REEMPLAZO DE LINEA DE AGUA DE PAMPA DE VACA-CAPILLUNE

J.R.VERSAC: Construcciones y Montajes Electromecnicos


Week Ending : 02/12/2007

Physical % of Work
Jobhours Physical % WEEKS
WORK ITEM Item
Contract Weight of Job
Pay Item No. Description Base Sched Actual Complete Cut off Date 17-Sep 24-Sep 01-Oct 08-Oct 15-Oct 22-Oct 29-Oct 05-Nov 12-Nov 19-Nov 26-Nov 03-Dic 10-Dic 17-Dic 24-Dic 31-Dic 07-Ene 14-Ene 21-Ene 28-Ene 04-Feb 11-Feb 18-Feb 25-Feb 03-Mar 10-Mar 17-Mar 24-Mar 31-Mar 07-Abr 14-Abr

Week No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

GESTION ADMINISTRATIVA EN LIMA - PRE OPERACIONES 1,820.00 1.47% 100.00% 89.15% 1.31%
Nue. Programado 0.00% 10.00% 15.52% 53.98% 83.10% 86.40% 88.87% 89.15% 89.15% 89.15% 89.15% 89.15% 89.15%
Reprogramacion
OBRAS CIVILES Actual 0.00% 25.00% 50.00% 75.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
OBRAS PRELIMINARES 12,491.00 10.09% 100.00% 58.80% 5.93%
Nue. Programado 0.00% 0.00% 13.57% 36.77% 44.22% 45.29% 48.43% 49.30% 49.30% 49.30% 60.40% 58.80% 58.80%
Reprogramacion
Actual
2 5

0.00% 0.00% 0.00% 0.00% 0.00% 25.00% 50.00% 75.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100%
MOVIMIENTO DE TIERRAS 23,832.00 19.25% 38.89% 55.00% 10.59%
Nue. Programado 0.00% 0.00% 0.00% 0.18% 0.74% 1.09% 1.87% 2.36% 4.62% 12.85% 18.20% 38.00% 55.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 5.56% 11.11% 16.67% 22.22% 27.78% 33.33% 38.89% 44.44% 50.00% 55.56% 61.11% 66.67% 72.22% 77.78% 83.33% 88.89% 94.44% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CONCRETO SIMPLE 672.00 0.54% 27.78% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion

CONCRETO ARMADO Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.56% 11.11% 16.67% 22.22% 27.78% 33.33% 38.89% 44.44% 50.00% 55.56% 61.11% 66.67% 72.22% 77.78% 83.33% 88.89% 94.44% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CAJAS BY PASS Y CAUDALOMETRO 331.00 0.27% 100.00% 7.55% 0.02%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7.55% 7.55% 90%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CAJAS TIPO 1 AL 4 1,899.00 1.53% 15.79% 3.02% 0.05%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3.02% 3.02%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.26% 10.53% 15.79% 21.05% 26.32% 31.58% 36.84% 42.11% 47.37% 52.63% 57.89% 63.16% 68.42% 73.68% 78.95% 84.21% 89.47% 94.74% 100.00% 100.00% 100.00% 100.00%
CAJAS DE VALVULAS DE CONTROL 1 AL 5 1,067.00 0.86% 15.79% 1.99% 0.02%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1.99% 0.00% 0.00% 1.99% 1.99%
Reprogramacion
Actual 2 0

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5.26% 10.53% 15.79% 21.05% 26.32% 31.58% 36.84% 42.11% 47.37% 52.63% 57.89% 63.16% 68.42% 73.68% 78.95% 84.21% 89.47% 94.74% 100.00% 100.00% 100.00% 100.00% 80%
APOYOS DE CONCRETO EN TUNEL 374.00 0.30% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 16.67% 33.33% 50.00% 66.67% 83.33% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CAMARA DE CARGA 1,010.00 0.82% 100.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CONCRETO EN APOYOS DE PUENTE 144.00 0.12% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 70%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CONCRETO EN BLOQUES DE ANCLAJE 2,086.00 1.69% 33.33% 0.58% 0.01%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.58% 0.58%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.67% 13.33% 20.00% 26.67% 33.33% 40.00% 46.67% 53.33% 60.00% 66.67% 73.33% 80.00% 86.67% 93.33% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
ESTRUCTURAS METALICAS 1,200.00 0.97% 100.00% 37.50% 0.36%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 37.50% 37.50%
Reprogramacion
Actual 1 5

0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25.00% 50.00% 75.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 60%
CARPINTERIA METALICA 5,781.00 4.67% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
TRABAJOS PARA PROTECCION CATODICA 1,338.00 1.08% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25.00% 50.00% 75.00% 100.00% 0.00% 0.00% 30.00% 40.00% 75.00% 150.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
VARIOS 363.00 0.29% 20.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
50%
CANAL DE REBOSE Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.67% 13.33% 20.00% 26.67% 33.33% 40.00% 46.67% 53.33% 60.00% 66.67% 73.33% 80.00% 86.67% 93.33% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
OBRAS PRELIMINARES 5,120.00 4.14% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
MOVIMIENTO DE TIERRAS Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
EXCAVACION AL INICIO 408.00 0.33% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
EXCAVACION EN PLATAFORMA DE CANAL 2,216.00 1.79% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
1 0

40%
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
EXCAVACION AL FINAL 256.00 0.21% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
CONCRETO ARMADO Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CAJON DE INGRESO 570.00 0.46% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CAJON DE SALIDA 529.00 0.43% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 30%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
CAJON DE SALIDA 213.00 0.17% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
REVESTIMIENTO DEL CANAL 6.00 0.00% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
OBRAS MECNICAS Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25.00% 50.00% 75.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
TUBERIAS 33,919.00 27.40% 37.50% 16.00% 4.38%
Nue. Programado
5

