1. Member present:

Attendance
Position in
No Name Country Day 1 Day 2
Delegation

KUNJUNG
1 ID JURY CHAIR
MASEHAT
NGUYEN QUANG
2 VN CHIEF EXPERT
HUY
SOMBOON DEPUTY CHIEF
3 TH
SANGTHEERATHITI EXPERT
PICHITKACHENTR
4 TH EXPERT
KANEEKUL
KYAW MYAT
5 KHAING MYN EXPERT

6 BUN HEANG CAM


EXPERT

7 CHY VANNY CAM


EXPERT

CHENG SHING EXPERT


8 HAUR SG

WINSTON CHENG EXPERT


9 SG

HENRY J. OCAMPO EXPERT


10 PH

EDDIE L. EXPERT
11 PH
CABALTERA
MAHEFAD ISMAIL EXPERT
12 IN

1
TRI WINAHYU EXPERT
13 ID
HARIYADI
Vanthong EXPERT
14 LAO
PHOTHICHAK
Phonesack EXPERT
15 LAO
XAYYALATH
VU THANH TUYEN EXPERT
16 VN

ZAKARIA ISMAIL EXPERT


17 MY

MAZLAN EXPERT
18 MY
ABDULLAH

Secretariat

1. Worshop Manager:
2. Secretariat:

2
2. Introduction and General issues

No Matters Action
1. Guidelines for the Chief Expert refer to World skills 2015 at Sao Paolo
competition Brazil method to direction this competition. The
method is new and different from Asean skill
previously. The differences are:
1. The participant only given layout drawing
except schematic diagram.
2. Participant only can see the sample
demonstration board 30 minute 2 day before
competition day.
3. The test project including programming,
mechanical work, electrical installation and
commissioning.
4. Participant only given the operation of the
project, their need to design the circuit
diagram and programming.
5. Participant need to identify and proficient with
the components functional and operation.
2. Overall time for the The participants has given to 3 day (18hours) to
competition completing their project. 14 hours for design and
installation, 3 hours for programming and 1 hour for
fault finding and total 18 hours.

3. Discussion/review of Technical Description

No Matters Action
1. The test project All the experts check the entire test project that
review made agreement from TCM1. Host country provides
more specific information about the size,
characteristics and standards of some supplies and
equipment related to the test project. The function
of KNX and Siemens logo was prepared by the
sponsor.
2. Workstation software KNX was prepared the software and computer. The
and materials version of programming software was informed to the
expert. The infrastructure list was given.

3
3. Module 1 Day 1 (20/9/16)
(Drawing) Discuss on changing item:
- Same level for SW1 to SW4
- Roof Design (Change position L3 & change
dimention of PVC Conduit for PIR and L2)
- Change position for flexible conduit (SW1 use
Flexible conduit & SW2 use PVC Conduit)
- Rotate 90o POS 5a and cable POS 5b use left side
Day 2 (21/9/16)
Final:
- Only change for the SW1 to SW4 make a same
level (others is same with TCM 1)
- No need prepare bend for metal conduit
- Rotate 90o POS 5a and cable POS 5b use left side
KNX Installation:
- Line 0: USB Interface, SW1, SW2, PIR
- Line 1: SW3, SW4, Line coupler and other KNX
devices
Installation :
L1+L3 = DALI
P1+P2 = Energy Switch Actuator
L2,L4 = Output Switch Actuator
L5,L6 = Dim 2T
Shutter = Shutter
4. Module 2 Day 1 (20/9/16)
(Motor control H1 indicates power supply for control circuit
functions and B2 & B4 = Up --> Process Up H2&H5 Blink 1s
programming) then reach L1, H2&H5 ON, 5 second delay
B3 & B5 = Down--> Process Up H4&H7 Blink 1s
then reach L2 H4&H7 ON, no need delay
O/L (MPS) --> H3 ON
B1 H6 ON
Note :
If Emergency stop push in the middle of process all
will be off, then Emergency stop normal door can
up or down (same situation with overload)

5. Module 2 Day 2 (21/9/16)


(KNX functions and KNX Malaysia handle KNX functions and show on
programming) competitors on Day 3 (programming). There are total
21 functions with total 10.5 marks.

6. Module 3 Day 2 (21/9/16)


(Installation testing) Nothing changes on drawing.
Each country propose 3-4 faults then experts will
choose 10 faults.

4
4. Discussion of Test Project

No Matters Action
1. Test project The Test project has 3 module. Module 1 is electrical
management installation, module 2 for motor control and module 3
for installation testing.

