Task Name Start Date End Date Duration % Complete Status Task Lead
1 Background Research 05/15/17 06/06/17 23d 100% Completed Y.Geng
2 Report 1 06/01/17 06/07/17 7d 100% Completed Y.Geng
3 Website Update 06/09/17 08/04/17 57d 1% In Progress Z.Xu
4 Design Concept Generation 06/08/17 06/18/17 11d 0% Not Started Y.Geng
5 Wings 06/08/17 06/10/17 3d 0% Not Started C.Okonkwo
6 Fuselage 06/08/17 06/10/17 3d 0% Not Started Y.Geng
7 Tail 06/08/17 06/10/17 3d 0% Not Started Z.Zhang
8 Landing Gear 06/08/17 06/10/17 3d 0% Not Started Z.Xu
9 Design Concept Evaluation 06/11/17 06/11/17 1d 0% Not Started Group Meeting
10 Design Selection 06/11/17 06/11/17 1d 0% Not Started Group Meeting
11 Report 2 06/12/17 06/16/17 5d 0% Not Started Y.Geng
12 Material Procurement 06/16/17 06/18/17 3d 0% Not Started Z.Zhang
13 Fabrication 06/19/17 06/26/17 8d 0% Not Started C.Okonkwo
14 Wings 06/19/17 06/20/17 2d 0% Not Started C.Okonkwo
15 Fuselage 06/21/17 06/22/17 2d 0% Not Started Y.Geng
16 Tail 06/23/17 06/24/17 2d 0% Not Started Z.Zhang
17 Landing Gear 06/25/17 06/26/17 2d 0% Not Started Z.Xu
18 Assembly 06/27/17 06/28/17 2d 0% Not Started C.Okonkwo
19 Flight Test 07/03/17 07/13/17 11d 0% Not Started Z.Xu
20 Reliability & Optimization 07/03/17 07/13/17 11d 0% Not Started Z.Xu
21 Report 3 07/09/17 07/14/17 6d 0% Not Started Y.Geng
22 Final Competiton 07/27/17 07/28/17 2d 0% Not Started Y.Geng
23 3D CAD Package 07/14/17 08/05/17 23d 0% Not Started C.Okonkwo
24 Final report 07/20/17 08/05/17 17d 0% Not Started Y.Geng
25
26
27

Exported on June 12, 2017 11:30:09 PM PDT Page 1 of 1