Limited and Homestake Gold of Australia Ltd, and is located Rock mass properties
adjacent to the City of Kalgoorlie-Boulder, Western Australia,
see Figure 1. The predominant host rock for the gold mineralisation is the
Golden Mile Dolerite (GMD). This occurs in a tight synclinal
structure surrounded by basalt, which can also be mineralised
along the contact area. Mineralisation is focused along faults
(lodes) within the dolerite and there are over 850 lodes that have
been stoped during the hundred years of underground mining on
the Golden Mile. Approximately 70 per cent of the ore occurs in
GMD and 30 per cent in the Paringa Basalt (PB). RQDs in the
GMD and PB are routinely 90 to 100 per cent. Average material
properties for are given in Table 1. The work described here
occurred predominantly within the GMD.
Blast design
In 1995 the KCGM geotechnical team initiated a review of blast
practices with a view to improving slope stability, particularly in
the vicinity of old stopes. At this time the operation had no wall
control blasting program in place. Unmodified production
blasting was carried out against pit walls with the result that
berm width and toe positions were difficult to maintain. Pit
designs regularly had to be adjusted in order to maintain safe
operating conditions.
Based on the text book premise that burden relief was the key
to minimising blast damage, four row trim blasts were
introduced. The high RQD nature of the rock mass also inspired
the introduction of pre-splits. The 25 metre width of the trim
blasts was largely determined on the practicality of blasthole rigs
being able to negotiate old underground workings routinely
encountered on benches.
Mine production viewed the trim blasts as a necessary evil.
They presented scheduling difficulties and were perceived to
cause dilution and to generally have lower productivity (flatter
muckpile). In reality the dilution could largely be controlled if
ore/waste contacts were taken into account when establishing
blast boundaries; and a comparison of dig rates often had trim
blasts as the most productive. The trim blast reserve also
provided ease of access to production blasts without the need to
provide ramps. The major drawback was thus the constraints
imposed on mine scheduling.
The wall control blasting practices that were initially
introduced consisted of:
FIG 1 - Location map and aerial view looking northward showing A presplit comprising 89 mm holes on a 1.2 m spacing, using
the Fimiston open pit operations in relation to the a decoupled explosive. The presplit was inclined with a
city of Kalgoorlie-Boulder. stand-off distance of 0.8 m to the toe of the back row
blastholes. This was fired in advance of the trim blast.
The focus of its mining activity is remnant pillar A trim blast of vertical 165 mm production holes charged
mineralisation within Kalgoorlies famous Golden Mile. Ore with heavy ANFO. The pattern was basically as for the
reserves for the Fimiston Mine, known as the Super Pit, as at production blasting at the time, ie 5.2 m burden and 5.8 m
30 June 2000 were 175.1 Mt containing 11 959 million ounces of spacing. The blast was fired with 17 ms on the control row
gold and represent a mine life of greater than 15 years. In and 100 ms on the echelon. The results were visually
calendar year 2000 the pit produced 715 164 ounces. spectacular, see Figure 2.
The final pit is expected to be 3.7 km long, 1.5 km wide and Production blasts were also free-faced, usually limited to eight
greater than 600 m deep. It should be appreciated that both in-pit to ten rows and were fired with 25 ms on the control row and
and near-pit exploration drilling programs are continuing and 100 ms on the echelon. The better directional firing with the 17
there is potential for both pit expansion and co-development of ms delays was adopted in the production blasts and remains the
underground mining. practice today. The benches were 10 m high and 1.3 m of subdrill
was used on production holes.
TABLE 1
Material properties for KCGM principal rock types.
Rock type Mean UCS Standard deviation Mean Standard deviation Mean density Standard deviation
(MPa) UCS (MPa) Youngs Modulus Youngs Modulus (kg/m3) 3
Density (kg/m )
(GPa) (GPa)
GMD 103 45 67 11 2920 150
PB 87 33 54 10 2860 -
FIG 2 - Results of four-row trim blast using 17 ms on control row and 100 ms on echelon.
