ID Task Task Name Duration Start Finish Predecessors Resource Names Half 1, 2017 Half 2, 2017 Half 1, 2018

e Names Half 1, 2017 Half 2, 2017 Half 1, 2018 Half 2, 2018 Half 1, 2019 Half 2, 2019
Mode J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O
1 CONSTRUCION DEL 650 days Mon Fri 02/08/19
OLIMPIC TOWER 06/02/17

2 ESTUDIO DE 33 days Mon Wed


FACTIBILIDAD 06/02/17 22/03/17

3 FIRMA DEL 0 days Wed Wed 2 22/03


CONTRATO 22/03/17 22/03/17

4 MODELO 10 days Thu Wed 3


ESQUEMATICO (ME) 23/03/17 05/04/17

5 ESTIMACION DE 5 days Thu Wed 4


COSTOS 06/04/17 12/04/17

6 APROBACION DE ME 1 day Thu 13/04/17Thu 13/04/175

7 CREACION DEL 40 days Fri 14/04/17 Thu 6


MODELO 08/06/17
ARQUITECTONICO

8 CREACION DE LOS 40 days Thu Wed 6SS+10 days


MODELOS SISTEMAS Y 27/04/17 21/06/17
SIMULACIONES

9 COORDINACION DE 15 days Thu Wed 8


MODELOS 22/06/17 12/07/17

10 PLANIFICACION 4D 20 days Thu 13/07/17Wed 09/08/179

11 BIM 5D 35 days Thu Wed 10


(PRESUPUESTO Y 10/08/17 27/09/17
LICITACION)

12 ELABORACION DE 5 days Thu Wed 11


EXPEDIENTE DE 28/09/17 04/10/17
PROYECTO

13 APROBACION DE 1 day Thu Thu 12


PROYECTO 05/10/17 05/10/17

14 INICIO DE 50 days Fri 06/10/17 Thu 13


MOVIMIENTOS DE 14/12/17
TIERRA

15 COSTRUCION 400 days Fri 15/12/17 Thu 14


27/06/19

16 FINALIZACION DE LA 1 day Fri 28/06/19 Fri 28/06/19 15


COSTRUCION

17 ENTREGA DE 25 days Mon Fri 02/08/19 16


DOCUMENTACION Y 01/07/19
MODELOS ASBUILD
PARA FM

Task Project Summary Manual Task Start-only Deadline


Project: CRONOGRAMA.mpp Split Inactive Task Duration-only Finish-only Progress
Date: Sun 12/02/17 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1