0.00% 0.00% 0.54% 0.90% 1.75% 2.71% 3.37% 5.12% 5.65% 6.70% 10.03% 16.00% 16.00% 20%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6.25% 12.50% 18.75% 25.00% 31.25% 37.50% 43.75% 50.00% 56.25% 62.50% 68.75% 75.00% 81.25% 87.50% 93.75% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
TRABAJOS PARA BY PASS 872.00 0.70% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 50.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
OTROS 6,572.00 5.31% 44.44% 12.78% 0.68%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 12.17% 12.78%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 38.89% 44.44% 50.00% 55.56% 61.11% 66.67% 72.22% 77.78% 83.33% 88.89% 94.44% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
REBOSE DE TANQUE DE 500,000 GL 1,810.00 1.46% 0.00% 0.00% 0.00% 10%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
OBRAS ELECTRICAS Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 25.00% 50.00% 75.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
SISTEMA DE PROTECCION CATODICA 16,800.00 13.57% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
OBRAS INSTRUMENTACION Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7.69% 15.38% 23.08% 30.77% 38.46% 46.15% 53.85% 61.54% 69.23% 76.92% 84.62% 92.31% 100.00% 100.00% 100.00% 100.00% 100.00%
OBRAS DE INSTRUMENTACION 81.00 0.07% 0.00% 0.00% 0.00%
Nue. Programado 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
Reprogramacion
Actual 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 16.67% 33.33% 50.00% 66.67% 83.33% 100.00% 100.00%
0

0%
TOTAL ######### 100.00% 23.35% 17-Sep 24-Sep 01-Oct 08-Oct 15-Oct 22-Oct 29-Oct 05-Nov 12-Nov 19-Nov 26-Nov 03-Dic 10-Dic 17-Dic 24-Dic 31-Dic 07-Ene 14-Ene 21-Ene 28-Ene 04-Feb 11-Feb 18-Feb 25-Feb 03- 10- 17- 24- 31- 07-Abr 14-Abr

70

60
Scheduled Direct Men Actual Direct Men

50
Number of Men

40

30

20

10

0 1 7 - Se p 2 4 - Se p 0 1 - O c t 0 8 - O c t 1 5 - O c t 2 2 - O c t 2 9 - O c t 0 5 - No v 1 2 - No v 1 9 - No v 2 6 - No v 0 3 - D ci 1 0 - D ci 1 7 - D ci 2 4 - D ci 3 1 - D ci 0 7 - En e 1 4 - En e 2 1 - En e 2 8 - En e 0 4 - Fe b 1 1 - Fe b

MANPOWER ACUMULADO
Scheduled - Staff & Supervision (men) 2 4 4 4 4 5 5 5 5 5 5 5 5 5 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Scheduled - Support & Maintenance (men) 5 7 8 8 8 8 8 9 9 10 10 10 10 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Scheduled - Direct (men) 4 10 11 12 16 21 21 21 21 31 31 31 51 51 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Total - Scheduled (A+B+C) 11 21 23 24 28 34 34 35 35 46 46 46 66 66 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Actual - Staff & Supervision (men) 5 5 5 5 5 5 5 5 5 5 5 5 5 5 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Actual - Support & Maintenance (men) 9 9 9 9 9 9 9 9 9 9 10 10 10 10 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Actual - Direct (men) 16 16 16 22 24 24 38 38 38 38 50 50 50 50 50 50 50 50 46 46 44 44 32 32 24 24 22 20 20 20 20
Total - Actual (H + I + J) 30 30 30 36 38 38 52 52 52 52 65 65 65 65 65 65 65 65 61 61 59 59 47 47 39 39 37 35 35 35 35
JOB HOURS - DIRECT LABOR
Scheduled - Period 455 455 455 455 4,187 4,187 7,014 7,591 9,841 10,030 7,027 6,693 5,025 5,334 6,626 11,808 6,892 7,548 7,472 6,934 6,765 6,386 2,409 2,409 1,962 1,925 1,471 178 14 14 0
Scheduled - Cumulative 455 910 1,365 1,820 6,007 10,195 17,209 24,800 34,641 44,671 51,698 58,391 63,416 68,749 75,375 87,183 94,075 101,623 109,095 116,029 122,793 129,180 131,588 133,997 135,959 137,883 139,354 139,532 139,546 139,559 139,559
Actual - Period (Expended)
Actual - Cumulative (Expended) 455 910 1,365 1,820 6,007 10,195 17,209 24,800 34,641 44,671 51,698 58,391 63,416 68,749 75,375 87,183 94,075 101,623 109,095 116,029 122,793 129,180 131,588 133,997 135,959 137,883 139,354 139,532 139,546 139,559 139,559
% COMPLETE
Scheduled - Physical % of Job Complete
Actual - Physical % of Job Complete 0.0% 0.00% 0.37% 0.74% 1.10% 1.47% 5.06% 10.37% 16.14% 22.56% 26.61% 32.31% 34.89% 38.37% 42.42% 49.64% 61.32% 67.12% 72.10% 77.56% 82.58% 87.47% 92.05% 94.69% 96.27% 97.48% 98.66% 99.84% 99.98% 99.99% 100.00% 100.00%
Nueva Contractual 0.00% 0.00% 0.15% 1.75% 4.78% 6.31% 6.80% 7.48% 8.14% 8.74% 10.60% 13.66% 20.05% 23.35%
Reprogramacion

Curva_S_Linea_de_Agua_Pampa_de_Vaca- al 09-12-07.xls / Curva de Progreso