F r o m : L a r r y L a M o n t a g n e p a r r y. l a m o n t a g n e @ s c m . c a ]
S e n t : M o n d a y, D e c e m b e r 0 6 , 2 0 1 0 9 : 2 3 A M
To : 'Ralph Herten'
Cc: 'Andy Tallentlre'; Chris Beaton; Roy Patzer; Robert Gagnon; pmanley@jltcanada.com;
shu@msexch.jltcanada.com; mjang@jltcanada.com; Dan Bock; 'Martijn Lunneker'; 'Lome
Ebenal'
Subject: RE: BC Place Crane - Dropped Cable Net Incident
Thanks Ralph,
Please let me know when more information is available. A preliminary rough estimate would also be
appreciated ASAP.
Cheers,
Larry LaMontagne, FCIP
Director-Commercial Claims
ClaimsPro (An SCM Company)
Tel. (604) 609-4116 Direct
Fax. (604) 662-8105
Original Message
From: Ralph Herten irmailto:RHerten@pcl.com1
Sent: 2010-12-06 9:18 AM
To: Larry Lamontagne
Cc: Andy Tallentire; CBeaton@bcpavco.com: RPatzer@bcpavco.com: RGagnon@bcpavco.com;
pmanlev@iltcanada.com; shu@msexch.iltcanada.com: mianq@iltcanada.com;
DBock@bcpavco.com: Martijn Lunneker; Lome Ebenal
Subject: RE: BC PLace Crane - Dropped Cable Net Incident
Larry,
Further to our discussion today, and as per your request, we are forwarding a plan and a photo of
typical cablenets. The photo shows one cablenet installed and another in the process of being
installed.
Our preliminary investigation is pointing towards a failure of the rigging during the installation of one
of the cablenets. There was some resultant damage to the components of the cablenet (cables and
castings) and also to the bleacher area below.
The incident is still under investigation and we expect to have more information in the next few days.
Regards,
Original Message
From: miana@iltcanada.com fmailto:mianq@iltcanada.com1
Sent: Sunday, December 05, 2010 11:19 AM
To: DBock@bcpavco.com: mianq@iltcanada.com
Cc: Andy Tallentire; Ralph Herten; CBeaton@bcpavco.com: RPatzer@bcpavco.com:
RGaqnon@bcpavco.com: pmanlev@iltcanada.com: shu@msexch.iltcanada.com
Subject: RE: BC PLace Crane - Dropped Cable Net Incident
Hi Dan,
Further to our conversation of just now, I will advise our claims department and Larry of the new
claims. It sounds to me like the majority of the damage is to the new COC materials with some minor
damage to the existing structure. We will report this into the insurers. In the meantime, please
continue to update us with any additional information that you receive on this.
Thanks,
Monica
Original Message
From: Dan Bock rmailto:DBock@bcpavco.com]
Hi Monica i pass along this notification at PCL's suggestion. Pavco has very little information on the
event at the current time. Here is what we know at this time. During the erection process late friday
afternoon a cable net fell from a crane connection. I dont believe there was any personal injuries
There was some minor damage to existing stadium. I understand from PCL's attached email that the
cable net itself was damaged and some components will require replacement.
I will discuss claim notification protocol with PCL. I suggest JLT's claims department contact Ralph
Herten at PCL for details on this claim.
Ralphs phone number is 604 673-4306.
The contents of this e-mail as received may not be a complete or accurate version of that sent. If you
consider that the contents are material to the formation of
a contract or you are otherwise relying upon its accuracy, you may wish to request a copy be sent by
facsimile or normal mail. The information in this e-mail is
confidential and may be privileged. If you are not the intended recipient, please
destroy this e-mail and notify the sender immediately - you should not retain, copy, distribute or use
this e-mail for any purpose, nor disclose any of its contents to
Page 18 of 96
Steve Lingenfelter
From: mjang@jltcanada.com
S e n t : Tu e s d a y, D e c e m b e r 0 7 , 2 0 1 0 11 : 2 6 A M
To : Dan Bock
Cc: atallentire@pcl.com; RHerten@pcl.com; Chris Beaton; Roy Patzer; Robert Gagnon;
pmanley@jltcanada.com; shu@msexch.jltcanada.com; mmcwilliams@msexch.jltcanada.com;
lany.lamontagne@scm.ca; mjang@jltcanada.com
Subject: BC PLace Crane - Dropped Cable Net Incident - Insurer Notification.
Hi Dan,
Further to our telecon of yesterday, this is to confirm that all COC and Wrap Up insurers have been
notified of the loss and acknowledged receipt of the report. As you can see, Larry is already working
on this with Ralph.
Please let us know if you have any questions and keep JLT informed of any further updates.
Many Thanks,
Monica
The contents of this e-mail as received may not be a complete or accurate version of that sent. If you
consider that the contents are material to the formation of
a contract or you are otherwise relying upon its accuracy, you may wish to request a copy be sent by
facsimile or normal mail. The information in this e-mail is
confidential and may be privileged, if you are not the intended recipient, please
destroy this e-mail and notify the sender immediately - you should not retain, copy, distribute or use
this e-mail for any purpose, nor disclose any of its contents to
Page 19 of 96
Steve Lingenfelter
Importance: High
We have requested Freyssinet to outline their plan for inspection of the elements on cable net R31 that was involved in
the incident last Friday.
Please review and provide any comments or concerns you may have.
We are currently focusing on the installation of R14 and are trying to get confirmation to install R15 after this. This will
hopefully buy us the necessary time to deal with R31.
The next cable net that needs to be installed after R14 and R15 will be R31. We cannot skip this one and continue with
R32 since we will not be able to make the pin connections at the node side at R31 at a later date.
Pins at the node can only be made in a pre-determined sequence because of space restrictions.
First priority would therefore be to get confirmation and approval to use elements from R06 and R24 to re-built cable
net R31.
As noted by Freyssinet the only elements that currently cannot be substituted are the A and B clamps.
Pending your comments on this proposal Freyssinet has therefore started inspection of these clamps.
Don't hesitate to ask for any information that you require in addition.
Regards,
This e-mail (including any attachments) is for the sole use of the intended recipient and may contain confidential information which may be protected by
legal privilege. If you are not the intended recipient, please immediately notify us by reply e-mail or by telephone 604-241-5200, delete this e-mail and
destroy any copies. Thank you.
File: 2200906-4:051000
Page 20 of 96
INSPECTION PROGRAM AND REPORT
NET 31 BC PLACE
FReyssineT
NET# R31
The purpose of this document is to present our inspection plan for the cable net R31 elements after
the lifting accident (Dec, 3rd 2010). It is organized in three parts.
1. Facts
In this first part we will present the position of the elements after the
accident and the elements available to get an understanding of the
situation
2. Analyze
This part details the possible damages we indentified and the inspections
that will be carried in order to control them.
3. Inspection documents
This will give a sample of each type of inspection record and the
instructions required to perform the inspections.
