PROJEK MEMBINA DAN MENYIAPKAN JALAN SAMBUNGAN (MAINLINE 3),

MENGHUBUNGKAN KG BIAK KE KG KANDEK,KUALA KRAI KELANTAN.

EARTHWORK : QUANTITY CUTTING 25-Apr-17

CUTTING
Chainage Distance Area (m2) Av. Area (m2) Volume Kumulatif Remarks
875.00
880.000 5.000 21.328 10.664 53.320 53.320
900.000 20.000 30.425 25.877 517.530 570.850
920.000 20.000 39.272 34.849 696.970 1,267.820
940.000 20.000 22.735 31.004 620.070 1,887.890
960.000 20.000 24.597 23.666 473.320 2,361.210
980.000 20.000 11.705 18.151 363.020 2,724.230
985.000 5.000 0.000 5.853 29.263 2,753.493

TOTAL 2,753.493