2. Additional test In module 1 the system controlled by KNX. Module 2


projects the motor controller unit is Siemens logo to control
pilot lamp, shutter door and forward and reverse
motor. For fault finding in module 3, the expert will
do the fault finding box to create the fault in the
system.

5. Competition Management

5.1. Competition time table

No Matters Action
1. The competition time The participants has given 18 hours to completing
table their project. The divided of timing:
Day 1: given time is 6 hours for installation.
Day 2: given 5 hours installation and 1 hour fault
finding.
Day 3: 3 hours installation, 3 hours programming.

2. Back-up plan for No additional


additional test
projects

5
5.2. Distribution of Experts responsibility

No Matters Action
1. Marking Group The experts are divided into 4 group:
Group 1
- Wiring Bay 1-5
1. Malaysia
2. Singapore
3. Indonesia
4. Cambodia
Group 2
- Wiring Bay 6-9
1. Myanmar
2. LAO PDR
3. Philippines
4. Thailand
Group 3
- Wiring Bay 1-5
1. Philippines
2. LAO PDR
3. Indonesia
4. Cambodia
Group 4
- Wiring Bay 1-5
1. Vietnam
2. Singapore
3. Thailand
4. Malaysia

2. Expert allocation for 2nd day competition (25/9/16)


marking - All group experts :
1. Measurement checking

3rd day competition (26/9/16)


- All group experts :
1. Installation and wire-way
2. Wiring and terminations
3. Function test
4. Circuit design

6
a. Competition area and facilities

No Matters Action
1. Location and layouts Was ready for Asean Skill Competition 2016 and
of the whole update at CIS
competition area

2. Layout of the skill Was prepared and ready for Asean Skill Competition
area: 700m2 2016 also update at CIS

5. Assessment and Marking Scheme

No Matters Action
1. Assessment allocation For electrical installation will using objective marking
and judgment to evaluating the test project. For
judgments marking has 10 item to be judging.

6. Health and Safety

No Matters Action
1. Refer to OHS Refer to host country regulation. Participant must
Regulations as ASC prepared their owned PPE requirement. Organizer
2016 Standard of will give eyewear, wall plug and half leather glove.
Health and Safety.
Document is attached.

7. Material and equipment

No Matters Action
1. Discussion of materials The infrastructure list prepared by the Competition
and equipment Organizer. Materials quantity and type (refer to IL)
suggested is attached prepared by organizer. Sponsor equipments and
tools must be use during the competition. The list of
equipment and tool has been prepared and set up
for each wiring bay on CIS forum.

7
8. Skill Promotion

No Matters Action
1. The content is Upgrade KNX skills to advance level in programming
proposed and agreed operations.
by all experts in
attached document.

9. Sustainability policy

No Matters Action

1. The actions for - Spare and balance material to be offered to


maintaining the local school.
sustainability - Use of green material such as halogen free,
recyclable and free from toxic substance.
- Material that can be reused, are to be offer to
local school.
- Project design competitor must carefully
considered sustainability as a key issue.
- All paperwork must be electronically copied.

10. Extra information:


a. TECHNICAL DESCRIPTION
No Matters Action

1. TECHNICAL - Updated
DESCRIPTION

2. MARKING SCHEME - Updated

3. COMPETITION - Updated
SCHEDULE

4. DRAW COMPETITION - Updated


WIRING BAY POSITION

8
11. Letter of information

.. .
(KUNJUNG MASEHAT) (Nguyen Quang Huy) (SOMBOON SANGTHEERATHITI)
(Indonesia) (Vietnam) (Thailand)

.. .
( VU THANH TUYEN ) ( PHICHITKACHENTR ) ( BUN HEANG )
( Vietnam ) ( Thailand ) ( Cambodia )

...
( CHY VANNY ) (CHENG SHING HAUR ) ( WINSTON CHENG )
( Cambodia ) ( Singapore ) ( Singapore )

...
( HENRY J. OCAMPO ) (EDDIE L. CABALTERA ) ( MAHEFUD ISMAIL )
( Philippines ) ( Philippines ) ( Indonesia )

...
(TRI WINAHYU HARIYADI) (KYAW MYAT KHAING ) ( Vanthong PHOTHICHAK )
(Indonesia ) ( MYANMAR ) ( LAO PDR )

...
(Phonesack XAYYALATH) ( ZAKARIA ISMAIL ) ( MAZLAN ABDULLAH )
(LAO PDR ) ( Malaysia ) ( Malaysia )

Anda mungkin juga menyukai