FOUNDATION CALCULATION SHEET

One-Stop Solution for Foundation

TITLE DESCRIPTION
PROJECT/JOB NO. WEST SUMBAWA CFSPP PROJECT 2X7 MW
PROJECT/JOB NAME PLTU SUMBAWA BARAT 2X7 MW
CLIENT NAME PT PLN (Persero) UIP KITRING NUSRA
SITE NAME TALIWANG
DOCUMENT NO.
REFERENCE NO.
STRUCTURE NAME CHIMNEY STRUCTURE KSB
LOAD COMBINATION GROUP NAME
REV DATE DESCRIPTION PREP'D CHK'D APPR'D APPR'D

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 1

FOUNDATION LISTS
Group Name No. Description No. Description
CHIMNEYKSB 1 F1

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 2

CONTENTS

1. GENERAL
1.1 CODE & STANDARD
1.2 MATERIALS & UNIT WEIGHT
1.3 SUBSOIL CONDITION & SAFETY FACTORS
1.4 LOAD COMBINATION

2. DRAWING
2.1 LOCATION PLAN
2.2 DETAIL SKETCH

3. FOUNDATION DATA
3.1 FOOTING DATA
3.2 PIER DATA
3.3 SECTION DATA
3.4 LOAD CASE
3.5 LOAD COMBINATION

4. CHECK OF STABILITY
4.1 CHECK OF PILE REACTION

5. DESIGN OF FOOTING
5.1 DESIGN MOMENT AND SHEAR FORCE
5.2 REQUIRED REINFORCEMENT
5.3 ONE WAY SHEAR FORCE
5.4 TWO WAY SHEAR FORCE
5.5 PILE PUNCHING SHEAR FORCE

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 3

1. GENERAL
1.1 CODE & STANDARD
Items Description
Design Code American Concrete Institute (ACI 318) [Metric]
Horizontal Force for Wind AMERICAN SOCIETY OF CIVIL ENGINEERS [ASCE 7-02]
Horizontal Force for Seismic AMERICAN SOCIETY CIVIL ENGINEERS [ASCE 7-02]
Unit System Input : MKS, Output : MKS, Calculation Unit : IMPERIAL

1.2 MATERIALS & UNIT WEIGHT


Items Value
2
Concrete (fck : compressive strength) 250.000 kgf/cm
2
Lean Concrete (Lfck : compressive strength) 150.000 kgf/cm
2
Reinforcement (10M ~ 16M , yield strength) 2400.000 kgf/cm
2
Reinforcement (19M ~ , yield strength) 3900.000 kgf/cm
3
Rs (Soil unit weight) 1.800 ton/m
3
Rc (Concrete unit weight) 2.400 ton/m
2.000 106 kgf/cm
2
Es (Steel Modulus of Elasticity)
2
Ec (Concrete Modulus of Elasticity) 235000.000 kgf/cm

- Pile Capacity
Items Value
Pile Name CHIMNEY KSB
Footing List F1
Diameter 350 mm
Length 20 m
Thick 350 mm
Shape Square
Capacity ( Ha , Ua , Va ) 5 , 17 , 70 tonf

1.3 SUBSOIL CONDITION & SAFETY FACTORS


Items Description
Allowable Increase of Soil (Wind) 0%
Allowable Increase of Soil (Seismic) 0%
Allowable Increase of Soil (Test) 0%
Allowable Increase of Pile Horizontal (Wind) 0%
Allowable Increase of Pile Horizontal (Seismic) 0%
Allowable Increase of Pile Horizontal (Test) 0%
Allowable Increase of Pile Vertical (Wind) 0%
Allowable Increase of Pile Vertical (Seismic) 0%
Allowable Increase of Pile Vertical (Test) 0%

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 4

Allowable Increase of Pile Uplift (Wind) 0%


Allowable Increase of Pile Uplift (Seismic) 0%
Allowable Increase of Pile Uplift (Test) 0%
Safety factor against overturning for OVM1(FO1) 2
Safety factor against overturning for OVM2(FO2) 2
Safety factor against overturning for OVM3(FO3) 2
Safety factor against overturning for OVM4(FO4) 2
Safety factor against sliding for the SL1(FS1) 2
Safety factor against sliding for the SL2(FS2) 2
Safety factor against sliding for the SL3(FS3) 2
Safety factor against sliding for the SL4(FS4) 2
Friction factor (m) 0.35

1.4 LOAD COMBINATION


Comb . ID Load Combination for stability
1000 1.0 SW + .75 DL + .75 Loadtype None Title Ll
2000 1.0 SW + .75 DL + .75 Loadtype Seismic Title Slx + .75 Loadtype None Title Ll
210 1.0 SW
220 1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + .75 Loadtype Wind Title Wlx
230 1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + .75 Loadtype Wind Title Wlz
240 1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + -.75 Loadtype Wind Title Wlx
250 1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + -.75 Loadtype Wind Title Wlz
1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + .75 Loadtype Seismic Title Slx + .22 Loadtype
260
Seismic Title Slz
1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + .75 Loadtype Seismic Title Slx + -.225 Loadtype
270
Seismic Title Slz
1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + -.75 Loadtype Seismic Title Slx + -.225
280
Loadtype Seismic Title Slz
1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + -.75 Loadtype Seismic Title Slx + .225 Loadtype
290
Seismic Title Slz
1.0 SW + .75 Loadtype Dead Title Dl + .75 Loadtype Live Title Ll + .75 Loadtype Seismic Title Slx + .225 Loadtype
300
Seismic Title Slz + .75 Loadtype None Title Cl6
3000 1.0 SW + .75 DL + -.75 Loadtype Seismic Title Slx
4000 1.0 SW + .75 DL + 1.0 Loadtype Seismic Title Slx
5000 1.0 SW + .75 DL + .75 Loadtype None Title Ll + .3 Loadtype None Title Slz
Comb . ID Load Combination for Reinforcement
100 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + 1.3 Loadtype Wind Title Wx
110 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + 1.3 Loadtype Wind Title Wz
120 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + 1.0 Loadtype Seismic Title Ex
130 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + -1.0 Loadtype Seismic Title Ex
140 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + 1.0 Loadtype Seismic Title Ez
150 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + -1.0 Loadtype Seismic Title Ez
160 1.0 SW + .9 Loadtype Dead Title Dl + 1.3 Loadtype Wind Title Wx

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 5

170 1.0 SW + .9 Loadtype Dead Title Dl + -1.3 Loadtype Wind Title Wx


180 1.0 SW + 1.0 Loadtype Dead Title Dl + 1.3 Loadtype Wind Title Wz
190 1.0 SW + .9 Loadtype Dead Title Dl + -1.3 Loadtype Wind Title Wz
60 1.0 SW + 1.4 Loadtype Dead Title Dl
70 1.0 SW + 1.2 Loadtype Dead Title Dl + 1.6 Loadtype Live Title Ll
80 1.0 SW + 1.2 Loadtype Dead Title Dl + 1.6 Loadtype Live Title Ll + .8 Loadtype Wind Title Wx
90 1.0 SW + 1.2 Loadtype Dead Title Dl + 1.6 Loadtype Live Title Ll + .8 Loadtype Wind Title Wz

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 6

2. DRAWING
2.1 LOCATION PLAN
2.2 DETAIL SKETCH

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016 Page 7

REFERENCE DWGS
A01 NO. DWG NO. DWG TITLE

1 395

NOTES
* OUTPUT UNIT : mm

01

PLTU SUMBAWA BARAT 2X7 MW PROJECT

397

FOUNDATION LOCATION PLAN

CHIMNEY STRUCTURE KSB

SQUAD CHECK
2 396
Y PROCESS PIPING VESSELS STRUCT. ELEC. INST.

F1

Z X SCALE JOB NO. MICROFILM NO.

WEST
AS SHOWN
SUMBAWA CFSPP PROJECT 2X7 MW

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016 Page 8

2.2 DETAIL SKETCH

OUTPUT UNIT : mm

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016 Page 9

REFERENCE DWGS
NO. DWG NO. DWG TITLE
CL FOOTING

11000
1000 1000
4500x2
1000

1000
1
1 395

NOTES
* PILE
16-350 CHIMNEY KSB
* OUTPUT UNIT : mm
CL FOOTING

4500x2

3000x3
11000

397

PLTU SUMBAWA BARAT 2X7 MW PROJECT


1000

1000
2 396
FOUNDATION DETAIL FOR

F1
1000 1000
3000x3

SQUAD CHECK
FOUNDATION PLAN PROCESS PIPING VESSELS STRUCT. ELEC. INST.

SCALE JOB NO. MICROFILM NO.

REV. DATE DESCRIPTION DRWNCHKDAPPDAPPDAPPD


WEST
AS SHOWN
SUMBAWA CFSPP PROJECT 2X7 MW

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016 Page 10

REFERENCE DWGS
NO. DWG NO. DWG TITLE

CL FOOTING

TOP BOTTOM

TYP.
50
NOTES
* PILE
16-350 CHIMNEY KSB
* OUTPUT UNIT : mm
16M@200

16M@200
PLTU SUMBAWA BARAT 2X7 MW PROJECT

FOUNDATION DETAIL FOR

F1
16M@200
16M@200

SQUAD CHECK
REINFORCEMENT PLAN PROCESS PIPING VESSELS STRUCT. ELEC. INST.

SCALE JOB NO. MICROFILM NO.

REV. DATE DESCRIPTION DRWNCHKDAPPDAPPDAPPD


WEST
AS SHOWN
SUMBAWA CFSPP PROJECT 2X7 MW

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016 Page 11

2 397 396

1 395

500
800
397

LEAN CONC. 50 THK

2 396 ELEVATION S1 - X

OUTPUT UNIT : mm

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016
F1 Item No. Page 12

1 2 395
600 600 600
50 50 50
62.5 62.5 62.5 62.5
TYP. TYP. TYP.
475 475

62.5

62.5
475

475
13M 13M 13M

62.5

62.5
10-19M 10-19M 10-19M

75 PR.

75 PR.
30 GR.

30 GR.

30 GR.
70

70

70
13M 100

13M 100

13M 100
@150

@150

@150
800

800

800
19M 75 19M 19M

75

75
396 397
600 3500
50 50
62.5 62.5 1512.5 1512.5
TYP. TYP.
475 475
62.5

1512.5 1512.5
475

475
13M 13M
62.5

10-19M 70-19M
75 PR.