Pjyu21 uf90
96 p gg a6ed
96ot an
IE* #13N
xauissxaud
aovid oa T3N
NVld NOULDHdSNI
INSPECTION PLAN
NET 31 BC PLACE
FReyssmeT
NET# R31
Lower damps Lower 1 and 2 on ground, 3,4 and 5 on or near trolleys, not touching ground
Other damps hanging in the air
Page 23 of 96
BCP_FREYJRP_3006_A - Inspection plan for Net R31 jds
spc%eMieN-KyuB|duoipedsu|-v 900C ddl A3dd d09
96 jo ^ a6ed
juappu/ ajqjBg
ley #JL3N
aUISSAdU=J
aovid oa TC13N
NVld NOLLDHdSNI
spr \.u jbn joj uejd uo(joedsu| - v 900e~dUrA3Hd~dO8
96 JO gg a6ed
ludppuijayv
lH #3N
auissxad=j
aovid oa TE13N
N\Hd NOLLD3dSNI
spci.eW9N-'tyu8Kluo?Podsul-V 900 ddl A3dd~d08 96 JO 92 oBed
j u ff p p u / j ff y y
xauissxadd
aovid oa TEJL3N
NVId NOUOadSNI
spriea J6N Jo; uejd uoipedsui - V~900~dyrABUd~dOa
96 jo LZ 96ed
TCy #3N
auissAau=i
aovid oa TEJL3N
NVld NOUOadSNI
sprj,caieNJOju8|duo|ped8U|-v""900e""dai A3dd d09 96 jo 82 o6ed
IZH #JL3N
xauissxadd
3DVld oa T13N
NVld NOIX33dSNI
spaea 8n jj ueid "oipodsui - v 90oe dai a3wj doa 96 JO 62 oBed
TEH #13N
xauissxadd
aovid oa TEJL3N
modern NOiioadSNi
96 jo 0 o6Bd
Bra am
OTOc* J3quJ9oaa pj uo Bujjjjj Buunp ||Bj 6u!mo||oj :uoseay
TEy #13N
xauissAadd
aovid oa TE13N
NVId NOLLDSdSNX
INSPECTION PLAN
NET 31 BC PLACE
FReyssineT
NET# R31
Substitution:
Substitution possible for R31 and Hangers: use R6
replacement ReDlacement: limited stock on Geobrugg's
plant - Delivery time: pending information
Visual inspection (straightness of cable, pin,
Inspections socket)
(see IRP 3006 A2) Checking galvanisation (impact area)
Inspection and re-certification by Geobrugg
Coating: touch up (cold spray galvanizing or
ZRC paint)
Repair Further repair to be defined following
inspection J
Page 31 of 96
BCP_FREYJRP_3006_A- Inspection plan for Net R31.xls
INSPECTION PLAN
NET 31 BC PLACE
FReyssineT
NET# R31
Substitution:
Substitution possible for R31 and
Damps A & B : none
replacement
Clamps C: use R6
Oamrjs A - Pos 1 to 5 :
Visual inspection AND SANDBLASTING
Casting : UT & MPT (according SCA 1010 B)
Welds :UT
Inspections Plates: geometrical survey
(see IRP 3006 A3 and IRP 3006 M)
Clamps A - Pos 6 to 9. damps B & C :
Visual Inspection
If marks of Impact, same process than damps
A pos 1 to 5
Protection : re-metallisation for damps A pos 1
to 5
Repairs Touch up for the other damps
Further repair to be defined following
inspections
Nota : Each component will be keep together and put aside for inspection.
Report of site inspection will be issued for each component (except bolts). It indudes pictures before and after
disassembling.
In case of further inspections, an NCR will be opened.
Page 32 of 96
BCP_FREY_|RP_3006_A - Inspection plan for Net R31.xte
spc%ea ion JOJ UB|d uofpedsui - v 900E~dbfABdrfdOa 96 jo oBBd
lauissxaud
aovid oa TE13N
NVTd NOULD3dSNI
96 jo f oBBd
sbbt 381
xauissAaud
aovid oa T3N
NVld NOLLHdSNI
INSPECTION REPORT
NET 31 BC PLACE
FReyssiner
Details;
Details:
Residual
NO YES
Deformations
Details;
Other observations
Sample
Note: Inspection by Geobrugg required for all the cables CHECKED BY:
Page 35 of 96
96 jo Q a6Bd
ajdiues
xauissAddd
aovid oa TCJL3N
luodara NOuoadSNi
INSPECTION REPORT
NET 31 BC PLACE
FReyssineT
Hangers dismantled
Sockets
and pins Rope Ref picture Conclusion
(coating and (wires, straightness)
shape)
Use as is
Hanger FR31H02 OK OK after Geobrugg's assesment
Use as is
Hanger FR31H03 OK OK
after Geobrugg's assesment
Use as is
Hanger FR31H04 OK Minor coating damage after Geobrugg's assesment
General Minor coating damage can be repaired per usual process (cold spray galvanised or ZRC rich paint)
Paytj 37 uf 90
96 jo 9C oBBd
xauissxaud
aovnd oa TEJL3N
modau NOiioadSNi
96 jo 6 96Bd
rofl =A9 Q3>D3HD sajeid pue sdeo 'bupseo uoperapisuco 0}uj sa>je} uorpadsui :sjon
loquco Aj}3Ui036 -
g~0T0T"VDS"A3yd"dDa uooejupads jad se 6upsac| iw pue in -
OXOZ Jaqujaaaa VM. uo 6uRse|qpues joj juas -
:(0S0O^DN~A=&fcTcD8 *DN P) ucfleoijipaoaj jo ssaaoid japun si dujeo -
J9M10
spjsg
'.S|lelarj
ejnpjd jag spajaa adAipajaa
S3A ON UOflBUlJOpQ
Isjlejad
xauissxaud
aovid oa TE13N
lUOdsRI NOUL33dSNI
96 jo Of oBBd
xauissAadd
aovid oa TC13N
IHOd3H NOLDHdSNI
96 jo |,f 96Bd
aidtue
xauissAadd
aovid oa TC13N
JHOdSlf NOLiOSdSNI
INSPECTION PLAN
NET 31 BC PLACE
FReyssmeT
NET# R31
- Geometrical control of the assembly, specially the flatness and coplanarity of the welded elements
Page 42 of 96
INSPECTION REPORT
NET 31 BC PLACE
FReyssineT
Details:
Shocks NO YES
Details:
Deformation of the
NO YES
assembled damp
Sanjiple
Alignment on cable
Groves NO YES
Details;
Deformation of YES
NO
individual elements
Perils:
Other
observations
Note: Inspection take in consideration the 4 casting parts, the connection plates, and the pins.
CHECKED BY:
Page 43 of 96
96 jo frfr sBBd
ajdaies
xauissAadd
aovid oa T3N
iaOd3 NOLLD3dSNI
Steve Lingenfelter
From: David Campbell [dmc@geigerengineers.com]
S e n t : W e d n e s d a y, D e c e m b e r 0 8 , 2 0 1 0 3 : 0 6 P M
To : Dan Bock
Cc: Karen Lynch
Subject: Re: Cable net Incident - Damage to Building or Cable net
Dan:
We have not been requested by PCL to review anything regarding cablenet incident as of yet. My
understanding is that Christoph was contemplating a site visit this week in any event. Geiger did not ask him to
make the trip to review the R31 net components nor did SBP inform us of any such intent.
We've asked you all to not work for PCL and Subcontractors directly. I appreciate this is a bit of emergency but no one
has approached Pavco for additional services so I can only assume you are performing activity on the Cable Net Incident
as part of your base fees. Alternatively if you are planning on submitting an additional services claim, please confirm
asap with a per diem proposal so we can put PCL on notice.
David I believe Christophe has made a special trip here to view the damaged cable net so these disbursements as a
minimum should be tracked separately. I gather there will be some effort involved on assessing the damage to the net.
PavCo
Dan Bock
Project Manager
Phone 604 661 3648
Cell 604 818 5552
Page 45 of 96
Steve Lingenfelter
Importance: High
Martijn:
We have reviewed the inspection program for the R31 cablenet components. We have not yet had the
opportunity to review this with SBP. We may have specific comments pending our review with SBP.
That said, in our view the checklist is and inspection plan is good as far as it goes. We see the key being the
review of the cables and the assessment of those which have been damaged as to whether can be employed in
the work or are to be replaced. We assume Geobrugg's representative will be making an assessment for
Structal/ Freyssinet. Note there is no reason to involve us should you and your subs decide to replace the
damaged cables with new assemblies. If the affected cables are proposed to employed in the Work, we note the
following:
1. We will want to see a written assessment from Geobrugg indicating any repairs required and an unqualified
certification that the repaired cable assemblies meet the specified requirements.
2. We will perform our own review and assessment, Please note this is not a service covered in the scope of
our agreement with PavCo and we will request additional fees for the time and expenses involved.
3. We reserve the right to make the final determination of the acceptability of use of any damaged (repaired or
otherwise) components in the structure. Our standard is that the (repaired) cables employed in the Work
perform as specified, essentially as new.
Anticipate the same approach to the castings and hardware. However, we note that the testing proposed should
be reasonably definitive. Key is the absence of cracks or permanent deformation, We suggest that all clamp
bolts of the castings subjected to impact should be replaced. Similarly the D clamp link pins should be replaced
where they were subject to impact.