Blast and monitoring set-up All holes were vertical. The blastholes were backfilled to a
A series of single blastholes of diameter 165 mm were charged depth of 10.2 m, while the monitoring holes were at depths in the
with a heavy ANFO formulation to simulate standard production range 10.2 m to 10.5 m. The six blastholes monitored were
blastholes. The blastholes were drilled on a bench at nominal loaded with the same heavy ANFO formulation. While the goal
distances from the face corresponding to one half, one and two was to achieve equal masses of explosives in each hole, in reality
burdens. The normal production blast burden distance was 5.2 m. the masses varied somewhat. However, all masses were within a
Duplicate sets of blastholes were located at each nominal burden 17 kg range and at least one hole at each burden distance had
distance, namely 2.6 m, 5.2 m and 10.4 m from the free face. explosive masses of 140 kg, enabling direct comparison without
any influence of explosive mass. The blastholes were stemmed
The technique of borehole pressure monitoring behind blasts
has been reported previously (for example Brent and Smith 1996 with imported aggregate. They were bottom primed with a 400 g
and 1999; Ouchterlony 1995; Ouchterlony et al 1996; Le Juge et primer, which was pulled up 0.5 m into the explosive while
al 1994). The methodology used in this work was the same as loading. They were also each loaded with two co-axial cables for
that reported in Brent and Smith (1996), with an array of holes velocity of detonation (VoD) monitoring. The primers were
for monitoring the pressure drilled behind each blasthole. Sets of initiated by nonelectric delay detonators. Table 2 summarises the
five pressure monitoring holes (102 mm diameter) were drilled loading details and measured VoDs from each blasthole.
on identical staggered patterns as shown schematically in Figure Each monitoring hole was viewed by a borehole video camera
3. This pattern was chosen to ensure that no two monitoring prior to the blasts. Pressure transducers were then placed in the
holes were within 3 m of each other and also to ensure that a monitoring holes, which were subsequently sealed with a gasbag
region of width corresponding to the normal trim and production at a depth of 2.2 m from the surface. The sealed holes were
blast spacing, (ie 5.8 m), was monitored behind each hole. It was monitored to check for any pressure variation before the
considered that this pattern would sample a representative region blastholes were fired. No variations were found. The transducer
of the rock mass behind each blasthole, enabling conclusions to cables were led back to the multi-channel pressure recorder,
be drawn about the possible damage effects which may be which was triggered by a break wire connected to the in-hole
expected behind each blasthole in a full production or trim blast. primer.
TABLE 2
Explosive loading details and measured VoDs for single hole trials.
Blasthole no Stemming length Explosive column Calculated explosive Cable 1 VoD Cable 2 VoD
(m) length (m) mass (kg) (km/s) (km/s)
1 (0.5 Burden) 4.3 5.9 150 5.3 5.1
2 (2 Burdens) 4.7 5.5 140 5.5 5.4
3 (2 Burdens) 5.0 5.2 130 5.2 5.3
4 (1 Burden) 4.9 5.3 140 5.3 5.5
5 (0.5 Burden) 4.7 5.5 140 5.1 5.2
6 (1 Burden) 4.7 5.5 140 5.0 5.2
Mean std. deviation 4.7 0.2 5.5 0.2 140 5.9 5.3 0.15
After the blast, the monitoring holes were cleared for borehole
video camera viewing by piercing the gasbags and retrieving
them. Generally, the two holes closest to the blasthole could not
Free face Hole position
be recovered as they were either covered by debris or too badly
damaged. A detailed program of vibration monitoring using
arrays of accelerometers was done behind each of these holes
and is reported separately by Blair and Armstrong (2001).
High-speed cinematography of the single hole blasts to view
blast performance was also carried out.