75 PR.
30 GR.

30 GR.
70

70
13M 100

13M 100
@150

@150
800

800

19M 19M
75

75

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 13

3. FOUNDATION DATA
3.1 FOOTING DATA
Unit : mmFt. Name F1
Ft. Type MAT
2
11000 Area 121.000 m
Ft. Thickness 800.00 mm
3
Ft. Volume 96.800 m
1 395
Ft. Weight 232.320 tonf
Soil Height 500.00 mm
3
Soil Volume 55.124 m
Soil Weight 99.223 tonf
11000

Buoyancy Not Consider


Self Weight (except Pr.SW) 331.543 tonf
397

800
500

2 396 800

The Origin coordinate


The Center of Gravity & Pile (0,0) mm

3.2 PIER DATA


Off X , Off Y is offset position from the Center of the footing
If Pier Shape is Circle or Circle wall, Pl is a Diameter. and Pw is a Inner Diameter
Area is pier concrete area
Weight is pier and inner soil weight in case circle wall except Tank1 Type(Circle Ring Footing Shape)
2
Unit( Length : mm , Weight : tonf , Area : m )
Ft.Name Pr.Name Shape Pl Pw Ph Area Weight Off X Off Y
1 Circle 600.000 600.000 800.000 0.283 0.543 -4500.000 4500.000
2 Circle 600.000 600.000 800.000 0.283 0.543 -4500.000 -4500.000
F1 395 Circle 600.000 600.000 800.000 0.283 0.543 4500.000 4500.000
396 Circle 600.000 600.000 800.000 0.283 0.543 4500.000 -4500.000
397 Circle 3500.000 3500.000 800.000 9.621 18.473 0.000 0.000

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 14

3.3 SECTION DATA


Ft.Name / Sec.Name F1 / S1

11000 Unit : mm
11000

2
Direction All Direct Section Area 121.000 m
3
F.Volume 96.800 m F.Weight 232.320 tonf
3
S.Volume 55.124 m S.Weight 99.223 tonf
Pier Wt 20.644 tonf Total Weight 352.187 tonf

3.4 LOAD CASE


Fz
Fy
Mz
Input the point loads in the global coordinate system direction. Positive directions of moments (shown in the sketch) are
My based on the right hand rule.
Fx
Mx

Index Load Case Name


1 SW
2 Loadtype Seismic Title Slx
3 Loadtype None Title Dl
4 Loadtype None Title Ll
5 Loadtype None Title Wlx
6 Loadtype None Title Slz
7 DL

Unit( tonf , tonf-m )


Ft.Name Pr.Name Load Case Fx Fy Fz Mx My
1 0.000 0.000 -0.543 0.000 0.000
2 12.500 -3.137 89.625 0.000 0.000
3 -0.687 0.592 -11.436 0.000 0.000
1 4 -0.338 0.261 -7.435 0.000 0.000
5 5.767 -1.416 40.465 0.000 0.000
F1 6 0.862 -2.567 19.141 0.000 0.000
7 0.000 0.000 0.000 0.000 0.000
1 0.000 0.000 -0.543 0.000 0.000
2 12.506 3.140 89.653 0.000 0.000
2
3 -0.687 -0.592 -11.436 0.000 0.000
4 -0.338 -0.261 -7.435 0.000 0.000

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 15

5 5.770 1.418 40.480 0.000 0.000


6 -0.862 -2.567 -19.141 0.000 0.000
7 0.000 0.000 0.000 0.000 0.000
1 0.000 0.000 -0.543 0.000 0.000
2 12.500 3.137 -89.625 0.000 0.000
3 0.687 0.592 -11.436 0.000 0.000
395 4 0.338 0.261 -7.435 0.000 0.000
5 5.767 1.416 -40.465 0.000 0.000
6 -0.862 -2.567 19.141 0.000 0.000
7 0.000 0.000 0.000 0.000 0.000
1 0.000 0.000 -0.543 0.000 0.000
2 12.506 -3.140 -89.653 0.000 0.000
3 0.687 -0.592 -11.436 0.000 0.000
396 4 0.338 -0.261 -7.435 0.000 0.000
5 5.770 -1.418 -40.480 0.000 0.000
6 0.862 -2.567 -19.141 0.000 0.000
7 0.000 0.000 0.000 0.000 0.000
1 0.000 0.000 -18.473 0.000 0.000
397
7 0.000 0.000 -90.000 0.000 0.000
Footing SW 0.000 0.000 -331.543 0.000 0.000

3.5 LOAD COMBINATION


In Pier Top In Footing Bottom In Footing Bottom Center
without Self Weight with Pier Self Weight, with Pier & Footing Self Weight & Soil Weight,
But without Footing Self Weight, Case PileType
in centroid of Pile Group
Case NonPileType
in centroid of Footing

3.5.1 Load Combination in Pier Top (Without SW)


Unit( tonf , tonf-m )
Ft.Name Pr.Name L.Comb. SFx SFy SFz SMx SMy
F1 1000 -0.253 0.196 -5.576 0.000 0.000
2000 9.122 -2.157 61.643 0.000 0.000
210 0.000 0.000 0.000 0.000 0.000
220 0.000 0.000 0.000 0.000 0.000
230 0.000 0.000 0.000 0.000 0.000
240 0.000 0.000 0.000 0.000 0.000
1
250 0.000 0.000 0.000 0.000 0.000
260 9.375 -2.353 67.219 0.000 0.000
270 9.375 -2.353 67.219 0.000 0.000
280 -9.375 2.353 -67.219 0.000 0.000
290 -9.375 2.353 -67.219 0.000 0.000
300 9.375 -2.353 67.219 0.000 0.000

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 16

3000 -9.375 2.353 -67.219 0.000 0.000


4000 12.500 -3.137 89.625 0.000 0.000
5000 0.005 -0.574 0.166 0.000 0.000
100 0.000 0.000 0.000 0.000 0.000
110 0.000 0.000 0.000 0.000 0.000
120 0.000 0.000 0.000 0.000 0.000
130 0.000 0.000 0.000 0.000 0.000
140 0.000 0.000 0.000 0.000 0.000
150 0.000 0.000 0.000 0.000 0.000
160 0.000 0.000 0.000 0.000 0.000
170 0.000 0.000 0.000 0.000 0.000
180 0.000 0.000 0.000 0.000 0.000
190 0.000 0.000 0.000 0.000 0.000
60 0.000 0.000 0.000 0.000 0.000
70 0.000 0.000 0.000 0.000 0.000
80 0.000 0.000 0.000 0.000 0.000
90 0.000 0.000 0.000 0.000 0.000
1000 -0.253 -0.196 -5.576 0.000 0.000
2000 9.126 2.159 61.663 0.000 0.000
210 0.000 0.000 0.000 0.000 0.000
220 0.000 0.000 0.000 0.000 0.000
230 0.000 0.000 0.000 0.000 0.000
240 0.000 0.000 0.000 0.000 0.000
250 0.000 0.000 0.000 0.000 0.000
260 9.379 2.355 67.240 0.000 0.000
270 9.379 2.355 67.240 0.000 0.000
280 -9.379 -2.355 -67.240 0.000 0.000
290 -9.379 -2.355 -67.240 0.000 0.000
300 9.379 2.355 67.240 0.000 0.000
3000 -9.379 -2.355 -67.240 0.000 0.000
4000 12.506 3.140 89.653 0.000 0.000
2 5000 -0.512 -0.966 -11.319 0.000 0.000
100 0.000 0.000 0.000 0.000 0.000
110 0.000 0.000 0.000 0.000 0.000
120 0.000 0.000 0.000 0.000 0.000
130 0.000 0.000 0.000 0.000 0.000
140 0.000 0.000 0.000 0.000 0.000
150 0.000 0.000 0.000 0.000 0.000
160 0.000 0.000 0.000 0.000 0.000
170 0.000 0.000 0.000 0.000 0.000
180 0.000 0.000 0.000 0.000 0.000
190 0.000 0.000 0.000 0.000 0.000
60 0.000 0.000 0.000 0.000 0.000
70 0.000 0.000 0.000 0.000 0.000
80 0.000 0.000 0.000 0.000 0.000
90 0.000 0.000 0.000 0.000 0.000
1000 0.253 0.196 -5.576 0.000 0.000
2000 9.628 2.549 -72.795 0.000 0.000
395
210 0.000 0.000 0.000 0.000 0.000
220 0.000 0.000 0.000 0.000 0.000

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 17

230 0.000 0.000 0.000 0.000 0.000


240 0.000 0.000 0.000 0.000 0.000
250 0.000 0.000 0.000 0.000 0.000
260 9.375 2.353 -67.219 0.000 0.000
270 9.375 2.353 -67.219 0.000 0.000
280 -9.375 -2.353 67.219 0.000 0.000
290 -9.375 -2.353 67.219 0.000 0.000
300 9.375 2.353 -67.219 0.000 0.000
3000 -9.375 -2.353 67.219 0.000 0.000
4000 12.500 3.137 -89.625 0.000 0.000
5000 -0.005 -0.574 0.166 0.000 0.000
100 0.000 0.000 0.000 0.000 0.000
110 0.000 0.000 0.000 0.000 0.000
120 0.000 0.000 0.000 0.000 0.000
130 0.000 0.000 0.000 0.000 0.000
140 0.000 0.000 0.000 0.000 0.000
150 0.000 0.000 0.000 0.000 0.000
160 0.000 0.000 0.000 0.000 0.000
170 0.000 0.000 0.000 0.000 0.000
180 0.000 0.000 0.000 0.000 0.000
190 0.000 0.000 0.000 0.000 0.000
60 0.000 0.000 0.000 0.000 0.000
70 0.000 0.000 0.000 0.000 0.000
80 0.000 0.000 0.000 0.000 0.000
90 0.000 0.000 0.000 0.000 0.000
1000 0.253 -0.196 -5.576 0.000 0.000
2000 9.633 -2.551 -72.816 0.000 0.000
210 0.000 0.000 0.000 0.000 0.000
220 0.000 0.000 0.000 0.000 0.000
230 0.000 0.000 0.000 0.000 0.000
240 0.000 0.000 0.000 0.000 0.000
250 0.000 0.000 0.000 0.000 0.000
260 9.379 -2.355 -67.240 0.000 0.000
270 9.379 -2.355 -67.240 0.000 0.000
280 -9.379 2.355 67.240 0.000 0.000
290 -9.379 2.355 67.240 0.000 0.000
300 9.379 -2.355 -67.240 0.000 0.000
396 3000 -9.379 2.355 67.240 0.000 0.000
4000 12.506 -3.140 -89.653 0.000 0.000
5000 0.512 -0.966 -11.319 0.000 0.000
100 0.000 0.000 0.000 0.000 0.000
110 0.000 0.000 0.000 0.000 0.000
120 0.000 0.000 0.000 0.000 0.000
130 0.000 0.000 0.000 0.000 0.000
140 0.000 0.000 0.000 0.000 0.000
150 0.000 0.000 0.000 0.000 0.000
160 0.000 0.000 0.000 0.000 0.000
170 0.000 0.000 0.000 0.000 0.000
180 0.000 0.000 0.000 0.000 0.000
190 0.000 0.000 0.000 0.000 0.000