Page 46 of 96
On Dec 8,2010, at 11:00 AM, Martijn Lunneker wrote:
We have requested Freyssinet to outline their plan for inspection of the elements on cable net R31 that was involved in
the incident last Friday.
Please review and provide any comments or concerns you may have.
We are currently focusing on the installation of R14 and are trying to get confirmation to install R15 after this. This will
hopefully buy us the necessary time to deal with R31.
The next cable net that needs to be installed after R14 and R15 will be R31. We cannot skip this one and continue with
R32 since we will not be able to make the pin connections at the node side at R31 at a later date.
Pins at the node can only be made in a pre-determined sequence because of space restrictions.
First priority would therefore be to get confirmation and approval to use elements from R06 and R24 to re-built cable
net R31.
As noted by Freyssinet the only elements that currently cannot be substituted are the A and B clamps.
Pending your comments on this proposal Freyssinet has therefore started inspection of these clamps.
Don't hesitate to ask for any information that you require in addition.
Regards,
This e-mail (including any attachments) is for the sole use of the intended recipient and may contain confidential Information which may be protected by
legal privilege. If you are not the intended recipient, please immediately notify us by reply e-mail or by telephone 604-241-5200, delete this e-maH and
destroy any copies. Thank you.
File: 2200906- 4:051000
Page 47 of 96
Steve Lingenfelter
Dan,
PCL/Structal will be putting forward and insurance claim for this incident.
Consultant cost would be part of this claim.
We appreciate your instruction to Geiger to advance their review.
We can review whether PavCo would invoice PCL directly or whether PCL would add this to the claim on PavCo's behalf.
For the record PCL will put Structal on notice that these cost are forthcoming.
Regards,
David thank you adhering to the protocol that Pavco requested. We would like Geiger to review this, if you can estimate
your time and cost involved that would be preferable. We would be prepared to have Geiger do this on a per diem basis
as well. You are authorized to proceed.
Martijn - Pavco will be approaching PCL or the insurers for cost of this review by Geiger. I'm not sure if you will
confirming an insurance claim or not.
PavCo
Dan Bock
Project Manager
Phone 604 661 3648
Cell 604 818 5552
Page 48 of 96 1
Subject: Re: FYI - BC Place - Submittal: CS 215 -Inspection of cable net R31 upper and lower cables, hanger cables, and
end sockets
Martijn:
Per previous email correspondence, review of the the R31 cablenet is outside the scope of our agreement with
PavCo for the project. This "submittal" will not be reviewed pending authorization to proceed with the services
associated with such review and evaluation.
22009Q6
Submittals Received: CS 215 -Inspection of cable net R31 upper and
cables, and end sockets
Click HERE to view CS 215 - Inspection of cable net R31 upper and lower cables, hanger cables, and end sockets.pdf Click HERE to take
Name CS 215 - Inspection of cable net R31 upper and lower cables, hanger cables, and end sockets.pdf
Submittal # CS215
Revision #
Description CS 215 -Inspection of cable net R31 upper and lower cables, hanger cables, and end sockets
Send Alerts To Geiger Engineers (K. Lyndi);New Cable Submittal Group;PCL Const Westcoast (J. Outerbridge);PO. Const Westcoast (M. Lunnek
Contributor Due
To Reviewer 12/16/2010
Page 49 of 96
96 jo OS 96ed
s|U3uiUMo srqe)S
IN Wd
leAOJddy
opfcUL
eseifd
siepwso UO|S|A|a
uado sraets
N aiqeoxy sja^pos pua pue 'sajqeD jacueu. 'sajqea jsmoi 3 jaddn sift jo vodai uojpadsui laups/teJd paipene am MajAaj aseaid S)U9UIUI03
sdmtieM
psuuqou
J8W9tAeb UIOJJ
Dan:
We anticipate our fee for review of this matter will not exceed $3k. We anticipate completing this service this
week.
David thank you adhering to the protocol that Pavco requested. We would like Geiger to review this, if you can estimate
your time and cost involved that would be preferable. We would be prepared to have Geiger do this on a per diem basis
as well. You are authorized to proceed.
Martijn - Pavco will be approaching PCL or the insurers for cost of this review by Geiger. I'm not sure if you will
confirming an insurance claim or not.
PavCo
Dan Bock
Project Manager
Phone 604 6613648
Cell 604 818 5552
Martijn:
Page 51 of 96
Per previous email correspondence, review of the the R31 cablenet is outside the scope of our agreement with
PavCo for the project. This "submittal" will not be reviewed pending authorization to proceed with the services
associated with such review and evaluation.
22009.06
Submittals Received: CS 215 -Inspection of cable net R31 upper and
cables, and end sockets
Click HERE to view CS 215 - Inspection of cable net R31 upper and lower cables, hanger cables, and end sockets.pdf Click HERE to take
Name CS 215 - Inspection of cable net R31 upper and lower cables, hanger cables, and end sockets.pdf
Submittal # CS215
Revision #
Description CS 215 -Inspection of cable net R31 upper and lower cables, hanger cables, and end sockets
Send Alerts To Geiger Engineers (K. Lynch);New Cable Submittal Group;PCL Const Westcoast (J. Outerbridge);PCL Const Westcoast (M. Lunnek
Contributor Due
To Reviewer 12/16/2010
From Reviewer
Page 52 of 96
96 jo S e6ed
siu8uiuio3 srqets
1W Nd
IBAOiddv
apeix
asetfd
S|E13W SO uopiAia
uado snms
N siqeD joj sppos pua pue 'safqea jaBueij 'sajqea j3M0| 9 -Bddn em P vodai uofpadsui jaujssAay paupene aifl m9|a3j aseaid S)uauiui03
sdnHjeM
pauiiqou
Steve Lingenfelter
From: Dan Bock
S e n t : M o n d a y, J a n u a r y 0 3 , 2 0 11 1 : 1 9 P M
T o : R o y P a t z e r ; B r i a n G r i f fi n
Subject: FW: BC Place Phase 2 Roof Cablenet R31 Cable Damage Assessment - Geiger Review
Attachments: R31 Damage - Cable Evaluation-10.12.28.pdf; ATT00001 ..htm
FYI re damaged cables at R31 after the dropping incident. Note that Geiger have OK'd their reuse. Separate emails to
follow on upper clamp and lower clamp condition after the incident.
PavCo
Dan Bock
Project Manager
Phone 604 661 3648
Cell 604 818 5552
Martijn
Please see the attached review of the R31 cable damage assessment report.
Please do not hesitate to contact me should you have any questions. This will posted on the PDC site as well.
Page 54 of 96
G e i g e r G o s s e n H a m i l t o n C a m p b e l l E n g i n e e r s P. C . N e w Yo r k / B e l l i n g h a m
28 December 2010
RE: BC Place, Phase 2 Roof, Division 5 Cables and Castings, Specification Section 05191
R31 Cablenet Damage, Cable Assessment, Submittal No. CS 215
Geiger Engineers* File No. 208054.19
Dear Martijn:
We have reviewed the attached report, "Inspection Report Net 31", prepared by Freyssinet
documenting the damage to the cables in the Grid R31 cable net assembly that fell during lifting
operations on 3 December 2010. We find the re-use of and repairs to the cables and endfittings
proposed to be acceptable. We note that the cold galvanizing of the damage to the cables zinc
wire coating will not offer quite the same service as the wires' zinc coating. That said, the areas
requiring coating repairs are quite limited.
Please do not hesitate to call me should you have any questions or desire more information.
2 Executive Blvd. Suite 410. Suffern, New York. 10901 -4164. tel: 845. 36B. 3330 fax: 845. 368. 3366. www.geigerengineers.com
Page 55 of 96
INSPECTION PLAN
NET 31 BC PLACE
FReyssineT
NET# R31
Reason: Following fall during lifting on 3rd December 2010 By: BCN
Checked: MDN
Document ref: BCP_FREY_IRP_3006 Rev: A Approved: BLT
The purpose of this document is to present the inspections performed on the cable net R31 (FLC and
OSS) after the lifting accident (Dec, 3rd 2010). It is organized in four parts.
Conclusion:
The inspections performed by Freyssinet, Geobrugg and Elander show that no defects on the cables
and sockets.
Touch-up will be performed as per usual procedure.
The cables are good for use as they are.
