Anda di halaman 1dari 1

ID Task Task Name Duration Start Finish Predecessors

Qtr 1, 2017 Qtr 2, 2017 Qtr 3, 2017


Mode Jan Feb Mar Apr May Jun Jul Aug
0 RUMAH TIPE 100/99 153 daysWed 01-02-17 Sat 29-07-17
1 Pekerjaan Persiapan 148 daysTue 07-02-17 Sat 29-07-17
8 Pekerjaan Pondasi 12 days Wed 15-02-17 Tue 28-02-17
17 Pekerjaan Beton 87 days Wed 01-03-17 Sat 10-06-17
23 Pekerjaan Dinding Batu Bata 19 days Wed 26-04-17 Wed 17-05-17
26 Pekerjaan Atap 10 days Mon 12-06-17 Thu 22-06-17
30 Pekerjaan Pintu dan Jendela 4 days Mon 10-07-17 Thu 13-07-17
35 Pekerjaan Lantai 79 days Wed 26-04-17 Wed 26-07-17
42 Pekerjaan Kamar Mandi/ WC 11 days Thu 11-05-17 Tue 23-05-17
48 Pekerjaan M/E 96 days Wed 01-02-17 Wed 24-05-17
56 Pekerjaan Plafond 7 days Thu 22-06-17 Thu 29-06-17
60 Pekerjaan Finishing 63 days Thu 18-05-17 Sat 29-07-17

Page 1

Anda mungkin juga menyukai