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 18

60 0.000 0.000 0.000 0.000 0.000


70 0.000 0.000 0.000 0.000 0.000
80 0.000 0.000 0.000 0.000 0.000
90 0.000 0.000 0.000 0.000 0.000
1000 0.000 0.000 -67.500 0.000 0.000
2000 0.000 0.000 -67.500 0.000 0.000
210 0.000 0.000 0.000 0.000 0.000
220 0.000 0.000 0.000 0.000 0.000
230 0.000 0.000 0.000 0.000 0.000
240 0.000 0.000 0.000 0.000 0.000
250 0.000 0.000 0.000 0.000 0.000
260 0.000 0.000 0.000 0.000 0.000
270 0.000 0.000 0.000 0.000 0.000
280 0.000 0.000 0.000 0.000 0.000
290 0.000 0.000 0.000 0.000 0.000
300 0.000 0.000 0.000 0.000 0.000
3000 0.000 0.000 -67.500 0.000 0.000
4000 0.000 0.000 -67.500 0.000 0.000
397 5000 0.000 0.000 -67.500 0.000 0.000
100 0.000 0.000 0.000 0.000 0.000
110 0.000 0.000 0.000 0.000 0.000
120 0.000 0.000 0.000 0.000 0.000
130 0.000 0.000 0.000 0.000 0.000
140 0.000 0.000 0.000 0.000 0.000
150 0.000 0.000 0.000 0.000 0.000
160 0.000 0.000 0.000 0.000 0.000
170 0.000 0.000 0.000 0.000 0.000
180 0.000 0.000 0.000 0.000 0.000
190 0.000 0.000 0.000 0.000 0.000
60 0.000 0.000 0.000 0.000 0.000
70 0.000 0.000 0.000 0.000 0.000
80 0.000 0.000 0.000 0.000 0.000
90 0.000 0.000 0.000 0.000 0.000

3.5.2 Load Combination in Footing Bottom (With Pier SW)


Unit( tonf , tonf-m )
Ft.Name Pr.Name L.Comb. SFx SFy SFz SMx SMy
F1 1000 -0.253 0.196 -6.119 -0.313 -0.406
2000 9.122 -2.157 61.100 3.451 14.594
210 0.000 0.000 -0.543 0.000 0.000
220 0.000 0.000 -0.543 0.000 0.000
230 0.000 0.000 -0.543 0.000 0.000
240 0.000 0.000 -0.543 0.000 0.000
1
250 0.000 0.000 -0.543 0.000 0.000
260 9.375 -2.353 66.676 3.764 15.000
270 9.375 -2.353 66.676 3.764 15.000
280 -9.375 2.353 -67.762 -3.764 -15.000
290 -9.375 2.353 -67.762 -3.764 -15.000
300 9.375 -2.353 66.676 3.764 15.000

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 19

3000 -9.375 2.353 -67.762 -3.764 -15.000


4000 12.500 -3.137 89.082 5.019 20.000
5000 0.005 -0.574 -0.377 0.919 0.008
100 0.000 0.000 -0.543 0.000 0.000
110 0.000 0.000 -0.543 0.000 0.000
120 0.000 0.000 -0.543 0.000 0.000
130 0.000 0.000 -0.543 0.000 0.000
140 0.000 0.000 -0.543 0.000 0.000
150 0.000 0.000 -0.543 0.000 0.000
160 0.000 0.000 -0.543 0.000 0.000
170 0.000 0.000 -0.543 0.000 0.000
180 0.000 0.000 -0.543 0.000 0.000
190 0.000 0.000 -0.543 0.000 0.000
60 0.000 0.000 -0.543 0.000 0.000
70 0.000 0.000 -0.543 0.000 0.000
80 0.000 0.000 -0.543 0.000 0.000
90 0.000 0.000 -0.543 0.000 0.000
1000 -0.253 -0.196 -6.119 0.313 -0.406
2000 9.126 2.159 61.121 -3.455 14.602
210 0.000 0.000 -0.543 0.000 0.000
220 0.000 0.000 -0.543 0.000 0.000
230 0.000 0.000 -0.543 0.000 0.000
240 0.000 0.000 -0.543 0.000 0.000
250 0.000 0.000 -0.543 0.000 0.000
260 9.379 2.355 66.697 -3.768 15.007
270 9.379 2.355 66.697 -3.768 15.007
280 -9.379 -2.355 -67.783 3.768 -15.007
290 -9.379 -2.355 -67.783 3.768 -15.007
300 9.379 2.355 66.697 -3.768 15.007
3000 -9.379 -2.355 -67.783 3.768 -15.007
4000 12.506 3.140 89.110 -5.024 20.010
2 5000 -0.512 -0.966 -11.861 1.545 -0.819
100 0.000 0.000 -0.543 0.000 0.000
110 0.000 0.000 -0.543 0.000 0.000
120 0.000 0.000 -0.543 0.000 0.000
130 0.000 0.000 -0.543 0.000 0.000
140 0.000 0.000 -0.543 0.000 0.000
150 0.000 0.000 -0.543 0.000 0.000
160 0.000 0.000 -0.543 0.000 0.000
170 0.000 0.000 -0.543 0.000 0.000
180 0.000 0.000 -0.543 0.000 0.000
190 0.000 0.000 -0.543 0.000 0.000
60 0.000 0.000 -0.543 0.000 0.000
70 0.000 0.000 -0.543 0.000 0.000
80 0.000 0.000 -0.543 0.000 0.000
90 0.000 0.000 -0.543 0.000 0.000
1000 0.253 0.196 -6.119 -0.313 0.406
2000 9.628 2.549 -73.338 -4.078 15.406
395
210 0.000 0.000 -0.543 0.000 0.000
220 0.000 0.000 -0.543 0.000 0.000

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 20

230 0.000 0.000 -0.543 0.000 0.000


240 0.000 0.000 -0.543 0.000 0.000
250 0.000 0.000 -0.543 0.000 0.000
260 9.375 2.353 -67.762 -3.764 15.000
270 9.375 2.353 -67.762 -3.764 15.000
280 -9.375 -2.353 66.676 3.764 -15.000
290 -9.375 -2.353 66.676 3.764 -15.000
300 9.375 2.353 -67.762 -3.764 15.000
3000 -9.375 -2.353 66.676 3.764 -15.000
4000 12.500 3.137 -90.168 -5.019 20.000
5000 -0.005 -0.574 -0.377 0.919 -0.008
100 0.000 0.000 -0.543 0.000 0.000
110 0.000 0.000 -0.543 0.000 0.000
120 0.000 0.000 -0.543 0.000 0.000
130 0.000 0.000 -0.543 0.000 0.000
140 0.000 0.000 -0.543 0.000 0.000
150 0.000 0.000 -0.543 0.000 0.000
160 0.000 0.000 -0.543 0.000 0.000
170 0.000 0.000 -0.543 0.000 0.000
180 0.000 0.000 -0.543 0.000 0.000
190 0.000 0.000 -0.543 0.000 0.000
60 0.000 0.000 -0.543 0.000 0.000
70 0.000 0.000 -0.543 0.000 0.000
80 0.000 0.000 -0.543 0.000 0.000
90 0.000 0.000 -0.543 0.000 0.000
1000 0.253 -0.196 -6.119 0.313 0.406
2000 9.633 -2.551 -73.359 4.081 15.413
210 0.000 0.000 -0.543 0.000 0.000
220 0.000 0.000 -0.543 0.000 0.000
230 0.000 0.000 -0.543 0.000 0.000
240 0.000 0.000 -0.543 0.000 0.000
250 0.000 0.000 -0.543 0.000 0.000
260 9.379 -2.355 -67.783 3.768 15.007
270 9.379 -2.355 -67.783 3.768 15.007
280 -9.379 2.355 66.697 -3.768 -15.007
290 -9.379 2.355 66.697 -3.768 -15.007
300 9.379 -2.355 -67.783 3.768 15.007
396 3000 -9.379 2.355 66.697 -3.768 -15.007
4000 12.506 -3.140 -90.196 5.024 20.010
5000 0.512 -0.966 -11.861 1.545 0.819
100 0.000 0.000 -0.543 0.000 0.000
110 0.000 0.000 -0.543 0.000 0.000
120 0.000 0.000 -0.543 0.000 0.000
130 0.000 0.000 -0.543 0.000 0.000
140 0.000 0.000 -0.543 0.000 0.000
150 0.000 0.000 -0.543 0.000 0.000
160 0.000 0.000 -0.543 0.000 0.000
170 0.000 0.000 -0.543 0.000 0.000
180 0.000 0.000 -0.543 0.000 0.000
190 0.000 0.000 -0.543 0.000 0.000