On his report, the cable manufacturer confirms his warranty.
Bags 56 af 06
96 P /g aBed
5QSE an
IE* #3N
iaUISSA8Ud
30Vld OQ TEJL3N
"'^SSSm^^' NVTd NOLLHdSNI
96 jo 89 96Bd
tusip a6eiuep jou pinoo sajqeo am uo aaioj D|iueuAp aifl }eifl saajuejen6 uoneujflsa s>m :U6|$npUo3
xauissAaud
3DVld OQ TE13N
HOd3H NOXJLD3dSNI
96 jo 69 oBed
:3UBd
900E dm
laUISSABUd
aovid oa Tc i 3 N
"^^^^5^ MVTd NOI133dSNI
INSPECTION REPORT
NET 31 BC PLACE
FReyssineT
Hangers dismantled j
Sockets and
Rope Ref picture Conclusion
pins (wires, straightness)
(coating and shape)
Use as is
Hanger FR31H03 OK OK
Use as is
Hanger FR31H04 OK Minor coating damage
Use as is
Hanger FR31H06 OK OK
Use as is
Hanger FR31H07 OK OK
Use as is
Hanger FR31H08 OK OK
Use as is
Hanger FR31H10 OK OK
OK Use as is
Hanger FR31H11 OK
Major bending/opening
Hanger FR31H13 OK FR31H13-001/002 Rope to be replaced
on female side
OK Use as is
Hanger FR31H14 OK
Hanger FR31H15 N/A N/A Use as is (tension rod is assembled after lifting)
Page 60 of 96
96 jo 1,9 aBed
lauissxadd
aovid oa T3N
*iOd3U NOLLD3dSNI
96 JO Z9 96Bd
xauissAddd
3DVld OQ TE13N
JL)IOd3tt NOIlDadSNI
INSPECTION REPORT
NET 31 BC PLACE
FReyssmeT
Details:
All undiped wires observed after the
Undiped wires NO YES fell went back in position with
straightening of cable.
Details:
Residual
Deformations NO YES
Details;
Minor surface coating damages.
Sockets NO YES MPT was performed by Elander on # 1, 2, 3,4
these areas. No indication found
Details;
Other observations
Minor coating damage can be repaired per usual process (cold spray galvanised or ZRC rich paint)
Use as is.
Note: Validation letter by Geobrugg endosed CHECKED BY: BCU /BCN / MDN
Page 63 of 96
96 jo PQ a6Bd
jrainpid Eainpid
spsqs itrensg Boppsqs - osfpsasai dw
Z ainpid i ainpu
PSSPSIP BS3B alft J6 Uot)jUU&d - UdtpadsUj. JJR
xauissAaud
aovid oa TEJJN
lUOd3U NOUOadSNI
96 JO 99 3BBd
8 ajnpjd L ainpy
nuBBBiOTOB m&m nns - gn gwp raflPPa tt isrerop bohbb3
9 ainpid S ainpu
OSPpRpqifll HU55SR] HffS - TO BBP uOft|sod - fa# 5BW0BP bUt|eoD
xauissAaud
aovid oa T3N
UOd3H NOLLD3dSNI
96 JO 99 aBBd
Z\ ainpld Tl ainpid
OT ajnpid 6 ainpid
ngmpraw qassgra fffig - ero pro ZCH osgnqsq nggpsa - cd# sbwbbp wpwa
xauissAaud
BOVld OQ TEJL3N
lUOdaU NOLLD3dSNI
96 jo 19 a6Bd
ST ajrrpid H ainpjd
OoHSfOKOVB WfOSSSm ||S - FH WH DSflPSa - 9d #abeude<p B0RS55
Et ajnpid
ussBinraBB spmsni nBS - 591 swromp bdrrq
XaUISSAddd
BOVld OQ TE13N
UOd3U NOXJL33dSNX
96 jo 89 36Bd
8T ainpid
l\ ainpy 9T ainpid
xauissAadd
BOVHd OQ TEJL3N
lUOdlU NOLLD3dSNI
INSPECTION REPORT
NET 31 BC PLACE
FReyssineT
Details;
All undiped wires observed after the
Undiped wires UQ YES fe|| went back in position with
straightening of cable.
Details:
Residual
Deformations NO YES
Details;
Minor surface coating damages.
Sockets NO YES MPT was performed by Elander on #1,2,3,4,5
these areas. No indication found
Details;
Other observations
Minor coating damage can be repaired per usual process (cold spray galvanised or ZRC rich paint)
Use as is.
Note: Validation letter by Geobrugg endosed CHECKED BY: BCU /BCN / MDN
^P"69 of 96
96 JO Ol eBBd
O t^ainpid campy
SPSQS |DS0B5 Boppaqs - osfpBRai dw
Z 3Jnpid lajnpy
P3>j09ip e^Je" Bin J uotjIUyQd - uotpadsui id W
auissAaud
aovid oq TE13N
!UOd3*J NOLLD3dSNI
96 jo tzeBed
6 ainpid 8 ainpkl
orcBHprensB nasm ims nsimn nsraasfl hbbto - Z9i bbrdbp burrs
L ampid 9 ainpid
uo.qKjuejiHb mnnaii m - en tt zh Dsramq QBfflssa - fro BBBurep bdrbss
XaUISSABcJd
aovid oq TE13N
l*90d3ti NOLLD3dSNI
96 JO ZL 96Bd
H ainpid OT ainpy
XaUISSAdUd
aovid oq TE13N
luodau NOLioadSNi
INSPECTION REPORT
NET 31 BC PLACE
FReyssmeT
Details:
DejaJlSi
Residual
Deformations NO YES
Cfitalls:
Minor surface coating damages.
Sockets NO YES MPT was performed by Elander on #ltol0
these areas. No indication found
Details;
Other observations
Minor coating damage can be repaired per usual process (cold spray galvanised or ZRC rich paint)
Use as is.
Note: Validation letter by Geobrugg endosed CHECKED BY: BCU /BCN / MDN
3 of 96
96 jo u a6Bd
gajnpid Sainpid
frampid
Z aJnpi.d T
11 n ainpjd
BOPPBip pile B93B M**o U6ft|Ul^d - uob>adSiIl JJJR
xauissAaud
aovid oq TEJJN
lUOd3U NOLL33dSNI
96 jo 91 eBBd
OTSunpid 6ainPkJ
SpSip IBSOBg
Sajnpid ^ajnpu
XaUISSAddd
BOVld OQ TEJL3N
lUOd3H NOLL33dSNI
96 jo 9Z sBBd
^ f fl l l
H ajnpid ET ainpid
O
1 ubiij^Siu^eb s^uaSfeiti ||B$ - ZH TH Uaawqaq u6tjiS6d - a# abeuiep bu.qt^D
73
ZI ainpid TT ainpid
XaUISSAdUd
aovnd oq TE13N
l*!Od3ti NOLL33dSNI
96 jo LL 3BBd
L\ ajnpid 9T ainpid
ST ajnpid
Uoftesjuejjeb qOBSSRI IRES - 38 5 3SP&B UaoMjaa; uOgBOd - ed# obeiUBp BU|)b63
xauissAaud
aovid oq TE13N
JLUOdaU NOLDHdSNI
INSPECTION REPORT
NET 31 BC PLACE
FReyssineT
Detail?;
Undiped wires NO YES
Details;
Residual
NQ YES
Deformations
Details;
Minor surface coating damages.
Sockets NO YES MPT was performed by Elander on #lto6
these areas. No indication found
Details;
Other observations
Minor coating damage can be repaired per usual process (cold spray galvanised or ZRC rich paint)
Use as is.