Blast performance
The single hole blasts drilled at one burden and one half a burden
all broke out to the free faces. As expected, the holes drilled at
two burdens did not break out at the free faces and formed only
surface craters, which were roughly circular. Figure 4 shows Free face
post-blast views of one set of holes. From the high-speed films of
the blasts, the blast outcomes appeared similar with no unusual Hole position
stemming or surface ejection. The VoD traces confirmed that
explosive performance in each hole was similar, with a mean of
5.3 km/s and a standard deviation of 0.15 km/s, as shown in
Table 2. Slight differences between results from the two cables
within each hole are attributable to variations in cable tension
and some twisting, while differences between holes may also be
attributed to slight variations in explosive density and hole
dimensions.
10.0
0.0
-10.0
-30.0
-40.0
-50.0
-60.0
-70.0
-80.0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
Time (s)
FIG 5 - Borehole pressure trace from a monitoring hole located 5.2 m behind one of the single blastholes.
60.0
40.0
20.0
Pressure (kPa)
0.0
-20.0
-40.0
-60.0
-80.0
0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
Time (s)
FIG 6 - The only trace that showed a positive pressure, from the hole located at 2.6 m behind blasthole 3. Note the initial underpressure.
5.6m 10
Pre-Blast Cracks-Trim Blast
7.4m Pre-Blast Cracks -Production Blast
8 Post-Blast Cracks-Trim Blast
9.6m Post-Blast Cracks-Production Blast
No. of visible cracks
6
5.8 m
4
0
5 10 15 20 25
10 m
Distance from blasthole (m)
15m
20m
FIG 10 - Number of cracks clearly visible with the borehole video camera
5.8 m 3m inspections before and after the trim and production blasts.
Pressure monitoring holes The vibration monitors recorded vector peak particle
Video inspection holes
accelerations in excess of 40 m/s2 behind both blasts and vector
peak particle velocities of approximately 250 mm/s (11 m behind
Accelerometer array the trim blast) and 150 mm/s (23 m behind the production blast).
These monitors were located behind the furthest pressure
monitoring holes, hence the actual levels at the monitoring holes,
FIG 8 - Schematic layout of monitoring behind the trim blast (top) particularly those much closer to the blastholes, would be
and the production blast (bottom). expected to be considerably higher. Blair and Armstrong (2001)
report similar vibration levels behind another trim blast in this
pit, both from a predictive model and direct measurement.
Borehole pressure monitoring
DISCUSSION AND CONCLUSIONS
The borehole pressure monitoring for these blasts resulted in
similar underpressures being recorded, with a similar form to that The negative peak pressures recorded in the monitoring holes
shown previously. The peak pressures measured in the and the decrease in their magnitude with distance have been
monitoring holes behind both blasts are summarised in Figure 9. observed in similar studies before. These effects are attributed to
Borehole video camera inspections revealed the formation of the formation of new voids (cracks) and the overall rock mass
new visible cracks or discontinuities in the walls of the dilation behind the blasts (Brent and Smith, 1996; 1999;
monitoring holes after the blasts. The number of cracks visible Ouchterlony, 1995; LeJuge et al, 1994). The measurement of
with the camera both before and after the blasts is summarised in these differential pressures may be likened to strain
Figure 10. The sampled area behind the production blast had a measurements using extensometers that detect the extent of
larger number of pre-existing cracks and also a correspondingly dynamic dilation.
larger number of post-blast cracks, however the number of new The borehole video camera records for the trim and production
cracks formed for each blast type is not widely dissimilar. blasts confirmed the formation of new visible cracks after these
Although the data is sparse, there is a decrease in the number of blasts. The vibration records from these blasts, as well as from
new cracks with distance behind the blasts. the single hole blasts (Blair and Armstrong, 2001), showed
hole
blasthole that had a confinement of twice the normal burden (see 1
/V
Figure 7). These results show that blast type or burden did not
significantly affect gas penetration beyond this distance.
ne w
V
In consideration of the positive pressure result, it may be taken 0.1
as an indication that gas penetration was somewhat enhanced by
the increased burden confinement. However, it is clear that
positive gas pressurisation did not extend to 5.2 m behind this, or
indeed any other, blasthole. This implies that any such increased 0.01
gas penetration would be limited to a region close to the 0 0.5 1 1.5
0.5
blastholes (ie within less than 5.2 m) and would not extend S ca le d dis ta nce (m/kg )
deeply into the 10 m wide berms. However, it is apparent from
the measured underpressures that dilation extended significantly
FIG 11 - New volume in each monitoring hole calculated from the
further than gas penetration.
measured underpressures plotted against conventional scaled distance.