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 21

60 0.000 0.000 -0.543 0.000 0.000


70 0.000 0.000 -0.543 0.000 0.000
80 0.000 0.000 -0.543 0.000 0.000
90 0.000 0.000 -0.543 0.000 0.000
1000 0.000 0.000 -85.973 0.000 0.000
2000 0.000 0.000 -85.973 0.000 0.000
210 0.000 0.000 -18.473 0.000 0.000
220 0.000 0.000 -18.473 0.000 0.000
230 0.000 0.000 -18.473 0.000 0.000
240 0.000 0.000 -18.473 0.000 0.000
250 0.000 0.000 -18.473 0.000 0.000
260 0.000 0.000 -18.473 0.000 0.000
270 0.000 0.000 -18.473 0.000 0.000
280 0.000 0.000 -18.473 0.000 0.000
290 0.000 0.000 -18.473 0.000 0.000
300 0.000 0.000 -18.473 0.000 0.000
3000 0.000 0.000 -85.973 0.000 0.000
4000 0.000 0.000 -85.973 0.000 0.000
397 5000 0.000 0.000 -85.973 0.000 0.000
100 0.000 0.000 -18.473 0.000 0.000
110 0.000 0.000 -18.473 0.000 0.000
120 0.000 0.000 -18.473 0.000 0.000
130 0.000 0.000 -18.473 0.000 0.000
140 0.000 0.000 -18.473 0.000 0.000
150 0.000 0.000 -18.473 0.000 0.000
160 0.000 0.000 -18.473 0.000 0.000
170 0.000 0.000 -18.473 0.000 0.000
180 0.000 0.000 -18.473 0.000 0.000
190 0.000 0.000 -18.473 0.000 0.000
60 0.000 0.000 -18.473 0.000 0.000
70 0.000 0.000 -18.473 0.000 0.000
80 0.000 0.000 -18.473 0.000 0.000
90 0.000 0.000 -18.473 0.000 0.000

3.5.3 Load Combination in Footing Bottom Center (With Pier & Footing SW)
Load Combination of Elastic Condition
: PileType
p
- C.G. of Load is coordinate from left bottom. Unit : mm Unit( tonf , tonf-m )
Ft.Name L.Comb. SFx SFy SFz SMx SMy C.G. of Loads
F1 p 1000 0.000 0.000 -441.992 0.000 0.000 5500.0 , 5500.0
2000 37.509 0.000 -441.992 0.000 1270.141 8237.9 , 5500.0
210 0.000 0.000 -352.187 0.000 0.000 5500.0 , 5500.0
220 0.000 0.000 -352.187 0.000 0.000 5500.0 , 5500.0
230 0.000 0.000 -352.187 0.000 0.000 5500.0 , 5500.0
240 0.000 0.000 -352.187 0.000 0.000 5500.0 , 5500.0
250 0.000 0.000 -352.187 0.000 0.000 5500.0 , 5500.0

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 22

260 37.509 0.000 -352.187 0.000 1270.141 8936.0 , 5500.0


270 37.509 0.000 -352.187 0.000 1270.141 8936.0 , 5500.0
280 -37.509 0.000 -352.187 0.000 -1270.141 2064.0 , 5500.0
290 -37.509 0.000 -352.187 0.000 -1270.141 2064.0 , 5500.0
300 37.509 0.000 -352.187 0.000 1270.141 8936.0 , 5500.0
3000 -37.509 0.000 -419.687 0.000 -1270.141 2616.6 , 5500.0
4000 50.012 0.000 -419.687 0.000 1693.521 9344.5 , 5500.0
5000 0.000 -3.080 -441.992 108.290 0.000 5500.0 , 5266.1

Load Combination of Ultimate Condition


: PileType
p
- C.G. of Load is coordinate from left bottom. Unit : mm Unit( tonf , tonf-m )
Ft.Name Sec.Nam L.Comb. SFx SFy SFz SMx SMy C.G. of Loads
100 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
110 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
120 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
130 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
140 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
150 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
160 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
F1 p S1
170 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
180 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
190 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
60 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
70 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
80 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0
90 0.000 0.000 -20.644 0.000 0.000 5500.0 , 5500.0

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 23

4. CHECK OF STABILITY
4.1 CHECK OF PILE REACTION (Bi-Axial)
4.1.1 Formula
if footing is checked in Buoyancy SFz means SFz - Fb
SFz SMy X SMx Y
a. Vertical - Bi Axial : R =
S Xi S Yi
2 2
Np
- Ru = Rmax
- Uf = Min[ 0 , Rmin ]
- Ru < Va => OK
(SHxi + SHyi )
2 2

b. Horizontal - Hmax = < Ha => OK


Np
c. Uplift - Uf < Ua => OK
Ver. / Uf. = Vertical / Uplift

4.1.2 Check of Vertical & Uplift Reaction


SXi (m ) SYi (m )
2 2 2 2
Ft.Name Np(EA) Fl (mm) Fw (mm)
F1 16 11000 11000 180 180

Unit( tonf )
Ft.Name L.Comb. Pile R Max R Min Ru Uf Ra Ua Result
F1 4000 CHIMNEY 68.568 -16.108 68.568 -16.108 70 17 OK

4.1.3 Check Of Horizontal Reaction


Ft.Name L.Comb. Pile Hmax (tonf) Ha (tonf) Result
CHIMNEY
F1 4000 3.126 5 OK
KSB

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 24

5. DESIGN OF FOOTING
5.1 DESIGN MOMENT AND SHEAR FORCE
Footing design is in accordance with unltimate strength method at footing bottom.
Calculated total pier load as
SQ = SFz - Self Weight Factor (Soil Weight + Footing Weight)
Ft.Name : Footing Name , Sec.Name : Strip Name for Footing Reinforcement Design
Dir. : Direction , L.Comb. : Load Combination Index , Sl or Sw : Strip X or Y width

5.1.1 Data Unit( mm , tonf , tonf-m )


Ft.Name Sec.Nam Dir. L.Comb. Fl or Fw Sl or Sw SFz SM SQ
F1 p 100 11000.00 11000.00 20.644 0.00 20.644
110 11000.00 11000.00 20.644 0.00 20.644
120 11000.00 11000.00 20.644 0.00 20.644
130 11000.00 11000.00 20.644 0.00 20.644
140 11000.00 11000.00 20.644 0.00 20.644
150 11000.00 11000.00 20.644 0.00 20.644
160 11000.00 11000.00 20.644 0.00 20.644
S1 X
170 11000.00 11000.00 20.644 0.00 20.644
180 11000.00 11000.00 20.644 0.00 20.644
190 11000.00 11000.00 20.644 0.00 20.644
60 11000.00 11000.00 20.644 0.00 20.644
70 11000.00 11000.00 20.644 0.00 20.644
80 11000.00 11000.00 20.644 0.00 20.644
90 11000.00 11000.00 20.644 0.00 20.644
100 11000.00 11000.00 20.644 0.000 20.644
110 11000.00 11000.00 20.644 0.000 20.644
120 11000.00 11000.00 20.644 0.000 20.644
130 11000.00 11000.00 20.644 0.000 20.644
140 11000.00 11000.00 20.644 0.000 20.644
150 11000.00 11000.00 20.644 0.000 20.644
160 11000.00 11000.00 20.644 0.000 20.644
S1 Y
170 11000.00 11000.00 20.644 0.000 20.644
180 11000.00 11000.00 20.644 0.000 20.644
190 11000.00 11000.00 20.644 0.000 20.644
60 11000.00 11000.00 20.644 0.000 20.644
70 11000.00 11000.00 20.644 0.000 20.644
80 11000.00 11000.00 20.644 0.000 20.644
90 11000.00 11000.00 20.644 0.000 20.644

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 25

5.1.2 Design Parameters


Yield Strength - 10M ~ 16M : fy1 , 19M ~ : fy2
f_cl : Clear Cover for edge of footing reinforcement
f_clt : Clear Cover for top of footing reinforcement
fp_clb : Clear Cover for bottom of footing reinforcement (Pile Foundation)
Loc. : Location of Critical Point from left side of footing

2
Unit(kgf/cm ,mm)
f(Flexure) f(Shear) fck fy1 fy2 f_cl f_clt fp_clb
0.9 0.75 250.00 2400.00 3900.00 50.0 50.0 150.0

5.2 REQUIRED REINFORCEMENT


5.2.1 Reinforcement Formula
- Shrinkage And Temperature Reinforcement ---- ACI CODE 7.12.2
As As1 = fac b h , fac = following
Area of shrinkage and temperature reinforcement shall provide at least the following ratio
of reinforcement area to gross concrete area, but not less than 0.0014
(a) Slabs where Grade 40 or 50 deformed bars are used ........................................................................0.0020
(b) Slabs where Grade 60 deformed bars or welded wire reinforcement are used....................................0.0018
(c) Slabs where reinforcement with yield stress exceeding 60,000 psi measured at a yield
0.0018 60,000
strain of 0.35 percent is used .......................................................................................................
fy
- Required Reinforcement by Analysis
As As2 = r.req b d
- At every section of flexural members where tensile reinforcement is required
3 fck 200
As (As5 = bw d) (As4 = b d) ---- ACI Eq (10-3)
fy fy
- The requirements of Eq (10-3) need not be applied, if every section As provided is
at least one -third greater then that required by analysis ---- ACI CODE 10.5.3
As3 = 1.333 r.req b d
Asmax = 0.75 rb b d
fck 0.003 Es
rb = 0.85 b 1
fy 0.003 Es + fy
Selected As = Max ( As1 , As2 , Min ( As3 , Max ( As4 , As5 ) ) )
If Selected As < Using As < Asmax , then OK!!

