ON
SITE VISIT OF
ELEVATED ROAD
BY
AMIT SONI
2015A2PS763P
AT
JAIPUR DEVELOPMENT
AUTHORITY(Jda),jaipur
June 16,2017
ACKNOWLEDGEMENT
I have taken sincere efforts in this project.
However, it would not have been possible
without the kind support and help of many
individuals and organizations. I would like to
extend our thanks to all of them. I am highly
indebted to Jaipur Development Authority for
their guidance and constant supervision as well
as for providing us with information regarding
the project and also for their support in
completing the project. I would also like to
express my gratitude towards Mr. Prem Kumar
for his kind co-operation and encouragement
which helped us in completion of this project.
INTRODUCTION
v) Precast cable ducts and covers. The top of duct cover should
have proper neat cement finish as per drawing
5) MISCELLANIOUS:-
,
CONSTRUCTION MATERIALS
WATER:- Water to be used for mixing and curing shall be clear and
free from injurious amounts of oils, acids, alkalis, salts, sugar, organic
materials or othersubstances that may be deleterious to concrete or steel.
Potable water is generally considered satisfactory for mixing concrete.
Only design mix concrete shall be used in the work. The design mix
concrete shall have the minimum compressive strength of 150 mm cubes
at 28 days according to the denomination of the grade the concrete e.g.
M 35 grade concrete shall have the minimum characteristic compressive
strength of 35 Mpa. The determination of the cement, aggregates and
water to attain the strength specified in clause 5.11.1 above shall be
made by designing the concrete mix in accordance with IS: 10262. The
trial mixes for mix design shall be prepared with approved aggregates,
cement and water. Coarse aggregates of different sizes shall be
combined in suitable proportion so as to result in an overall grading
conforming to IS : 383.
Fly ash will not be allowed to be used in the mix. Minimum six cubes
shall be prepared from each trial mix for testing compressive strength at
28 days. In proportioning concrete the quantity of both cement and
aggregates shall be determined by weight. The cement shall be weighed
separately from the aggregates. Water shall either be measured by
volume in calibrated tanks or weighed. All measuring equipment shall
be maintained in a clean and serviceable condition. The amount of
mixing water shall be adjusted to compensate for moisture content in
both coarse and fine aggregates. The moisture content in both coarse and
fine aggregates shall be determined in accordance with IS : 2386 (Part-
III). Suitable adjustments shall also be made in the weights of aggregates
to allow for the variation in weight of aggregates due to variation in
moisture content.
PILE CONCRETING
1. The concrete placing shall not proceed if density of fluid near about
the bottom of borehole exceeds 1250 kg/m3.
2. Determination of the density of the drilling mud from the base of the
borehole shall be carried out by taking samples of fluid by suitable
slurry sample approved by the engineer in charge, in first few piles
and at suitable interval of piles thereafter and the results recorded.
3. After flushing is completed, tremie head should be removed and
funnel should be attached to the tremie pipe.
4. The slump of the concrete will be maintained at 150 mm to 200 mm.
5. Concreting operation will be carried out using the 200 mm diameter
trmie pipes.
6. Initial charge of concrete should be given in the funnel using a plug.
Total concrete quantity in the funnel should be more than the volume
of the entire pipe plus free space below the tremie. This will ensure a
water tight concrete pouring through tremie.
7. Lifting and lowering is repeated keeping sufficient concrete in funnel
all the time. As the concreting proceeds the tremie pipe are to be
removed one by one, taking care that the tremie pipe has sufficient
embedment in the concrete until the whole pipe is concreted.
Sufficient head of green concrete shall be maintained to prevent
inflow of soil or water in to concrete. Placing of concrete shall be a
continuous process from the toe level to top of pile.
8. The concrete is poured in the funnel. As the concrete reaches the top
of the funnel, the plug is lifted up to allow the concrete to flow
corresponding to the placing of each batch of concrete.
9. The concreting of pile is to be done up to minimum of 300 mm
above the cut off level to get good and sound concrete at cut off
level.
10. After completion of concreting tremie, funnel and other
accessories are to be washed properly and kept greased in proper
stacking condition near next pile location.
11. While doing under water concreting 10% extra cement over and
above the design mix requirement should be added in each batch.
THE END
REFERENCES
http://civilblog.org/
http://TheConstructor.org