Note: Validation letter by Geobrugg endosed CHECKED BY: BCU /BCN / MDN
Page 78 of 96
96 jo 61 96ed
gainpid sainpid
vajrtpid Eajnpu
Z aunpid i ajnpu
XdUISSAdUd
aovid oq TE13N
mod=ra NOiioadSNi
96 jo 08 oBBd
II ainpid
osppBpqpB igasnaa ims - 558 * 38 BBBmsq Qoup&a - 95 BBnmp BOgBSS
Oi ajnpjd 6 3Jnp!d
i^l
^^5181
* ^
i / -4^
8 ainpy Z ainpid
u6j)&idejjeb s^Ua^BJd [|B - 5PeH UoldJcog - BbBUiep B0RBB5
aUISSA3dd
aovid oq TCJL3N
Od3H NOLLD3dSNI
96 jo L8*0Bd
3)
9Q9E 381
Ty #13N
xauissAaud
BOVld OQ TE13N
NVld NOLLDSdSNI
A\
Te s t r e p o r t
P09-500803 - Stadium Vancouver (BC Place)
Test object:
Page 82 of 96
96 JO 68 aBBd
1 INTRODUCTION
In order to determine the effects of the falling down of Grid 31 during erection we
did a visual test of the cables and of the fittings. Additionally we measured the
thickness of the remaining Galfan coating at the position where scratches were
found. At the end fittings we did magnetic particle inspection carried out by
Elander Inspection.
Page 84 of 96
P09-500803 - STADIUM VANCOUVER
The pictures above where made by Freyssinet right after the incident was happen. Af
ter the cables where moved out of the stadium the wires jump into the right position.
=
in
GEOBRUGG A\
Page 85 of 96
96 jo 98 e6ed
I
o-p
a\
Q
uo;padsu| japue|3 Aq
poLjjaui 5jU| >pe|q auj ljjim sjsa; 6uunrj
S1S31 - w t
96 jo Z8 96Bd
\r DDnuaoaD
pgpuuB 6u;uy
U!e6e jsgj pue
owz 9t|) $0 puu6 oj pgpj09p 9/v\ ped
-uij jsjom 9u,j 9)jj| s)jooi z *on osneogg
03
Page 88 of 96
A
96 jo 68 oBBd
oonuao3D
V
A||npjBo padsui
9M p9U0!J|S0d SBM SdUJB|0 9U.J 9J9Uj\A
ti*
5 CONCLUSION
Freyssinet International & Cie asked us to check the suspension cables of the
Grid 31. Our conclusions are the following:
- The minor damages found on the cables do not have negative influence
on the cables breaking loads, service loads and lifetime.
- At the indicated locations where the thickness of Galfan was measured
lower as nominal, cold zinc spray shall be applied. The surface will serf-
heal from the cathode/anode effect.
- The fittings were MPT tested and no defects were found.
So the R31 suspension cables and fitting still reach the required mechanical
characteristic (MBL) and the required corrosion protection for the project. As a
consequence, the observed elements have no influence on the warranty on our
products.
S
s
Head of department
Ir--
Markus ZOrcher
A\
Page 91 of 96
96 jo 26 36ed
M6 aSI
18UISSA8Ud
aovid oa TEX3N
^5^a^"' NVld NOIOadSNI
Suite 128-11800 River Road,
C Llc_
I E N^T : REPORT
f ^ f c OF
Y S SNONDESTRUCTIVE
f^CT P R O J E C EXAMINATION
T NO:
REPORT DATE: tSi-i
Attention: Al frft "0 A/ ^U&PYOrS
T E S T D AT E : \ O t C
P.O. NO:
H ,2010
CLIENT'S NO:
REPORT NO:
LOCATION: BC Place CODE: see below
PROJECT: BC Place. New Roof Erection PAGE: 1of
EXAMINATION METHOD
MAGNETIC PARTICLE & LIQUID PENETRANT Q EDDY CURRENT D ULTRASONIC D VISUAL Q
Srf^!!ilP!Sr!,nl exaj"S,ton "^ *?ducte,d m !!* J?rt* as described- above; Penetrant was applied to the areas after the component
tiand
SSdried,
*%??*Devetoper
deane(1 S6 waspen?8ntwas altowed
applied and t0 dwe"for15
the parts minu,fes ^ for
visually examined P3*5 were orwaterwashed
cracks to remove
other significant the excessSant
problems, penetrant.
Siwtef<Ji2SSOrtfc ta"a^anai ^P^100 was conducted on the areas described above to determine If any cracks or otherobwious reflectors
Test Results
1
IN Attendance N.R J. * No cracks or retevant indicai'ons tound using referenced Inspection technique and acceptance criteria.
C E RT I F I E D W E L D I N G I N S P E C T I O N O R G A N I Z AT I O N - C S A W 1 7 8 . 1
Page 93 of 96
Suite 128- 11800 River Road,
Richmond, B.C. Canada V6X1Z7
Elander InspectionLm Phone: (604)214-1318 Fax: (604)214-1349
> E-mail: ElandanS>Jn^eraa1a,ca
Nondestructive Testing and Marine Inspection qfp Web Page: Etahdertnapectlon.ca
F
f ^
VP- ^ f
m t >t>~i ""TftvK 2 * - 6 ( ^5 i-
> i - 0 > OR. S/ r 6 ! kr> *l& i>.
* 4 7?r <W J f f \ * P* { Z ? ft? <
\ / t 2 ,1 M > f ^ > ' > . t-c tf^ T l (-v r A J ? H r--7 v & S>.
) - 4 v/B rf ^ u e W hr^ 7 " It ^ 9-A T t 5HN fc? & ? & ' / ^ r
[>/ <
> F ^ 3l
Z- I < #H * c cr ( ^ ^
U - r f tf t " n - i W >./* r f t * & r^- 0 <* - V? * A - i xH>
^ 1 - p (s^ ? & ^
f. 2, ^ , H* "A"1 * 1 i tT l " 0 ' ^ A ; T i t - I * ' /
^. / u 9 ' & \ + ' y 5 V A - > j - ; ' Av>/ & \ T7 an- 5 ? ^ > t j**- b .
p <*' * i
J . 7. <5^V 3 c ^ i ; T** >5
U d T>f \ " i 7rf* -f< r"A \r* rV? ^ e-T < ^ f V ^ . ^ ^
/, 5L A-
!>% > ' | i ^P" rv* r-7 ? ^ ^ 5 J r >< ^ c " >& D
* i ~te f L(2T ^ i 5-v ' fi r r*/~ T - $ t - -A' '' dr, r^^ 2< *u - t .
//
1
Name of Ship/Item Tank No Aocatlcn:
LM.O.. Frame No.:
Class No.: Port/Starboard:
Attending Surveyor. Type of test: MT DWFMPI DDry DBIack/White
U T D We l d O U T t h i c k n e s s
PT DPT
T ^ ^ t r
Peter D. Gabor ELANDER INSPECTION LTD.
TECHNICIAN:
CGSB Level II, PT El MT El, UT D
Cert. No. 3845 Allan Elander, Manager, NDT
Consumables:
J
CERTIFIED WELDING INSPECTION ORGANIZATION - CSA W178.1
Page 94 of 96
Suite 128 - 11800 River Road,
yf 1 r ... ... .. _ _
^Tfc&c^ csi-QciJLj&g*ilrezx:^' de-G-c'- %&*>< j&-& /'^^eJLaj/
lJ>L_:&iLZV ** f*eySS~i/*ri ', ^<^^~^^^rL^Lj^2cfe:
J2& A,&AAc?u^ ^LA^C fc^rYtg IpjW,^ t^nfij^ .:^llfllt& 5&
JL^'.-Pftr-rjL^j, I
r Te t * \ 10. A'<?$i't~7. |
H4%.- fvLr\ J
HII+ ,v IL 1
\
J S-4-1""
g r 3 T4.
^sl_jl_
*_Li_.
ztz zt
g _: > i t x z- ^ / L _ ^L r t r zr _^
g3'0- ^^_I_
JrTi'T^F ^V^J_
-R-LX- Z^&.J
tL_j;i3 Av^ ">^; TO*tf>5 ,
S
j
1 Zj
Name of Ship/Item Tank NoAocatton:
I.M.O.: Frame No.:
Class Na: Port/Starboard:
Attending Surveyor Type of test: MT QWFMPI QDry QBtack/White
UT QWeld DUT thickness
0. A/?/ PT DPT
They have used the components intended for R8 for Installing the net at R26. This shifted the problem from R26 to R8.
They had a spare lower radial on site that it is about 100mm too short for use at R8. To lengthen and use this cable, they
proposed to fabricate longer than normal threaded connector. Geiger and I approved this plan. They expect they can
have this new component on site in 2 weeks.