Note : The reinforcement is calculated bases on the maximum moment under the foundation in each direction.
But, the 'ISO' , 'OCT' , 'HEX' , 'COMB' , 'TANK1' foundations are calaulated as face pier
Where,
Mu 0.85 fck 2Rn
Rn =
fbd
2 , f = 0.9 , r.req =
fy
1- 1- (
0.85fck )

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 26

5.2.2 Check of Footing Reinforcement


Footing Name : F1 GroupType : Mat_Foundation
- X direction (Unit Width)

2
Sec.Name L.Comb. Using Bar (mm) Loc. (m) Width b (m) d (cm) As (cm )
90 top 5 - 16M @ 200 7.150 1.000 74.200 10.053
S1
90 botom 5 - 16M @ 200 5.500 1.000 64.200 10.053

Sec.Name L.Comb. Mu (tonf-m) Rn r.Req


90 top 0.198 0.040 0.0000
S1
90 bottom - - -
2 2 2 2 2 2
Sec.Name L.Comb. As1(cm ) As2(cm ) As3(cm ) As4(cm ) As5(cm ) Asmax(cm )
90 top 8.000 0.124 0.165 43.473 38.885 299.160
S1
90 bottom 8.000 - - 37.614 33.644 258.842
2 2
Sec.Name L.Comb. Using As(cm ) Select As(cm ) Result
90 top 10.053 8.000 OK
S1
90 bottom 10.053 8.000 OK

- Y direction (Unit Width)

2
Sec.Name L.Comb. Using Bar (mm) Loc. (m) Width b (m) d (cm) As (cm )
90 top 5 - 16M @ 200 7.150 1.000 72.600 10.053
S1
90 botom 5 - 16M @ 200 5.500 1.000 62.600 10.053

Sec.Name L.Comb. Mu (tonf-m) Rn r.Req


90 top 0.198 0.042 0.0000
S1
90 bottom - - -
2 2 2 2 2 2
Sec.Name L.Comb. As1(cm ) As2(cm ) As3(cm ) As4(cm ) As5(cm ) Asmax(cm )
90 top 8.000 0.126 0.168 42.536 38.047 292.709
S1
90 bottom 8.000 - - 36.677 32.806 252.391
2 2
Sec.Name L.Comb. Using As(cm ) Select As(cm ) Result
90 top 10.053 8.000 OK
S1
90 bottom 10.053 8.000 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 27

5.3 ONE WAY SHEAR FORCE


5.3.1 One-Way Shear Formula
ACI 318-05 CODE 11.3.1.1
- For members subject to shear and flexure only.
- f Vc = 0.75 2 fck B'w d (eq 11-3)
- Vu <= f Vc , then OK!!

5.3.2 Check of One-Way Shear


Footing Name : F1 GroupType : Mat_Foundation PileType : True

Unit : mm
11000

1 395
11000

9092

397

2 396

9092

- X direction One-Way Shear (Unit Width)


Sec.Name L.Comb. Loc. (mm) d (mm) Bw (mm) fVc (tonf) Vu (tonf) Result
S1 100 9092 642 1000 40.373 0.07 OK
- Y direction One-Way Shear (Unit Width)
Sec.Name L.Comb. Loc. (mm) d (mm) Bw (mm) fVc (tonf) Vu (tonf) Result
S1 100 9092 626 1000 39.367 0.07 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 28

5.4 TWO WAY SHEAR FORCE


5.4.1 Two-Way Shear Formula
Vu = SFz Shade Ratio
(a) f Vc1 = 0.75 2 (1 + 2/b c) fck bo d (eq 11-33) <- Vc1
(b) f Vc2 = 0.75 2 (1 + as d / 2 bo) fck bo d (eq 11-34) <- Vc2
(c) f Vc3 = 0.75 4 fck bo d (eq 11-35) <- Vc3
f Vc = Min(f Vc1 , f Vc2 , f Vc3) ACI 318-05 CODE 11.12.2.1
Vu f Vc , then OK
where
b = ratio of long side to short side of the column, concentrated load or reaction area
as = 40 for interior colimns
= 30 for edge columns
= 20 for corner columns
bo = perimeter of critical section
Footing Area - Punching Area
Shade Ratio =
Footing Area

5.4.2 Check of Two-WayShear

2
Ft.Name F1 Punching Area 134527.800 cm

11000 Pr.Name 397 Pile effect 14.941 / 16

Shape Circle f Vc1 1575.416 tonf


1 395

L.Comb. 90 f Vc2 1043.525 tonf


11000

Pl 3500 mm f Vc3 1050.278 tonf


397
Pw 3500 mm f Vc 1043.525 tonf
2 396
bo / d 13007.25 / 642 mm Vu 17.250 tonf

bc / as 1 / 40 Result OK

5.5 PILE PUNCHING SHEAR FORCE


5.5.1 Pile Punching Shear Formula
Vu = SFz Shade Ratio
(a) f Vc1 = 0.75 2 (1 + 2/bc) fck bo d (eq 11-33) <- Vc1
(b) f Vc2 = 0.75 2 (1 + as d / 2 b o) fck bo d (eq 11-34) <- Vc2
(c) f Vc3 = 0.75 4 fck bo d (eq 11-35) <- Vc3
f Vc = Min(f Vc1 , f Vc2 , f Vc3) ACI 318-05 CODE 11.12.2.1
Vu f Vc , then OK
where
b = ratio of long side to short side of the column, concentrated load or reaction area
as = 40 for interior colimns
= 30 for edge columns
= 20 for corner columns
b o = perimeter of critical section
Footing Area - Punching Area
Shade Ratio =
Footing Area

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Foundation Client : PT PLN (Persero)... Page 29

5.5.2 Check of Pile Punching Shear


2
Ft.Name F1 Punching Area 9840.641 cm

11000 Pile No. 1 bc / as 1 / 40

Shape Square f Vc1 480.598 tonf


13 14 15 16

L.Comb. 100 f Vc2 678.586 tonf


11000

9 10 11 12
PileName CHIMNEY KSB f Vc3 320.398 tonf
5 6 7 8
Diameter 350mm f Vc 320.398 tonf
1 2 3 4
bo 3968mm Vu 22.012 tonf

d 642mm Result OK

Copyright (c) GS E&C. All Rights Reserved


COLUMN CALCULATION SHEET

One-Stop Solution for Column

TITLE DESCRIPTION
PROJECT/JOB NO. WEST SUMBAWA CFSPP PROJECT 2X7 MW
PROJECT/JOB NAME PLTU SUMBAWA BARAT 2X7 MW
CLIENT NAME PT PLN (Persero) UIP KITRING NUSRA
SITE NAME TALIWANG
DOCUMENT NO.
REFERENCE NO.
STRUCTURE NAME CHIMNEY STRUCTURE KSB
GROUP NAME
LOADCOMBINATION GROUP NAME
REV DATE DESCRIPTION PREP'D CHK'D APPR'D APPR'D

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 1

CONTENTS

1. INPUT DATA
1.1 GENERAL
1.2 PIER DATA
1.3 LOADING DATA
2. PM DIAGRAM
2.1 FORMULA
2.2 PM DIAGRAM & ANALYSIS
2.3 ANALYSIS & RESULT
2.4 DETAIL PM DIAGRAM
3. ONE-WAY SHEAR
3.1 FORMULA
3.2 ONE-WAY SHEAR

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 2

1. INPUT DATA
1.1 General
Design Code American Concrete Institute (ACI 318) [Metric]

Input Unit MKS Output Unit MKS

f Bending f Axial f Sprial reinf. f Tied reinf. f Shear


0.9 0.9 0.7 0.65 0.75

fck fy (10M ~ 16M) fy (19M ~) Ec Es Steel Db Cover


2 2 2 2 2
250 kgf/cm 2400 kgf/cm 3900 kgf/cm 235000 kgf/cm 2000000 kgf/cm ASTM A615 (M) 50 mm

1.2 Pier Data


600 Pier Name 1 Ver Bar 19M, 10 EA
50
Pier Shape Circle Tie Bar -
2
Width 600 mm Fck 250 kgf/cm
2
Length 600 mm fy 3900 kgf/cm
2
Height 800 mm Using As 28.35 cm

dx - dy -
2 2 2
Main Bar 3 EA , Area = 28.353cm , Amin (1%) = 28.3cm , Amax (5%) = 141.4cm

Bar Check Reinforcrment Area is OK

600 Pier Name 2 Ver Bar 19M, 10 EA


50
Pier Shape Circle Tie Bar -
2
Width 600 mm Fck 250 kgf/cm
2
Length 600 mm fy 3900 kgf/cm
2
Height 800 mm Using As 28.35 cm

dx - dy -
2 2 2
Main Bar 3 EA , Area = 28.353cm , Amin (1%) = 28.3cm , Amax (5%) = 141.4cm

Bar Check Reinforcrment Area is OK

600 Pier Name 395 Ver Bar 19M, 10 EA


50
Pier Shape Circle Tie Bar -
2
Width 600 mm Fck 250 kgf/cm
2
Length 600 mm fy 3900 kgf/cm
2
Height 800 mm Using As 28.35 cm

dx - dy -
2 2 2
Main Bar 3 EA , Area = 28.353cm , Amin (1%) = 28.3cm , Amax (5%) = 141.4cm

Bar Check Reinforcrment Area is OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 3

600 Pier Name 396 Ver Bar 19M, 10 EA


50
Pier Shape Circle Tie Bar -
2
Width 600 mm Fck 250 kgf/cm
2
Length 600 mm fy 3900 kgf/cm
2
Height 800 mm Using As 28.35 cm

dx - dy -
2 2 2
Main Bar 3 EA , Area = 28.353cm , Amin (1%) = 28.3cm , Amax (5%) = 141.4cm

Bar Check Reinforcrment Area is OK

3500 Pier Name 397 Ver Bar 19M, 70 EA


50
Pier Shape Circle Tie Bar -
2
Width 3500 mm Fck 250 kgf/cm
2
Length 3500 mm fy 3900 kgf/cm
2
Height 800 mm Using As 198.47 cm

dx - dy -

Main Bar 18 EA , Area = 198.47cm2 , Amin (1%) = 962.1cm2 , Amax (5%) = 4810.6cm2

Bar Check Reinforcrment Area is too small

1.3 Loading Data


1.3.1 Load Case Unit( tonf , tonf-m )
Pier Name Name Fx Fy Fz Mx My
SW 0 0 -0.543 0 0
Loadtype Seismic 12.5 -3.137 89.625 0 0
Loadtype None Title Dl -0.687 0.592 -11.436 0 0
1 Loadtype None Title Ll -0.338 0.261 -7.435 0 0
Loadtype None Title 5.767 -1.416 40.465 0 0
Loadtype None Title 0.862 -2.567 19.141 0 0
DL 0 0 0 0 0
SW 0 0 -0.543 0 0
Loadtype Seismic 12.506 3.14 89.653 0 0
Loadtype None Title Dl -0.687 -0.592 -11.436 0 0
2 Loadtype None Title Ll -0.338 -0.261 -7.435 0 0
Loadtype None Title 5.77 1.418 40.48 0 0
Loadtype None Title -0.862 -2.567 -19.141 0 0
DL 0 0 0 0 0
SW 0 0 -0.543 0 0
Loadtype Seismic 12.5 3.137 -89.625 0 0
Loadtype None Title Dl 0.687 0.592 -11.436 0 0
395 Loadtype None Title Ll 0.338 0.261 -7.435 0 0
Loadtype None Title 5.767 1.416 -40.465 0 0
Loadtype None Title -0.862 -2.567 19.141 0 0
DL 0 0 0 0 0
396 SW 0 0 -0.543 0 0

