MATERIALES 3,782.44
Bloque de concreto de 10x20x40 c/u 501.00 5.80 2,905.80
Mortero M3 0.82
Cemento gris bolsa 10.18 32.74 333.29
Arena de rio m3 1.15 55.00 63.25
Concreto 210 kg/cm2 M3 0.00
Cemento gris bolsa 0.00 32.74 0.00
Arena de rio m3 0.00 55.00 0.00
Grava triturada m3 0.00 150.00 0.00
Agua potable m3 0.00 0.00
Hierro de refuerzo
Hierro liso No. 2 qq 0.65 195.00 126.18 RESUMEN
Hierro corrugado No. 3 qq 1.53 195.00 297.78
Hierro corrugado No. 4 qq 0.00 195.00 0.00 COSTO UNITARIO TOTAL POR M2
Hierro corrugado No. 5 qq 0.00 195.00 0.00 COSTOS DIRECTOS 186.74 /M2
Alambre de amarre libra 1.91 3.00 5.73 COSTOS INDIRECTOS 0.75 /M2
Clavo de hierro libra 0.00 3.00 0.00 SUB TOTAL 187.49 /M2
Clavo de acero c/u 10.00 0.40 4.00 ( + ) I.V.A 0.00 /M2
Cuarton de pino vara 3.68 9.50 34.96 COSTO UNITARIO 187.49 /M2
Costanera de pino vara 0.00 4.50 0.00
Regla pacha de pino vara 3.82 3.00 11.45 COSTO UNITARIO TOTAL POR ML 9.20
EQUIPO 365.45
Alquiler de andamios metalico ML 9.20 30.00 276.00
Concretera de 1 bolsa h-m 0.00 27.00 0.00
Herramienta pequea S.G. 1.00 89.45 89.45