In the interim they have inventory to continue with CN fabrication and erection at R26,25, R24. They expect to have all
components soon for dropped radial R31 which would allow them to recommence clockwise installation direction.
We lost about a week due to the R26 problem component. Going forward they are working on checking all lengths to
ensure this doesn't surprise us in the future. This is the issue that concerns me most.
PavCo
Dan Bock
Project Manager
Phone 604 6613648
Cell 604 818 5552
Page 96 of 96
Corporate Headquarter*
.HADE WORLDWIDE, Inc.
V/ett Coait Headquarters
8505A Chn<elloi Row, Dollai, ri 75747 350 Kalmui Drift, Coif a Mtia, (* 97626
P 5I4.905.9SOO f 214.905.9514 Tf 800.966.5005 P 714.427.6981 714.477.6982 It 800.50.SHADI
Dear Martijn,
We received the information for the cable grease transmitted in your email of 11-23-10 as well as
the test results from NTB in your 1-17-11 email and forwarded all data to Saint Gobain. B oth Saint
Gobain and ourselves reviewed the information and have concluded the following to date
s17. s13
^
We applied some grease to both the SF I and Fabrasorb fabrics and have concluded that
the grease will most likely permanently stain the both the outer and liner fabrics.
o Photo 1 is of the sam pies with the grease applied for a period of 5 days, note you
can see the grease stain wlcking into the porous Fabrasorb fabric.
o Photos 2 and 3 are of the fabr ic after it was cleaned with water.
o Photo 4 is of the unbleached SF I fabric after it was cleaned with the recommended
cleaning soap (Murphy's Oil Soap). The dark stain indicates the fabric is
permanently stained. We are bleaching the fabric under UV exposure to get a better
sense of the darkening resultant of the staining.
(4
So
Thank you for your attention to this matter, we await your further instruction.
Sincerely,
tl
Bill Schmidt
Project Executive
Shade Worldwide, Inc. branded as FabriTec Structures
^ur*o'
January 26,2011
Bill Schmidt
USA Shade & Fabric Structures, Inc
8505 Chancellor Row
Dallas, TX 75247
Dear Bill:
Marcel Dery
Market Manager - Architectural
INSPECTION REPORT
LEAKING STATUS OF NET CABLES
Page 1/14
BC STADIUM ROOF PROJECT
INSPECTION REPORT
LEAKING STATUS OF NET CABLES
CONTENTS
INTRODUCTION 3
1 CORRECTIVE ACTION PERFORMED 3
1.1 INITIAL S TAT U S 3
1.2 NODE / UPPER CABLE 4
13 UPPER CABLE 5
M LOWER CABLE / IET TO CLAMP 14 5
1.5 LOWER CABLE / MAST TO IET 5
2 FURTHER ACTIONS 6
2.1 GUTTERS 6
2.1.1 Lower cable at mast location 6
2.1.2 Cleaning frequency 7
3 MAINTENANCE 11
3.1 CABLE PICTURE MAP 11
3.2 MAINTENANCE PROGRAM 11
3.2.1 Lower cables from clamp 1 to node 11
3.2.2 Gutters and trays 12
3.2.3 Upper Gutters removal 13
4 INSPECTION AND CLEANING CREW 13
4.1 C O N TA C T PERSON 13
5 APPENDIX 14
Page2/14
BC STADIUM ROOF PROJECT
INSPECTION REPORT
LEAKING STATUS OF NET CABLES
rcv
INTRODUCTION
The full locked cables supplied by our company tend to release some lubricant.
This lubricant is used to conserve the interior steel wires of the cable in order to
protect them against corrosion.
Since two months, the leaking rate tends to decrease, even if, some random
location are still releasing some lubricant
Since the beginning of the leaking issue, the status of each cable and the date
of successive cleaning have been recorded.
Based on these data, each cable have been given a note reflecting their
tendency to leak.
The hypothesis was that if a cable is cleaned many times, it means that it is
leaking the most. It is not perfectly accurate as some radials (especially radials
8, 9 and 10) have been dealed with more often due to first installation of fixed
and retractable membranes to avoid drop hits on the first panels. However, due
to the extensive cleaning and number of data recorded, the note reflect correctly
the tendency.
The note has been ponderated, based on the cleaning/ protection method used.
For instance, the upper cables have an higher note as they had to be wrapped
in absorbent pad which was not the case for the lowers. Equivalent ponderation
have been applied to sockets area and lower points (mast, node).
The highest the note is, the more, the related cable was leaking.
Since the end of July most of the cable stop to leak and / or decreased their
leaking rate. Except at specific and isolated area, they are now quite
homogenous. Then the graph below shall be considered as a initial leaking
status illustration only and not current behaviour:
Page 3/14
BC STADIUM ROOF PROJECT
GEOBRUGG* A\ INSPECTION REPORT
LEAKING STATUS OF NET CABLES
During the cleaning period, some corrective actions have been implemented in
order to contain the drops or to avoid that the accumulating drops fall off the
cable. These actions are described below.
At the node area some trays have been installed below the socket to
collect lubricant.
On the upper top and upper bottom cables some gutters have been
installed to collect lubricant.
Those area are then secured and the retractable membrane is protected from
lubricant drop while folded in garage.
Page 4/14
BC STADIUM ROOF PROJECT
GEOBRUGG* INSPECTION REPORT
LEAKING STATUS OF NET CABLES
13 UPPER CABLE
All the upper top and upper bottom cable have been equipped with
gutters
Those area are then secured. However some clamps (less than 0,1%) still need
some action. The caulking needs to be reinforced to ensure a 100% sealing.
This is monitored on a daily basis by our team, in order to identify any default.
The first heavy rains that occurred after gutter installation showed the good
behaviour and efficiency of drainage system.
This area is, so far, the best in term of leaking. Very few spot has been noticed
during these last 50 days. It is noticeable that the summer months have been
quite warm (2113 average) and sunny (which bring the cable outer skin
temperature to 40*C) and didn't impact the overall leaking rate.
Furthermore, during the pouring of the Field of Play concrete slab, no drops
have been noticed on the whole area.
This area tends to improve significantly, in the last 2 months. Few cleaning
operation has been required even if some random location are still leaking.
Especially the socket area and the first meter of cable. Most of the extra
lubricant is accumulating by gravity at these lower points and then induce more
oozing.
Randomly, some other area may leak at a lower level up to significant level. It is
often where the cable is most loaded (i.e. catwalk) or during the tensioning of
fixed membrane connection point.
An overall cleaning is currently performed by our team before the closing of the
membrane.
Page 5/14
BC STADIUM ROOF PROJECT
GEOBRUGG'JiK INSPECTION REPORT
LEAKING STATUS OF NET CABLES
2 FURTHER ACTIONS
2.1 GUTTERS
As it has been observed that the lower cable continue to leak on the lower cable
connection to the mast, we will installed some gutters.
These gutters will run from the bottom of the sockets to the sealing clamp of
fixed membrane.
This gutters will avoid the lubricant to fall in the main drainage gutter.
A mock-up have been performed to illustrate the shape of this gutter. The
material and principle is identical to initial lower gutter plan.
Page 6/14
BC STADIUM ROOF PROJECT
GEOBRUGG* A\ INSPECTION REPORT
LEAKING STATUS OF NET CABLES
The cleaning frequency has been recorded since the beginning of the leaking
issue.
In average, all cables have been cleaned 10 times: minimum 5 times, maximum
16 times according to the behaviour of the cable. This extensive cleaning
allowed to remove most of the extra lubricant. However, some area, such as the
most loaded part of cables, the clamps and the lowest point, keep leaking at
lower rate. Some random area are also noticed and are the most difficult to
monitor.
The last months, even though the hottest in term of temperature, the cleaning
was not necessary for most of the cable.