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 4

Loadtype Seismic 12.506 -3.14 -89.653 0 0


Loadtype None Title Dl 0.687 -0.592 -11.436 0 0
Loadtype None Title Ll 0.338 -0.261 -7.435 0 0
Loadtype None Title 5.77 -1.418 -40.48 0 0
Loadtype None Title 0.862 -2.567 -19.141 0 0
DL 0 0 0 0 0
SW 0 0 -18.473 0 0
397
DL 0 0 -90 0 0

1.3.2 Load Combination List


Comb . ID Load Combination for Reinforcement
100 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + 1.3 Loadtype Wind Title Wx
110 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + 1.3 Loadtype Wind Title Wz
120 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + 1.0 Loadtype Seismic Title Ex
130 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + -1.0 Loadtype Seismic Title Ex
140 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + 1.0 Loadtype Seismic Title Ez
150 1.0 SW + 1.2 Loadtype Dead Title Dl + .5 Loadtype Live Title Ll + -1.0 Loadtype Seismic Title Ez
160 1.0 SW + .9 Loadtype Dead Title Dl + 1.3 Loadtype Wind Title Wx
170 1.0 SW + .9 Loadtype Dead Title Dl + -1.3 Loadtype Wind Title Wx
180 1.0 SW + 1.0 Loadtype Dead Title Dl + 1.3 Loadtype Wind Title Wz
190 1.0 SW + .9 Loadtype Dead Title Dl + -1.3 Loadtype Wind Title Wz
60 1.0 SW + 1.4 Loadtype Dead Title Dl
70 1.0 SW + 1.2 Loadtype Dead Title Dl + 1.6 Loadtype Live Title Ll
80 1.0 SW + 1.2 Loadtype Dead Title Dl + 1.6 Loadtype Live Title Ll + .8 Loadtype Wind Title Wx
90 1.0 SW + 1.2 Loadtype Dead Title Dl + 1.6 Loadtype Live Title Ll + .8 Loadtype Wind Title Wz

1.3.3 In Pier Top Unit( tonf , tonf-m )


P. Name LC# SFx SFy SFz SMx SMy
100 0 0 0 0 0
110 0 0 0 0 0
120 0 0 0 0 0
130 0 0 0 0 0
140 0 0 0 0 0
150 0 0 0 0 0
160 0 0 0 0 0
1
170 0 0 0 0 0
180 0 0 0 0 0
190 0 0 0 0 0
60 0 0 0 0 0
70 0 0 0 0 0
80 0 0 0 0 0
90 0 0 0 0 0
2 100 0 0 0 0 0

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 5

110 0 0 0 0 0
120 0 0 0 0 0
130 0 0 0 0 0
140 0 0 0 0 0
150 0 0 0 0 0
160 0 0 0 0 0
170 0 0 0 0 0
180 0 0 0 0 0
190 0 0 0 0 0
60 0 0 0 0 0
70 0 0 0 0 0
80 0 0 0 0 0
90 0 0 0 0 0
100 0 0 0 0 0
110 0 0 0 0 0
120 0 0 0 0 0
130 0 0 0 0 0
140 0 0 0 0 0
150 0 0 0 0 0
160 0 0 0 0 0
395
170 0 0 0 0 0
180 0 0 0 0 0
190 0 0 0 0 0
60 0 0 0 0 0
70 0 0 0 0 0
80 0 0 0 0 0
90 0 0 0 0 0
100 0 0 0 0 0
110 0 0 0 0 0
120 0 0 0 0 0
130 0 0 0 0 0
140 0 0 0 0 0
150 0 0 0 0 0
160 0 0 0 0 0
396
170 0 0 0 0 0
180 0 0 0 0 0
190 0 0 0 0 0
60 0 0 0 0 0
70 0 0 0 0 0
80 0 0 0 0 0
90 0 0 0 0 0

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 6

100 0 0 0 0 0
110 0 0 0 0 0
120 0 0 0 0 0
130 0 0 0 0 0
140 0 0 0 0 0
150 0 0 0 0 0
160 0 0 0 0 0
397
170 0 0 0 0 0
180 0 0 0 0 0
190 0 0 0 0 0
60 0 0 0 0 0
70 0 0 0 0 0
80 0 0 0 0 0
90 0 0 0 0 0

1.3.4 In Pier Bottom Unit( tonf , tonf-m )


P. Name LC# SFx SFy SFz SMx SMy
100 0 0 0.543 0 0
110 0 0 0.543 0 0
120 0 0 0.543 0 0
130 0 0 0.543 0 0
140 0 0 0.543 0 0
150 0 0 0.543 0 0
160 0 0 0.543 0 0
1
170 0 0 0.543 0 0
180 0 0 0.543 0 0
190 0 0 0.543 0 0
60 0 0 0.543 0 0
70 0 0 0.543 0 0
80 0 0 0.543 0 0
90 0 0 0.543 0 0
100 0 0 0.543 0 0
110 0 0 0.543 0 0
120 0 0 0.543 0 0
130 0 0 0.543 0 0
140 0 0 0.543 0 0
2
150 0 0 0.543 0 0
160 0 0 0.543 0 0
170 0 0 0.543 0 0
180 0 0 0.543 0 0
190 0 0 0.543 0 0

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 7

60 0 0 0.543 0 0
70 0 0 0.543 0 0
80 0 0 0.543 0 0
90 0 0 0.543 0 0
100 0 0 0.543 0 0
110 0 0 0.543 0 0
120 0 0 0.543 0 0
130 0 0 0.543 0 0
140 0 0 0.543 0 0
150 0 0 0.543 0 0
160 0 0 0.543 0 0
395
170 0 0 0.543 0 0
180 0 0 0.543 0 0
190 0 0 0.543 0 0
60 0 0 0.543 0 0
70 0 0 0.543 0 0
80 0 0 0.543 0 0
90 0 0 0.543 0 0
100 0 0 0.543 0 0
110 0 0 0.543 0 0
120 0 0 0.543 0 0
130 0 0 0.543 0 0
140 0 0 0.543 0 0
150 0 0 0.543 0 0
160 0 0 0.543 0 0
396
170 0 0 0.543 0 0
180 0 0 0.543 0 0
190 0 0 0.543 0 0
60 0 0 0.543 0 0
70 0 0 0.543 0 0
80 0 0 0.543 0 0
90 0 0 0.543 0 0
100 0 0 18.473 0 0
110 0 0 18.473 0 0
120 0 0 18.473 0 0
130 0 0 18.473 0 0
397 140 0 0 18.473 0 0
150 0 0 18.473 0 0
160 0 0 18.473 0 0
170 0 0 18.473 0 0
180 0 0 18.473 0 0

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 8

190 0 0 18.473 0 0
60 0 0 18.473 0 0
70 0 0 18.473 0 0
80 0 0 18.473 0 0
90 0 0 18.473 0 0

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 9

2. ONE-WAY SHEAR
2.1 FORMULA
1) Maximum Axial Load Strength
- Po = 0.85 fck (Ag-Ast) + S fy Ast
- Pnmax = f1 Po ( f1 = Axial Strenth Resuction Factiors)
- Mnmax = The Value of diagram, When P is Pn.
- Pumax = f2 Pnmax

f2 = Sprial or Tied Reinforcement Reduction Factor

2) Balanced Strain Condition


A balanced Strain condition exists at a cross-setion
when the maximum strain at the extreme
compression fiber just reaches eu = 0.003 simultaneously
with the first yield strain of es = fy/Es in the tension reinforcement.
The ratio of neutral axis depth cb is shown below
Cb eu
=
d eu + ey
eu = 0.003
fc = 0.85 fck

3) Strength for Combined Flexure and Axial Load


Maximum usable strain at extreme
concrete compression fiber shall
be assumed equal to eu = 0.003
if c that is neutral axis is supposed,
Pn and Mn can be calculated as below
fPn = f0.85 fck ( Acomp - S(1 to 11) Ast ) + S(1 to 28) fs Ast
fMn = f0.85 fck ( Acomp - S(1 to 11) Ast ) ( h/2 - c + yc )
+ S(1 to 28) fs Ast ( h/2 - c + ys )
fs(i) = e(i) Es , - fy fs(i) fy
Pn
Sprial or Tied Reinforcement Reduction Factor f = 0.9 - 0.2 0.9
Pa
Pa = 0.1 fck Ag
Acomp is Area from top to a (b 1c)
b 1c = 0.85 - 0.05 ( fck - 4000 ) / 1000 0.65 (psi)

4) Slenderness Effects
p EI
2
Cm 0.2EcIg + EsIse
dns = 1 Pc = 2 EI =
1-Pu/0.75Pc (klu) 1+b d

5) Shear
f fy Av d
fVc = f 2 fck bw d , fVs = (psi)
s
fVsmax = f 8 fck bw d (psi)
fVn = fVc + fVs

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 10

2.2 PM DIAGRAM & ANALYSIS


2.2.1 Pier Name : 1

P (tonf , tonf-m ) Axis X - Axis (All comb.)


700
Po 662.841 tonf
600 Pnmax
Pn / fPn 596.557 tonf / 417.590 tonf
500
fPnmax Mn / fMn 16.04 tonf-m / 11.23 tonf-m
400
Balanced Pb / fPb 329.529 tonf / 230.670 tonf
300

200 Mb / fM 46.25 tonf-m / 32.38 tonf-m

100 c(Balanced) 376.79 mm

0 Mx emin 33.24 mm

-100 klu / rx 10.67


10 20 30 40 50 60
Slender Neglect

P (tonf , tonf-m ) Axis Y - Axis (All comb.)


