systems
4 MEN 1 (CMEN) SP0405C01 A Secondary Systems
10 (MEN) or as
allowed by ESO Code
5 Voltage Check +/- 6% of nominal SP0405C01 A Secondary Systems
6 Phase Check ABC SP0405C01 A Secondary Systems
7 Pre-commissioning checklist All items completed as SP0405C01 A Secondary Systems
per design specification

Plant Verification by Commissioning Officer of Satisfactory Completion (sign off)


Description/ Comment
Bay Number 1. Continuity 2. IR 3. SI 4.MEN 5. Voltage 6. Phasing 7. Checklist

Check this is the latest version before use. Page 1 of 1 Form SP0405C03 Ver 2
Form Owner: Mark Carroll, Manager Technical Standards
Ergon Energy Corporation Limited ABN 50 087 646 062