Page 7/14
BC STADIUM ROOF PROJECT
GEOBRUGG* A\ INSPECTION REPORT
LEAKING STATUS OF NET CABLES
Below are some graphs showing the number of day spent since the last
cleaning. During this period, almost no drops have been noticed in the related
area:
Page 8/14
BC STADIUM ROOF PROJECT
GEOBRUGG* AV INSPECTION REPORT
LEAKING STATUS OF NET CABLES
REV
T^>3
32/ I /\ A6
3 l / k X \ \ 7
30 /C/vN?S /7tC^
9
29/L7T^^
28 10
27 11
2 6 \ \ \ > S ^ ^ AVvA^X
2 5 \ X \ / / 0 / ~ "T \ J r V V / ^
24 \ \C^nT/ ~~X\^Ks\ /i4
4
AT >15
23^\/7^L
22\7 7 ^ 1 6
2*V19 H8
17
Page 9/14
BC STADIUM ROOF PROJECT
GEOBRUGG* A \ INSPECTION REPORT
LEAKING STATUS OF NET CABLES
This area is located from the socket fixed to the mast to the first clamp of
membrane edge fixation.
In average 14 days time frame virtually free of drops have been recorded
except at very specific location.
This area remain a significant leaking source. Indeed, being situated at the
lower point, all the extra lubricant within the cable tends to accumulate there.
The area will be equipped with lower gutters at completion of membrane trades
activity to avoid damage on them.
As a temporary measure, the end of the sockets is wrapped in an absorbent
pad.
Page 10/14
BC STADIUM ROOF PROJECT
INSPECTION REPORT
LEAKING STATUS OF NET CABLES
REV
3 MAINTENANCE
In order to illustrate the current status of lower cables during this month "free of
cleaning" a picture map has been made as follow:
All lower cable length from mast to IET pictures taken from the top
All lower cable length from IET to clamp 5 pictures taken from the bottom
It appeared to be not relevant to take picture from the bottom between mast to
clamp 5. Indeed the quality of pictures taken from the bleachers (extensive
zoom) and face to high fight exposure, is very poor. Furthermore, the status of
this area is totally similar to the other ones.
Cycle I:
Inspection once every two weeks
* If no leaking issue noticed, schedule a new inspection 2 weeks
after
- If leaking issue is noticed, plan immediate cleaning and schedule
a new inspection 1 week after
Page 11/14
BC STADIUM ROOF PROJECT
GEOBRUGG AX INSPECTION REPORT
LEAKING STATUS OF NET CABLES
Cycle II:
Inspection once every four weeks
* If no leaking issue noticed, schedule a new inspection 4 weeks
after
> If leaking issue is noticed, plan immediate cleaning and return to
cycle I
The passage from cycle II to III will be based on 2 inspections without leaking
noticed.
In case of 2 successive inspections with leaking noticed, restart the cycle I.
Cycle III:
Inspection once every 2 months
> If no leaking issue noticed, schedule a new inspection 2 month
after
* If leaking issue is noticed, plan immediate cleaning and schedule
a new inspection 1 months after
-> After 2 inspections without leaking, end of the cycle III
In case of 2 successive inspections with leaking noticed, restart the cycle II.
Cycle II:
Inspection once every 2 months
* If no leaking issue noticed, schedule a new inspection 2 months
after
- If leaking issue is noticed, plan immediate reparation and return to
cycle II
The passage from cycle II to III will be based on 2 inspections without
reparation required.
In case of 2 successive inspections with reparation required, restart the cycle I.
Cycle III:
Inspection once every 6 months
If no leaking issue noticed, schedule a new inspection 6 months
after
* If leaking issue is noticed, plan immediate reparation and
schedule a new inspection 3 months after
Page 12/14
BC STADIUM ROOF PROJECT
GEOBRUGG A\ INSPECTION REPORT
LEAKING STATUS OF NET CABLES
REV
One month after completion of upper gutter removal a final inspection of upper
cables will be conducted to confirm that the cables remain dry.
The cleaning team will be composed of rope access workers able to work on
the cables:
Access to lower cable from mast to clamp 1: from top facade beam with
fall arrest protection
Access to lower cables from clamp 1 to clamp 7: rope access while
walking on the liner from the catwalk
Access to lower cable from clamp 7 to 10: rope access from underneath
the cable
Access to lower cable from clamp 10 to node: rope access, walking on
the cable
Access to upper cables: from the node and then fall arrest protection
Page 13/14
BC STADIUM ROOF PROJECT
GEOBRUGG* AV INSPECTION REPORT
LEAKING STATUS OF NET CABLES
Franz SPICHTIG
Rigging Specialties
A Division of E.V.A.S. Trading Co. Ltd.
E-mail: franzspichtig@hotmail.com
Phone: (403)762-2509
Fax: (403)762-3718
Cell: (403)763-8863
APPENDIX
Page 14/14
E8JB amwejuew-"0^"^1
jpdaiwBuiuwpBpeP^11
K>J
6Ui IM
Bit)
ii OT
iZH
sza
oca
-..Aqpapodsui
S m :eW3
a fe|diQPPU
aoojjuoflowJsuj
CLEANING RECOMMENDATIONS
SEFAR* Architecture TENARA* Fabric is 100% fluoropolymer and is naturally dirt-repellent. However,
additional cleaning procedures can be employed to remove stubborn dirt or stains.
Overall Cleaning
In general, most contaminants such as dust and dirt can be deaned with water. If water proves insufficient to
clean the fabric, an ammonia or detergent solution can be used, along with a soft brush and a gentle cleaning
action. It should not be necessary to aggressively scrub" the fabric to remove dirt/ stains. If desired, chlorine
bleach solutions can also be used in any concentration without affecting the fabric. ..Pressure washers" should
not be used, as their extremely high pressure could damage the fabric.
Spot Cleaning
First wipe the discoloration off with a clean damp rag by rubbing gently. If this fails to remove the discoloration,
apply a liberal amount of cleaning solution (as recommended below) to a clean rag and rub the fabric gently.
Use a final water rinse, and allow the fabric to air dry. If desired, dry fabric with a clean rag. This should
remove most dirt spots.
Note: Ammonia and detergents are recommended cleaning agents to try BEFORE isopropyl alcohol, as alcohol
will tend to dissolve the contaminant and could cause it to be absorbed into the top fabric layer.
Importance: High
Good afternoon,
We have a bundle of FOIs being released to an applicant from the media this afternoon as follows:
Oul of Scope
#200
"Correspondence and reports regarding concerns and problems (including, but not limited to, flaws, failure and malfunction)
encountered in the construction and installation of cable and steel components associated with the new roof and its support
mechanisms for the BC Place Stadium renovation. I am seeking records for the period of October 1, 2010 to September 30,
2011".
Thank you!
Ali
Alexandra Wagner
Assistant Corporate Secretary
PavCo
Suite 850 - 999 West Hastings Street
Vancouver, BC V6C 2W2
Direct: 604.484.5153
Cell: 604.730.4821
Confidential Fax: 604.484.5154
Email: awaqner(g)bcpavco.com
Good afternoon,
"Correspondence and reports regarding concerns and problems (including, but not limited to, flaws, failure and malfunction)
encountered in the construction and installation of cable and steel components associated with the new roof and its support
mechanisms for the BC Place Stadium renovation. I am seeking records for the period of October 1, 2010 to September 30,
2011".
Out of Scope, s13
Regards,
Ali
Alexandra Wagner
Assistant Corporate Secretary
PavCo
Suite 850 - 999 West Hastings Street
Vancouver, BC V6C 2W2
Direct: 604.484.5153
Cell: 604.730.4821
Confidential Fax: 604.484.5154
Email: awaqner(5)bcpavco.com
Hi Ali
In talking with Warren and John last night you can go ahead and send out the
previously released material (larger bundle of documents) to Mackin as a partial
reply.
Steve Lingenfelter
604.484.5216
Sincerely,
Bob Mackin
18-1073 Lynn Valley Rd.
North Vancouver, B.C. V7J 1Z6
604-982-9130
Graham / Duncan,
"Correspondence and reports regarding concerns and problems (including, but not limited to, flaws,
failure and malfunction) encountered in the construction and installation of cable and steel components
associated with the new roof and its support mechanisms for the BC Place Stadium renovation. I am
seeking records for the period of October 1, 2010 to September 30, 2011".