700
Po 662.841 tonf
600 Pnmax
Pn / fPn 596.557 tonf / 417.590 tonf
500
fPnmax Mn / fMn 16.11 tonf-m / 11.23 tonf-m
400
Balanced Pb / fPb 341.918 tonf / 230.670 tonf
300

200 Mb / fM 45.87 tonf-m / 32.38 tonf-m

100 c(Balanced) 376.79 mm

0 My emin 33.24 mm

-100 klu / rx 10.67


10 20 30 40 50 60
Slender Neglect

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 11

2.2.2 Pier Name : 2

P (tonf , tonf-m ) Axis X - Axis (All comb.)


700
Po 662.841 tonf
600 Pnmax
Pn / fPn 596.557 tonf / 417.590 tonf
500
fPnmax Mn / fMn 16.04 tonf-m / 11.23 tonf-m
400
Balanced Pb / fPb 329.529 tonf / 230.670 tonf
300

200 Mb / fM 46.25 tonf-m / 32.38 tonf-m

100 c(Balanced) 376.79 mm

0 Mx emin 33.24 mm

-100 klu / rx 10.67


10 20 30 40 50 60
Slender Neglect

P (tonf , tonf-m ) Axis Y - Axis (All comb.)


700
Po 662.841 tonf
600 Pnmax
Pn / fPn 596.557 tonf / 417.590 tonf
500
fPnmax Mn / fMn 16.11 tonf-m / 11.23 tonf-m
400
Balanced Pb / fPb 341.918 tonf / 230.670 tonf
300

200 Mb / fM 45.87 tonf-m / 32.38 tonf-m

100 c(Balanced) 376.79 mm

0 My emin 33.24 mm

-100 klu / rx 10.67


10 20 30 40 50 60
Slender Neglect

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 12

2.2.3 Pier Name : 395

P (tonf , tonf-m ) Axis X - Axis (All comb.)


700
Po 662.841 tonf
600 Pnmax
Pn / fPn 596.557 tonf / 417.590 tonf
500
fPnmax Mn / fMn 16.04 tonf-m / 11.23 tonf-m
400
Balanced Pb / fPb 329.529 tonf / 230.670 tonf
300

200 Mb / fM 46.25 tonf-m / 32.38 tonf-m

100 c(Balanced) 376.79 mm

0 Mx emin 33.24 mm

-100 klu / rx 10.67


10 20 30 40 50 60
Slender Neglect

P (tonf , tonf-m ) Axis Y - Axis (All comb.)


700
Po 662.841 tonf
600 Pnmax
Pn / fPn 596.557 tonf / 417.590 tonf
500
fPnmax Mn / fMn 16.11 tonf-m / 11.23 tonf-m
400
Balanced Pb / fPb 341.918 tonf / 230.670 tonf
300

200 Mb / fM 45.87 tonf-m / 32.38 tonf-m

100 c(Balanced) 376.79 mm

0 My emin 33.24 mm

-100 klu / rx 10.67


10 20 30 40 50 60
Slender Neglect

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 13

2.2.4 Pier Name : 396

P (tonf , tonf-m ) Axis X - Axis (All comb.)


700
Po 662.841 tonf
600 Pnmax
Pn / fPn 596.557 tonf / 417.590 tonf
500
fPnmax Mn / fMn 16.04 tonf-m / 11.23 tonf-m
400
Balanced Pb / fPb 329.529 tonf / 230.670 tonf
300

200 Mb / fM 46.25 tonf-m / 32.38 tonf-m

100 c(Balanced) 376.79 mm

0 Mx emin 33.24 mm

-100 klu / rx 10.67


10 20 30 40 50 60
Slender Neglect

P (tonf , tonf-m ) Axis Y - Axis (All comb.)


700
Po 662.841 tonf
600 Pnmax
Pn / fPn 596.557 tonf / 417.590 tonf
500
fPnmax Mn / fMn 16.11 tonf-m / 11.23 tonf-m
400
Balanced Pb / fPb 341.918 tonf / 230.670 tonf
300

200 Mb / fM 45.87 tonf-m / 32.38 tonf-m

100 c(Balanced) 376.79 mm

0 My emin 33.24 mm

-100 klu / rx 10.67


10 20 30 40 50 60
Slender Neglect

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 14

2.2.5 Pier Name : 397

P (tonf , tonf-m ) Axis X - Axis (All comb.)

Po 20878.720 tonf
20000 Pnmax
Pn / fPn 18790.850 tonf / 13153.590 tonf

15000
fPnmax Mn / fMn 2863.27 tonf-m / 2004.29 tonf-m
Balanced
Pb / fPb 12732.190 tonf / 8912.532 tonf
10000
Mb / fM 7535.05 tonf-m / 5274.54 tonf-m

5000 c(Balanced) 2448.21 mm

emin 120.24 mm
0 Mx
klu / rx 1.83
2000 4000 6000 8000 10000
Slender Neglect

P (tonf , tonf-m ) Axis Y - Axis (All comb.)

Po 20878.720 tonf
20000 Pnmax
Pn / fPn 18790.850 tonf / 13153.590 tonf

15000
fPnmax
Mn / fMn 2863.29 tonf-m / 2004.29 tonf-m
Balanced
Pb / fPb 12739.900 tonf / 8912.532 tonf
10000
Mb / fM 7532.15 tonf-m / 5274.54 tonf-m

5000 c(Balanced) 2448.21 mm

emin 120.24 mm
0 My
klu / rx 1.83
2000 4000 6000 8000 10000
Slender Neglect

2.3 ANALYSIS & RESULT


2.3.1 Moment Check unit (tonf-m )
Pier L/C# dx dy SdMux SdMuy fMnx fMny Result
100 1 1 0.02 0.02 10.41 10.55 OK
110 1 1 0.02 0.02 10.41 10.55 OK
120 1 1 0.02 0.02 10.41 10.55 OK
130 1 1 0.02 0.02 10.41 10.55 OK
1 140 1 1 0.02 0.02 10.41 10.55 OK
150 1 1 0.02 0.02 10.41 10.55 OK
160 1 1 0.02 0.02 10.41 10.55 OK
170 1 1 0.02 0.02 10.41 10.55 OK
180 1 1 0.02 0.02 10.41 10.55 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 15

190 1 1 0.02 0.02 10.41 10.55 OK


60 1 1 0.02 0.02 10.41 10.55 OK
70 1 1 0.02 0.02 10.41 10.55 OK
80 1 1 0.02 0.02 10.41 10.55 OK
90 1 1 0.02 0.02 10.41 10.55 OK
100 1 1 0.02 0.02 10.41 10.55 OK
110 1 1 0.02 0.02 10.41 10.55 OK
120 1 1 0.02 0.02 10.41 10.55 OK
130 1 1 0.02 0.02 10.41 10.55 OK
140 1 1 0.02 0.02 10.41 10.55 OK
150 1 1 0.02 0.02 10.41 10.55 OK
160 1 1 0.02 0.02 10.41 10.55 OK
2
170 1 1 0.02 0.02 10.41 10.55 OK
180 1 1 0.02 0.02 10.41 10.55 OK
190 1 1 0.02 0.02 10.41 10.55 OK
60 1 1 0.02 0.02 10.41 10.55 OK
70 1 1 0.02 0.02 10.41 10.55 OK
80 1 1 0.02 0.02 10.41 10.55 OK
90 1 1 0.02 0.02 10.41 10.55 OK
100 1 1 0.02 0.02 10.41 10.55 OK
110 1 1 0.02 0.02 10.41 10.55 OK
120 1 1 0.02 0.02 10.41 10.55 OK
130 1 1 0.02 0.02 10.41 10.55 OK
140 1 1 0.02 0.02 10.41 10.55 OK
150 1 1 0.02 0.02 10.41 10.55 OK
160 1 1 0.02 0.02 10.41 10.55 OK
395
170 1 1 0.02 0.02 10.41 10.55 OK
180 1 1 0.02 0.02 10.41 10.55 OK
190 1 1 0.02 0.02 10.41 10.55 OK
60 1 1 0.02 0.02 10.41 10.55 OK
70 1 1 0.02 0.02 10.41 10.55 OK
80 1 1 0.02 0.02 10.41 10.55 OK
90 1 1 0.02 0.02 10.41 10.55 OK
100 1 1 0.02 0.02 10.41 10.55 OK
110 1 1 0.02 0.02 10.41 10.55 OK
120 1 1 0.02 0.02 10.41 10.55 OK
130 1 1 0.02 0.02 10.41 10.55 OK
396
140 1 1 0.02 0.02 10.41 10.55 OK
150 1 1 0.02 0.02 10.41 10.55 OK
160 1 1 0.02 0.02 10.41 10.55 OK
170 1 1 0.02 0.02 10.41 10.55 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 16

180 1 1 0.02 0.02 10.41 10.55 OK


190 1 1 0.02 0.02 10.41 10.55 OK
60 1 1 0.02 0.02 10.41 10.55 OK
70 1 1 0.02 0.02 10.41 10.55 OK
80 1 1 0.02 0.02 10.41 10.55 OK
90 1 1 0.02 0.02 10.41 10.55 OK
100 1 1 2.22 2.22 517.26 516.74 OK
110 1 1 2.22 2.22 517.26 516.74 OK
120 1 1 2.22 2.22 517.26 516.74 OK
130 1 1 2.22 2.22 517.26 516.74 OK
140 1 1 2.22 2.22 517.26 516.74 OK
150 1 1 2.22 2.22 517.26 516.74 OK
160 1 1 2.22 2.22 517.26 516.74 OK
397
170 1 1 2.22 2.22 517.26 516.74 OK
180 1 1 2.22 2.22 517.26 516.74 OK
190 1 1 2.22 2.22 517.26 516.74 OK
60 1 1 2.22 2.22 517.26 516.74 OK
70 1 1 2.22 2.22 517.26 516.74 OK
80 1 1 2.22 2.22 517.26 516.74 OK
90 1 1 2.22 2.22 517.26 516.74 OK