The data from the single holes at various burdens, shown in
Figure 7, and from the trim and production blast, shown in
Figure 9, appear to follow a similar trend in the magnitude of the
measured negative pressures for each case of confining burden or
blast type. The new volume created within each monitoring hole 2000
during the active dilation phase may be calculated from the peak All da ta
1000
underpressures assuming a rapid adiabatic expansion of the air in Burde n=5.2 m
Burde n=10.4 m
the holes as described by Brent and Smith (1999). VP PV (mm/s )
Burde n=2.6 m
This new volume formed during the dilation phase has been
proposed as a relative indicator of rock damage at the monitoring
hole locations (Brent and Smith, 1999). This is based on the
assumption that increased dilation or expansion of the 100
monitoring hole volume is related to increased voidage or
rupturing (cracking) processes within the rock mass surrounding
the monitoring hole. Such rupturing may be at random
20
orientations within the rock mass and may preferentially occur at
0 1 2 3 4 5 6 7 8
interfaces such as free faces, inclusions, or joints, or at weak
points within the rock mass, or may be part of large cracks that S ca le d dis ta nce (m/kg
0.5
)
originate at nearby blastholes. Although the expansion is
transient and the measured pressures recover to ambient, such
rupture processes are irreversible and damage remains. Hence the FIG 12 - Measured vibration levels (vector peak particle velocities)
relative magnitude of the new volume created during expansion behind the single blastholes of varying burden.
is used here as an indicator of the overall extent of dilation and
rupturing at the monitoring hole location. This is plotted against
the conventional scaled distance in Figure 11. As may be is consistent with this, since the rock dilation (hence damage)
expected from this type of measurement there is much scatter in detected by the borehole pressure technique may be expected to
the data, however it has been fitted with a power curve of the relate to vibration levels in the near field, and it was also found
same form as is usually used for blast vibration data, namely: to be independent of blasthole burden over the range tested.
In summary, the following conclusions were drawn from the
Vnew/Vhole = a (scaled distance)-b trials, in conjunction with the comprehensive studies on vibration
where by Blair and Armstrong (2001):
Vnew = new volume created at peak dilation (m3) there was no dependence of vibration levels on blasthole
burden, or blast type;
Vhole = original monitoring hole volume (m3)
positive pressurisation by gases did not extend to 5.2 m or
scaled distance = distance (m) [charge mass (kg)]-0.5 beyond, regardless of blasthole burden or blast type;
a,b = constants found by regression rock dilation, as indicated by monitoring hole
A formal statistical analysis of the data was conducted underpressures, extended much further than the gas and
following the methods outlined by Draper and Smith (1981). It similarly showed no dependence on blasthole burden or blast
was found that the all the data (linearised by using logarithms), is type;
best fit by a single line and hence treated as a single data set. The new crack formation visible with a borehole camera under
test was conducted at the 0.01 significance level. the trial conditions occurred to a similar extent behind the
The conclusion for this data set concurs with the findings of production and trim blast, and could not be discerned behind
Blair and Armstrong (2001). Their vibration data for the single the single hole blasts regardless of burden, and
hole trials is shown in Figure 12. By applying various statistical the apparent scaled distance dependence both of vibration
techniques to their data, including those of Draper and Smith and rock dilation, measured from borehole underpressures,
(1981), they found no significant difference between the data sets indicated the importance of explosive charge masses in
for the three cases of burden, clearly demonstrating that the damage control.
vibration was independent of burden in these cases. Our finding
These conclusions indicated that blast configurations with Brent, G F and Smith, G E, 1996. Borehole pressure measurements
increased burdens, or apparent burdens (due to choking), would behind blast limits as an aid to determining the extent of rock
not result in increased vibration levels or increased penetration damage, in Proceedings Fifth International Symposium on Rock
Fragmentation by Blasting - Fragblast 5 (Ed: B Mohanty) pp
by explosive gases. Hence no significant increase in damage to 103-112 (Balkema: Rotterdam).