Attached are the documents we propose to release to the Applicant following a courtesy review by
Victoria 0u,0,Scope
Oul of Scope
Cheers,
Ali
Alexandra Wagner
Assistant Corporate Secretary
ZrBwCo
Suite 850 - 999 West Hastings Street
Vancouver, BC V6C 2W2
Direct: 604.484.5153
Cell: 604.730.4821
Confidential Fax: 604.484.5154
Email: awagneri@bcpavco.com
Good afternoon
I have received the following FOI request from a member of the media:
Steve Lingenfelter
604.484.5216
Sensitivity: Confidential
This email and any attachments are only for the use of the intended recipient only and must not be distributed, disclosed, used or copied by or to
anyone else. This email and any attachments may be confidential, privileged and/or subject to the provisions of the Freedom of Information and
Protection of Privacy Act. If you receive this in error please contact the sender by return email and delete all copies of this email and any
attachments. You can also call us at (250) 387-5629 Thank you.. Email can be intercepted in transit or sent to the wrong address, so use secure
means to communicate with us if you are concerned about confidentiality.
Elizabeth Darche
Intake Officer
Office of the Information and Privacy Commissioner of B.C.
Phone: (250) 387-0354 Toll Free: (800) 663-7867 FAX: (250)387-1696
Email: edarche(5)oipc.bc.ca Website: www.oipc.bc.ca
PO Box 9038 STN PROV GOVT, Victoria, BC V8W 9A4
This email and any attachments are only for the use of the intended recipient only and must not be distributed, disclosed, used or copied by or to
anyone else. This email and any attachments may be confidential, privileged and/or subject to the provisions of the Freedom of Information and
Protection of Privacy Act. If you receive this in error please contact the sender by return email and delete all copies of this email and any
attachments. You can also call us at (250) 387-5629 Thank you.. Email can be intercepted in transit or sent to the wrong address, so use secure
means to communicate with us if you are concerned about confidentiality.
Alexandra Wagner
From: Alexandra Wagner
Sent: Wednesday, February 01, 2012 3:59 PM
To: 'Elizabeth Darche'
Subject: RE: Alleded Deemed Refusal Your Files BCPC 200 Oul of Scope
Out of Scope
Attachments: Response Letter200.pdf
Sensitivity: Confidential
Elizabeth Darche
Intake Officer
Office of the Information and Privacy Commissioner of B.C.
Phone: (250) 387-0354 Toll Free: (800) 663-7867 FAX: (250)387-1696
Email: edarche(a)oipc.bc.ca Website: www.oipc.bc.ca
PO Box 9038 STN PROV GOVT, Victoria, BC V8W 9A4
This email and any attachments are only for the use of the intended recipient only and must not be distributed, disclosed, used or copied by or to
anyone else. This email and any attachments may be confidential, privileged and/or subject to the provisions of the Freedom of Information and
Protection of Privacy Act. If you receive this in error please contact the sender by return email and delete all copies of this email and any
attachments. You can also call us at (250) 387-5629 Thank you.. Email can be intercepted in transit or sent to the wrong address, so use secure
means to communicate with us if you are concerned about confidentiality.
From: Elizabeth Darche
Sent: January-26-12 1:19 PM
To: 'slingenfelter@bcpavco.com'
Out of Scope
Subject: Re: Alleded Deemed Refusal Your Files BCPC 200
Importance: High
Sensitivity: Confidential
Oul of Scope, s3(1)(C)
Elizabeth Darche
Intake Officer
Office of the Information and Privacy Commissioner of B.C.
Phone: (250) 387-0354 Toll Free: (800) 663-7867 FAX: (250)387-1696
Email: edarche(5)oipc.bc.ca Website: www.oipc.bc.ca
PO Box 9038 STN PROV GOVT, Victoria, BC V8W 9A4
This email and any attachments are only for the use of the intended recipient only and must not be distributed, disclosed, used or copied by or to
anyone else. This email and any attachments may be confidential, privileged and/or subject to the provisions of the Freedom of Information and
AiifDiwapiJuoD jnoqo paujaouoa djo noAfi sn qijM ajoojunujujoD 01 suodui
amoas dsn os 'ssajppo Buojm aqi 03 juas jo iisudji uj paidajjawi aq uoo 110013 ' 'noA yuoq 6Z9S-L8E (OSZ) W sn hod os/d uoo no^ sjuaujqoojjo
Auo puo 11u1.ua siqj fo saidoo //o aia/ap puo ijouia ujnjaj Aq japuas aqi 10031100 asoa/d jojja ui siqi a/\iaoaj noA f\ jo\/ Aootujd fo uojioaiojrf
From: Pearson. Barbera CSCD:EX
To: Alexandra Waaner
Cc: Pearson. Barbera CSCD:EX: ):EX: Smerechinskiv. Kathrvn I ITTrFX
Subject: RE: PavCo FOI - Courtesy Consultation - BCPC-200 (Construction issues)
Date: Wednesday, February 01, 2012 15:15:33
Attachments:
Importance: High
Hi Ali:
We have completed our courtesy review and have made some additional
severing recommendations (refer to the attached) for the updated package.
Please process accordingly.
Thank you for your assistance, please contact our office if you have any
questions.
Cheers,
Barb
"Correspondence and reports regarding concerns and problems (including, but not limited to, flaws,
failure and malfunction) encountered in the construction and installation of cable and steel components
associated with the new roof and its support mechanisms for the BC Place Stadium renovation. I am
seeking records for the period of October 1,2010 to September 30, 2011".
PavCo would like to release these records today. The remaining 96 pages of records in this package have already
been released in a previous FOI request, so we are not recommending any changes to this package:
Danine Leduc
Manager, Crowns & Strategic Initiatives
Hi Dan
Steve Lingenfelter
604.484.5216
PavCo
Dan Bock
Project Manager
Phone 604 661 3648
Cell 604 818 5552
Good morning
Are there any further records for the period Mar 12/11 - Sept 30/11 ?
Thank you.
Steve Lingenfelter
604.484.5216
Good afternoon
I have received the following FOI request from a member of the media:
This is similar to request #167 we received back in March of this year so I already
have the records from June 1, 2010 to March 11, 2011 so please just send me any
further records you may have between March 12 and Sept 30. 2011.
Steve Lingenfelter
604.484.5216
Steve,
Thanks,
Chris "Beaton
Project Manager
BC Place Revitalization
Direct: 604-661-3632
Cell: 604-307-0123
Good morning
Are there any further records for the period Mar 12/11 - Sept 30/11 ?
Thank you.
Steve Lingenfelter
604.484.5216
Good afternoon
I have received the following FOI request from a member of the media:
This is similar to request #167 we received back in March of this year so I already
have the records from June 1, 2010 to March 11, 2011 so please just send me any
further records you may have between March 12 and Sept 30. 2011.
Steve Lingenfelter
604.484.5216
Good morning
Are there any further records for the period Mar 12/11 - Sept 30/11 ?
Thank you.
Steve Lingenfelter
604.484.5216
Good afternoon
I have received the following FOI request from a member of the media:
This is similar to request #167 we received back in March of this year so I already
have the records from June 1, 2010 to March 11, 2011 so please just send me any
further records you may have between March 12 and Sept 30r 2011.
Steve Lingenfelter
604.484.5216
Steve I have attached the documents I feel are appropriate to the response to this FOI request,
have limited the response to currently unresolved "problems or concerns" on the basis that
resolved issues are neither problems nor concerns.
PavCo
Dan Bock
Project Manager
Phone 604 661 3648
Cell 604 818 5552
Hi Dan
Steve Lingenfelter
604.484.5216
PavCo
Dan Bock
Project Manager
Phone 604 661 3648
Cell 604 818 5552
Good morning
Are there any further records for the period Mar 12/11 - Sept 30/11 ?
Thank you.
Steve Lingenfelter
604.484.5216
Good afternoon
I have received the following FOI request from a member of the media:
This is similar to request #167 we received back in March of this year so I already
have the records from June 1, 2010 to March 11, 2011 so please just send me any
further records you may have between March 12 and Sept 30T 2011.
Steve Lingenfelter
604.484.5216
This e-mail is Hie property of Terasen Inc. and/or its affiliates and may contain confidential material for the sole use of the intended reciptent(s). Any review, use,
distribution or disclosure by others is strictly prohibited. Terasen Inc. and its affiliates do not accept liability for any errors or omissions which arise as a result of e-
mail transmission, if you are not the intended recipient, please contact the sender immediately and delete all copies of the message including removal from your
harrldnve. Thank you.