ISSN: 2321-9653
AbstractThe paper aims to fill a void created by the absence of proper materials management on construction sites.
Research has shown that construction materials accounts for 50-60% of the total cost in construction projects. For a
productive and cost efficiency, material management is very essential. Material mismanagement decrease the
contractors profit leading to huge losses, and leaving the project in big troubles, therefore the proper management of
this single largest component can improve the productivity and cost efficiency of a project and help ensure its timely
completion. The existing construction material management practices of contracting companies are investigated in this
paper. The study was exclusively assessed through questionnaire survey, interviews, field visits and discussion with the
concerned authorities. 26 factors were selected for the proper assessment of most critical factors. The factors are ranked
according to the degree of significance as assessed by the respondents. The results obtained from the ranking factors
shows that the top five majors causes of cost overruns are: design issues, market condition, store issues, contractor
issues and external issues. Recommendations are given for reducing the material mismanagement in the construction
industry.
Page 486
www.ijraset.com Vol. 2 Issue V, May 2014
ISSN: 2321-9653
Client related issues: Poor cooperation of owner towards VI. RESULTS AND DISCUSSIONS
purchase, delay in suppliers payment and claim. After collection of sample, data analysis was conducted
with research instruments such as the Statistical Package for
Contractor related issues: Improper supervision at site Social Science (SPSS) software. The data from the
and control, insufficient material handling instructions, questionnaires was fed into SPSS software version 20, and the
engaging inadequate skill on labour, improper results were analyzed to determine the major factors. The
construction methods, improper planning and errors mean scores were calculated to rank mismanagement issues.
during construction, fraudulent activities of The steps undergone for this analysis are given below
subcontractors. Step 1: Statistical analysis done for each attribute.
Site related issues: Waste control during material usage, Step 2: Bar graph showing mean values were found
lack of site storage space, operation limitation within out.
site, stealing on site, unforeseen site condition, existence
of unnecessary material. Step 3: Based on high mean, the ranking of issues
found out.
Page 487
www.ijraset.com Vol. 2 Issue V, May 2014
ISSN: 2321-9653
4.4 4
3.5
4.3
3
4.2 2.5
2
4.1
1.5
4 1
3.9 0.5
0
3.8
delay in contractor's poor cooperation of
3.7 payment owner
material Inflated Preconstruction
availability specification material survey
study Fig. 3 Client related factors
Page 488
www.ijraset.com Vol. 2 Issue V, May 2014
ISSN: 2321-9653
4.5
3.5
4
3.4
3.3 3.5
3.2 3
3.1
3 2.5
2.9 2
2.8
2.7 1.5
2.6 1
0.5
0
price fluctuation materials scarcity
Page 489
www.ijraset.com Vol. 2 Issue V, May 2014
ISSN: 2321-9653
3.7 3.5
3
3.6
2.5
3.5 2
1.5
3.4
1
3.3 0.5
0
3.2
design client
3.1
procurement inventory logistics of Fig. 8 External factors
policy control material
Fig. 7 Store related factors The results indicates that most of the respondents are
The results indicates that most of the respondents are agreed that above said two external factors will significantly
moderately agree the above said store related factors are increase the cost and the results indicates most of the
responsible for cost overrun in building construction projects, respondents moderately agree that these two external factors
the result of ranking factors indicate that improper are responsible for cost overrun in building construction
procurement policy has the highest in the ranking of store projects, the result of ranking factors indicate that problem
related factor analysis, improper inventory control ranked the with neighbours has the highest in the ranking of external
second among the factors outline above, problem on logistics factor analysis, weather condition ranked the second the
of materials that occupied third position in the above ranking above ranking material mismanagement factors of the cost
material mismanagement factors of the cost overrun in overrun in construction projects.
construction projects.
H. Market Condition Factors
G. External Factors Increased price was recognized as the top critical risk factor
Most of the projects surveyed were in the early affecting both project time and cost. On the projects surveyed,
stages and this means that the works being undertaken were the prices of steel, cement and timber had increased
foundation work or construction of the building structure. dramatically over a few years. As indicated, most of the
Such activities would undoubtedly be affected by rain. Project activities were affected by these unwelcome effects. The Fig.
managers whose buildings included basements said that their 9 shows the response of companies towards market condition
basements were flooded and they needed extra time and factors.
equipment to dewater them. Most of the concreting works for
the structures were also affected by heavy rain and
occasionally, concreting was postponed. Another impact of
weather was that rivers with sand quarries were flooded and
affecting the availability of sand. The Fig. 8 shows the
response of companies towards external issues.