the pit walls was anticipated and choked blasting, or the use of
Brent, G F and Smith, G E, 1999. The detection of blast damage by
larger blasts with more rows of blastholes, would be acceptable. borehole pressure measurement, in Proceedings Sixth International
It was recommended that the mine trial the use of production Symposium on Rock Fragmentation by Blasting - Fragblast 6, pp
blasts, with modified charge masses in the back rows, in 9-13 (South African Institute of Mining and Metallurgy:
preference to smaller dedicated free face trim blasts. Further, it Johannesburg).
was recommended that the general practice of choking blasts Dowding, C H, 1996. Construction Vibrations, p 494 (Prentice Hall: New
would not be detrimental to the pit walls. Jersey).
As a result, dedicated free face trim blasts have been Draper, N R and Smith, H, 1981. Applied Regression Analysis, second
edition, pp 241-246 (Wiley: New York).
eliminated. KCGM now carries out modified production blasts,
(following pre-splitting), against all walls with the direction of Du Pont, 1980. Blasters Handbook, pp 423-434 (E I du Pont de
Nemours & Co: Delaware).
firing being along the wall strike (following the main lode trend).
The number of rows in production blasts is now only constrained Floyd, J L, 1999. Explosive energy relief - The key to controlling
overbreak, in Proceedings Explo 99 (Ed: C Workman-Davies) pp
by production requirements and site-specific issues. The 147-154 (The Australasian Institute of Mining and Metallurgy:
elimination of conventional dedicated trim blasts and the Melbourne).
introduction of choke blasting has had no quantifiable Hoek, E and Bray J, 1974. Rock Slope Engineering, pp 234-240
detrimental effect on the pit wall stability. (Institution of Mining and Metallurgy: London).
However, caution should be exercised in generalising all these Langefors, U and Kihlstrm, B, 1967. The Modern Technique of Rock
conclusions to other mine sites and conditions without prior Blasting, pp 296-321 (John Wiley and Sons Inc: New York.)
measurement. LeJuge, G E, Lubber, E, Sandy, D A and McKenzie, C K, 1994. Blast
damage mechanisms in open cut mining, in Proceedings Open Pit
Blasting Workshop 94, pp 96-103 (Curtin University: Perth).
ACKNOWLEDGEMENTS
Ouchterlony, F, 1995. Review of rock blasting and explosives
The authors thank personnel from KCGM Fimiston Mine, Roche engineering research at SveBeFo, in Proceedings Explo 95, pp
Mining (contractor on site until end 1999) and Orica Limited for 133-146 (The Australasian Institute of Mining and Metallurgy:
their cooperation and assistance during this work, in particular Melbourne).
Ian Brunton, Dane Blair, Les Armstrong, Dave Kay and Sahul Ouchterlony, F, Nie, S, Nyberg, U and Deng, J, 1996. Monitoring of large
open cut rounds by VOD, PPV and gas pressure measurements, in
Rafiudeen. KCGM and Orica Limited are thanked for permission
Proceedings Fifth International Symposium on Rock Fragmentation
to publish this paper. It is recognised that the establishment of a by Blasting - Fragblast 5 (Ed: B Mohanty) pp 167-176 (Balkema:
strict experimental protocol was key to the success of the blast Rotterdam).
improvement program which lead to the implemented solutions. Singh, S P, 1993. Prediction and determination of explosive induced
damage, in Proceedings Fourth International Symposium on Rock
REFERENCES Fragmentation by Blasting - Fragblast 4 (Ed: H P Rossmanith) pp
183-192 (Balkema: Rotterdam).
Blair, D P and Armstrong, L W, 2001. The influence of burden on blast
vibration, paper submitted to Fragblast - Int J for Blasting and
Fragmentation (Balkema: Rotterdam).