Ln o l eo s t o t o . 0 1
%rooms 11011 rim 1444
OO
S
C I "StOo4,COIC to
Lo \
Tram E030 auto
\Y
1.
___________________ SPoOlo With eatrradeL
so/deicer __________________________________
SOO
tivdial,
K5+600 K-6/
K 6.400
Sultheod
Voce roloncht occurred
Figure 3. Case B; Geological conditions.
Some sixty cubic meters of material were removed, but the water kept
carrying new material until it filled the tunnel at Station K 6+098 and
extended down to Station X 6+230. The following day, the water flow
increased to 100 l/s, and carried even more material. An emergency
inspection was carried out from the portal up to Station K 6+900, and
it was observed that the invert was covered with blocks of clay. The
size of these clay blocks increased approaching the face. It was also
observed that the invert had been eroded. Twenty minutes after this
inspection was completed, four very sizable waves of mud and water
were observed at the portal of the tunnel, more than one kilometer
from the face. It is assessed that approximately 50,000 cubic meters
of material were involved. Material came out of three penstock tunnels
as well. The surface powerhouse under construction was partly
flooded, as was the switchyard. A concrete plant adjacent to the
portal was destroyed.
71