Dear User, thank you for using my template. Please remove sample entries from the register

2)
Please make your data entries on the sheet "Estimation Sheet". Cells containing formulas or functions are protected, the password is blank
you wish to modify anything.

3)
To avoid typing mistakes resulting in incorrect filter results, some entries are restricted. To modify acceptable values change entries on the
"Validation".

4)
You downloaded this sheet free of charge from
http: project-management.magt.biz
You may use this sheet for your personal use and projects. However, selling the sheet is strictly prohibited.
ected, the password is blank should

alues change entries on the sheet

bited.
This template is downloaded from http://project-management.magt.biz

Project: [Project Name]


Sub-Project or Phase: [Sub-Project or Phase]
Activity Cost Estimation
Client: [Client] Project Mngr.: [Proj. Mngr.] Printed on 5/23/2017
Client's Representative: [Client's Representative] QA/QC Mngr.: [QA/QC Mngr.] Ref.-No.: [ref. number]
Contractor: [r]
Activity Description: [Activity Description]
Material Manpower Tools & Equipment
Total Man
Item UOM QTY Rate (EUR) Total (EUR) Name QTY days hrs/day Rate (EUR) Total (EUR) Item UOM QTY Rate (EUR) Total (EUR)
Hours
A B C D E F G H I J K L M N O P Q R
0001 Item 1 lm 1,000 111 111,000 Skilled Worker 3 10 8 240 40 9,600 Some item LS 1 15,000 15,000
0002 Item 2 nos 5,000 5 25,000 Helper 2 10 8 160 28 4,480 -
0003 - Operator 1 10 8 80 34 2,720 -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
Sub-Total Material (EUR) 136,000 Sub-Total Human Ressources (EUR) 16,800 Sub-Total Equipment and Tools (EUR) 15,000

Grand Total Direct Cost (EUR) 167,800

Estimation Class Range Lower Limit (EUR) Upper Limit (EUR)

Budget Estimation -10% 25% 151,020 209,750

Prepared by: Marc Arnecke,PMP


Order of Magnitude -25% 75% Currency: EUR
Preliminary Estimation -15% 50%
Budget Estimation -10% 25%
Definitive Estimation -5% 10%