1 2
Cairo University
Faculty of Engineering
Risk response strategies
STRN-421 3. Transfer
4. Mitigation
Dr. Hatem ElBehairy
Lecture (10)
3 4
Response plans requires resources to implement Even if physical materials are not needed, human
Buy materials/suppliers Resources, no matter what they are doing, cost the
Spend time and effort by your own workforce (e.g. contingency company money.
planning), With possible alternative response strategies, costs and
Hire contractors on fixed-price basis, benefits should be evaluated for selection of the most
Purchase insurance. suitable action to take.
1
Lec (3) 12/26/2012
5 6
Let us consider the risk of late delivery of a constructio The following estimates were made:
material Impact of risk occurrence is $5,000.
Assume the material to be newly introduced to the Probability of risk occurrence is 40%.
7 8
Cost of risk occurrence (expected value) is $2,000. Let us consider the risk of Equipment Failure.
Cost of avoidance is $1,000, while cost of mitigation is Assume that adopting a periodic maintenance procedure
$3,000. for owned equipment will reduce chances of failure.
Cost of mitigation exceeds benefit-- rejected. An agreement can be made with an equipment supplier
Cost of avoidance is less then the benefit. to insure availability of equipment at all times (with
immediate replacement in case of failure).
Thus, use the other common material.
2
Lec (3) 12/26/2012
9 10
The following estimates were made: Cost of risk occurrence (expected value) = $16,000.
Impact of risk occurrence is $40,000. Cost of mitigation is $5,000.
Probability of risk occurrence is 40%.
Cost of transfer is $10,0000.
Cost of mitigation (through periodic maintenance is an extra
Cost of mitigation and transfer are both below the benefit
$5,000). In this case chances will become 2%.
both accepted.
Cost of transfer (paying a premium for rental vs. use of own
equipment) is an extra $10,000. Cost vs. benefit is better in case of mitigation.
12
Contingency
contingency owner.
3
Lec (3) 12/26/2012
13 14
Different terms are used to represent the contingency In any project, there is also possibility of unknown /
values unpredictable risks that are:
Time contingency & cost contingency. Not recognized during the identification stage, and/or
Time buffer & cost Buffer. Not planned for during the risk response planning.
Contingency reserve. Think of the external risks that could take place in the
business environment, while you had no clue they could
ever occur.
15
Management reserves
4
Lec (3) 12/26/2012
17 18
This documents typically contains the following: Called also risk lo.
Purpose, definitions and methodology. Think of a database with records, each corresponding to
Roles and responsibilities. an identified risk.
Contingency.
The question is what kind of info to associate with each
Risk register.
identified risk.
Tracking system.
Reporting.
19 20
The risk register typically contains the following: Expected value (risk score)
Risk category Any information needed to track and monitor the risk throughout
the project.
Risk triggers
Risk originator
Risk owner
Probability
Impact
5
Lec (3) 12/26/2012
21 22
Risk originator: vendor for mechanical supplies. Resources needed: personnel and procedures for
24
6
Lec (3) 12/26/2012
25 26
Steps of implementation: 5. Approval process for expenditures is done (if plan requires money
to implement).
1. Risk owners notifies the project manager (PM) of the risk event or
risk trigger. 6. Resources are assigned in preparation for the risk response.
2. PM and risk owner together agree that the response plan should 7. Response plan is implemented.
be put into action. 8. Risk owner monitors the effectiveness of the response plan and
3. Response plan is reexamined to assure the suitability of the risk reports status at project meetings.
response strategy. 9. Risk owner and PM document results of the risk event and the
4. If needed, a meeting of the project team and stakeholders is called response plan for the benefit of future projects.
to review the risk event and response plan prior to implementing. 10.
27 28
Projects have unknown/unpredictable risks, for which This term is used to imply:
response plans do not exist. Unplanned response to risks that were unknown/unidentified
during the risk identification process.
In this case, response plans which are called
Unplanned response to risks that were passively accepted.
workarounds- are devised as the unpredictable risks
materialize. Workarounds are similar to contingency plans, expect
that they are devised and implemented as the
risk/problem is recognized.
7
Lec (3) 12/26/2012
30
31 32
A risk audit is performed at the end of a project. Completeness of the risk management plan.
Contingency plans.
8
Lec (3) 12/26/2012
33
Risk mitigation