OBRA : CONSTRUCCION DE VIVIENDA UNIFAMILIAR

PROPIETARIO : EMILIANO MALINO CUEVA GALARRETA


FECHA : 07 DE ABRIL DEL 2015

PART. ESPECIFICACIONES N DE
N VECES LARGO
3.0.0 ARQUITECTURA
3.1.0 MUROS Y TABIQUES DE ALBAILERIA
3.1.1 MUROS DE ADOBE
3.1.1.3 DE SOGA
EJE A-A ENTRE 1 Y 2 1 3.26
EJE A-A ENTRE 2 Y 3 1 3.83
EJE B-B ENTRE 1 Y 2 1 4.42
EJE C-C ENTRE 1 Y2 1 3.52
EJE D-D ENTRE 1 Y 2 1 3.52
EJE 1-1 ENTRE A Y B 1 2
EJE 1-1 ENTRE B Y C 1 3.53
EJE 1-1 ENTRE C Y D 1 2.31
EJE 2-2 ENTRE B Y C 1 3.53
EJE 3-3 ENTRE A Y B 1 2.85
EJE 3-3 ENTRE B Y C 1 3.78

3.1.2 MURO DE LADRILLO KING KONG


3.1.2.1 DE SOGA
BAO
EJE B-B ENTRE 2-3 1 0.90
1 2.37
EJE C-C ENTRE 2-3 1 0.90
1 2.37
EJE 2-2 ENTRE B-C 1 2.51
EJE 3-3 ENTRE B Y C 1 2.31

ADOBE
EJE B-B ENTRE 2-3 1 0.90
1 2.37
EJE C-C ENTRE 2-3 1 0.90
1 2.37
EJE 2-2 ENTRE B-C 1 2.51
EJE 3-3 ENTRE B Y C 1 2.31
FORMATO DE METRADO

METRADO VANOS TOTAL UNID.


ANCHO ALTURA PARCIAL LARGO ANCHO ALTURA

72.47 M2

- 1.20 3.91 3.91


- 1.20 4.6 4.6
- 2.8 12.38 1.30 - 2.10 9.65
- 2.8 9.86 0.96 - 2.10 7.84
- 2.8 9.86 2.64 - 1.45 6.03
- 1.2 2.4 2.4
- 3 10.59 10.59
- 3 6.93 6.93
- 3 10.59 1.45 - 1.45 8.49
- 1.2 3.42 3.42
- 3 11.34 1.88 - 1.45 8.61

5.7 M2

- 0.50 0.45 0.45


- 0.50 1.19 1.19
- 0.50 0.45 0.45
- 0.50 1.19 1.19
- 0.50 1.26 1.26
- 0.50 1.16 1.16

22.02 M2
- 2.30 2.07 0.75 - 2.10 0.5
- 2.30 5.45 5.45
- 2.30 2.07 2.07
- 2.30 5.45 5.45
- 2.50 6.28 0.90 - 2.10 4.39
- 2.50 5.78 1.25 - 1.30 4.16
cantidad
24.0384615 x metro
25

TOTAL DE ADOBE= 1811.75


1812
Desperdicio 5% 90.6

Adobes a Usar= 1902.35


1903

cantidad
48.0769231 x metro
49

TOTAL DE LADRILLOS= 279.3


280
Desperdicio 5% 13.965

ladrillos a Usar= 293.265


294

cantidad
24.0384615 x metro
25

TOTAL DE ADOBE= 550.5


551
Desperdicio 5% 27.525

Adobes a Usar= 578.025


579
PRESUPUESTO DEDUCTIVO N 01

REAHIBILITACION CAMINO RURAL


ITEM DESCRIPCION

13.02 PISO DE LADRILLO PASTELERO

COSTO DIRECTO
GASTOS GENERALES 7.5%
UTILIDAD 6%
TOTAL PRESUPUESTO

PRESUPUESTO ADICIONAL N 01

REAHIBILITACION CAMINO RURAL


ITEM DESCRIPCION

03.04 FALSO PISO E=10CM


13.02 PISO CERAMICA 30X30

COSTO DIRECTO
GASTOS GENERALES 7.5%
UTILIDAD 6%
TOTAL PRESUPUESTO

PRESUPUESTO ADICIONAL N 02

ITEM DESCRIPCION

03.04 PISO DE CONCRETO COLOREADO E=10CM

COSTO DIRECTO
GASTOS GENERALES 7.5%
UTILIDAD 6%
TOTAL PRESUPUESTO
TO DEDUCTIVO N 01

PRESUPUESTO
UNID. METRADO P. UNIT. P. PARCIAL

M2 33.06 31.00 1024.86

S/. 1,024.86
S/. 76.86
S/. 61.49
S/. 1,163.22

TO ADICIONAL N 01

PRESUPUESTO
UNID. METRADO P. UNIT. P. PARCIAL

M2 33.06 29.23 966.34


M2 33.06 44.04 1455.96

S/. 2,422.30
S/. 181.67
S/. 145.34
S/. 2,749.31

TO ADICIONAL N 02 ANALISIS DE

PRESUPUESTO ITEM
UNID. METRADO P. UNIT. P. PARCIAL
03.04
M2 33.06 44.72 1478.44

S/. 1,478.44
S/. 110.88
S/. 88.71
S/. 1,678.03
ANALISIS DE COSTO UNITARIOS

REAHIBILITACION CAMINO RURAL PRESUPUESTO


DESCRIPCION UNID. CUDRI. CANT PRECIO

PISO DE CONCRETO COLOREADO E=10CM


RECURSOS
Cemento Portland Tipo I BOL 0.6 25.00
Hormigon M3 0.13 70.00
Agua M3 0.015 1.20
MANO DE OBRA
Capataz H-H 0.33 0.088 23.04
Operario H-H 2 0.5333 19.30
Peon H-H 2 0.5333 14.40

HERRAMIENTAS MANUALES 3% % 0.03

COSTO UNIDAD POR M2


P. PARCIAL

15
9.1
0.02
2.03
10.29
7.68

0.6

44.72