2.3.2 Force Check unit (tonf )


Pier L/C# SFz fPs fPnmax Result
100 -61.14 417.59 0.54 OK
110 -61.14 417.59 0.54 OK
120 -61.14 417.59 0.54 OK
130 -61.14 417.59 0.54 OK
140 -61.14 417.59 0.54 OK
150 -61.14 417.59 0.54 OK
160 -61.14 417.59 0.54 OK
1
170 -61.14 417.59 0.54 OK
180 -61.14 417.59 0.54 OK
190 -61.14 417.59 0.54 OK
60 -61.14 417.59 0.54 OK
70 -61.14 417.59 0.54 OK
80 -61.14 417.59 0.54 OK
90 -61.14 417.59 0.54 OK
100 -61.14 417.59 0.54 OK
110 -61.14 417.59 0.54 OK
2
120 -61.14 417.59 0.54 OK
130 -61.14 417.59 0.54 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 17

140 -61.14 417.59 0.54 OK


150 -61.14 417.59 0.54 OK
160 -61.14 417.59 0.54 OK
170 -61.14 417.59 0.54 OK
180 -61.14 417.59 0.54 OK
190 -61.14 417.59 0.54 OK
60 -61.14 417.59 0.54 OK
70 -61.14 417.59 0.54 OK
80 -61.14 417.59 0.54 OK
90 -61.14 417.59 0.54 OK
100 -61.14 417.59 0.54 OK
110 -61.14 417.59 0.54 OK
120 -61.14 417.59 0.54 OK
130 -61.14 417.59 0.54 OK
140 -61.14 417.59 0.54 OK
150 -61.14 417.59 0.54 OK
160 -61.14 417.59 0.54 OK
395
170 -61.14 417.59 0.54 OK
180 -61.14 417.59 0.54 OK
190 -61.14 417.59 0.54 OK
60 -61.14 417.59 0.54 OK
70 -61.14 417.59 0.54 OK
80 -61.14 417.59 0.54 OK
90 -61.14 417.59 0.54 OK
100 -61.14 417.59 0.54 OK
110 -61.14 417.59 0.54 OK
120 -61.14 417.59 0.54 OK
130 -61.14 417.59 0.54 OK
140 -61.14 417.59 0.54 OK
150 -61.14 417.59 0.54 OK
160 -61.14 417.59 0.54 OK
396
170 -61.14 417.59 0.54 OK
180 -61.14 417.59 0.54 OK
190 -61.14 417.59 0.54 OK
60 -61.14 417.59 0.54 OK
70 -61.14 417.59 0.54 OK
80 -61.14 417.59 0.54 OK
90 -61.14 417.59 0.54 OK
100 -427.96 13153.59 18.47 OK
397 110 -427.96 13153.59 18.47 OK
120 -427.96 13153.59 18.47 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 18

130 -427.96 13153.59 18.47 OK


140 -427.96 13153.59 18.47 OK
150 -427.96 13153.59 18.47 OK
160 -427.96 13153.59 18.47 OK
170 -427.96 13153.59 18.47 OK
180 -427.96 13153.59 18.47 OK
190 -427.96 13153.59 18.47 OK
60 -427.96 13153.59 18.47 OK
70 -427.96 13153.59 18.47 OK
80 -427.96 13153.59 18.47 OK
90 -427.96 13153.59 18.47 OK

3. ONE-WAY SHEAR
3.1 FORMULA
ACI 318-05 CODE 11.3.1.1
- For members subject to shear and flexure only.
- Vc = 2 fck Bw d (eq 11-3)
Av fy d
- Vs = (eq 11-15)
s
- Vu <= f Vc + f Vs , f = 0.75 (eq 11-1)
- When, Value of f Vs shall not exceed f 8 fck Bw d (Vs max)

3.2 ONE-WAY SHEAR Unit(tonf)


P. Name Dir. LC# fVc fVs fVs max Vu Result
100 17.945 8.402 71.781 0 OK
110 17.945 8.402 71.781 0 OK
120 17.945 8.402 71.781 0 OK
130 17.945 8.402 71.781 0 OK
140 17.945 8.402 71.781 0 OK
150 17.945 8.402 71.781 0 OK
160 17.945 8.402 71.781 0 OK
X
170 17.945 8.402 71.781 0 OK
1 180 17.945 8.402 71.781 0 OK
190 17.945 8.402 71.781 0 OK
60 17.945 8.402 71.781 0 OK
70 17.945 8.402 71.781 0 OK
80 17.945 8.402 71.781 0 OK
90 17.945 8.402 71.781 0 OK
100 17.945 8.402 71.781 0 OK
Y 110 17.945 8.402 71.781 0 OK
120 17.945 8.402 71.781 0 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 19

130 17.945 8.402 71.781 0 OK


140 17.945 8.402 71.781 0 OK
150 17.945 8.402 71.781 0 OK
160 17.945 8.402 71.781 0 OK
170 17.945 8.402 71.781 0 OK
Y 180 17.945 8.402 71.781 0 OK
190 17.945 8.402 71.781 0 OK
60 17.945 8.402 71.781 0 OK
70 17.945 8.402 71.781 0 OK
80 17.945 8.402 71.781 0 OK
90 17.945 8.402 71.781 0 OK
100 17.945 8.402 71.781 0 OK
110 17.945 8.402 71.781 0 OK
120 17.945 8.402 71.781 0 OK
130 17.945 8.402 71.781 0 OK
140 17.945 8.402 71.781 0 OK
150 17.945 8.402 71.781 0 OK
160 17.945 8.402 71.781 0 OK
X
170 17.945 8.402 71.781 0 OK
180 17.945 8.402 71.781 0 OK
190 17.945 8.402 71.781 0 OK
60 17.945 8.402 71.781 0 OK
70 17.945 8.402 71.781 0 OK
80 17.945 8.402 71.781 0 OK
90 17.945 8.402 71.781 0 OK
2
100 17.945 8.402 71.781 0 OK
110 17.945 8.402 71.781 0 OK
120 17.945 8.402 71.781 0 OK
130 17.945 8.402 71.781 0 OK
140 17.945 8.402 71.781 0 OK
150 17.945 8.402 71.781 0 OK
160 17.945 8.402 71.781 0 OK
Y
170 17.945 8.402 71.781 0 OK
180 17.945 8.402 71.781 0 OK
190 17.945 8.402 71.781 0 OK
60 17.945 8.402 71.781 0 OK
70 17.945 8.402 71.781 0 OK
80 17.945 8.402 71.781 0 OK
90 17.945 8.402 71.781 0 OK
100 17.945 8.402 71.781 0 OK
395 X
110 17.945 8.402 71.781 0 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 20

120 17.945 8.402 71.781 0 OK


130 17.945 8.402 71.781 0 OK
140 17.945 8.402 71.781 0 OK
150 17.945 8.402 71.781 0 OK
160 17.945 8.402 71.781 0 OK
170 17.945 8.402 71.781 0 OK
X
180 17.945 8.402 71.781 0 OK
190 17.945 8.402 71.781 0 OK
60 17.945 8.402 71.781 0 OK
70 17.945 8.402 71.781 0 OK
80 17.945 8.402 71.781 0 OK
90 17.945 8.402 71.781 0 OK
100 17.945 8.402 71.781 0 OK
110 17.945 8.402 71.781 0 OK
120 17.945 8.402 71.781 0 OK
130 17.945 8.402 71.781 0 OK
140 17.945 8.402 71.781 0 OK
150 17.945 8.402 71.781 0 OK
160 17.945 8.402 71.781 0 OK
Y
170 17.945 8.402 71.781 0 OK
180 17.945 8.402 71.781 0 OK
190 17.945 8.402 71.781 0 OK
60 17.945 8.402 71.781 0 OK
70 17.945 8.402 71.781 0 OK
80 17.945 8.402 71.781 0 OK
90 17.945 8.402 71.781 0 OK
100 17.945 8.402 71.781 0 OK
110 17.945 8.402 71.781 0 OK
120 17.945 8.402 71.781 0 OK
130 17.945 8.402 71.781 0 OK
140 17.945 8.402 71.781 0 OK
150 17.945 8.402 71.781 0 OK
160 17.945 8.402 71.781 0 OK
X
396 170 17.945 8.402 71.781 0 OK
180 17.945 8.402 71.781 0 OK
190 17.945 8.402 71.781 0 OK
60 17.945 8.402 71.781 0 OK
70 17.945 8.402 71.781 0 OK
80 17.945 8.402 71.781 0 OK
90 17.945 8.402 71.781 0 OK
Y 100 17.945 8.402 71.781 0 OK

Copyright (c) GS E&C. All Rights Reserved


TAIL PULLEY FRAME COAL CONVEYOR C-1B - Method 1 - ACI318(MKS) 4/11/2016

Project Na. : PLTU SUMBAWA BARAT 2X7


.. Calculation Sheet
of Project No. : WEST SUMBAWA CFSPP PR..

Pier Client : PT PLN (Persero)... Page 21

110 17.945 8.402 71.781 0 OK


120 17.945 8.402 71.781 0 OK
130 17.945 8.402 71.781 0 OK
140 17.945 8.402 71.781 0 OK
150 17.945 8.402 71.781 0 OK
160 17.945 8.402 71.781 0 OK
Y 170 17.945 8.402 71.781 0 OK
180 17.945 8.402 71.781 0 OK
190 17.945 8.402 71.781 0 OK
60 17.945 8.402 71.781 0 OK
70 17.945 8.402 71.781 0 OK
80 17.945 8.402 71.781 0 OK
90 17.945 8.402 71.781 0 OK
100 605.419 54.592 2421.675 0 OK
110 605.419 54.592 2421.675 0 OK
120 605.419 54.592 2421.675 0 OK
130 605.419 54.592 2421.675 0 OK
140 605.419 54.592 2421.675 0 OK
150 605.419 54.592 2421.675 0 OK
160 605.419 54.592 2421.675 0 OK
X
170 605.419 54.592 2421.675 0 OK
180 605.419 54.592 2421.675 0 OK
190 605.419 54.592 2421.675 0 OK
60 605.419 54.592 2421.675 0 OK
70 605.419 54.592 2421.675 0 OK
80 605.419 54.592 2421.675 0 OK
90 605.419 54.592 2421.675 0 OK
397
100 605.419 54.592 2421.675 0 OK
110 605.419 54.592 2421.675 0 OK
120 605.419 54.592 2421.675 0 OK
130 605.419 54.592 2421.675 0 OK
140 605.419 54.592 2421.675 0 OK
150 605.419 54.592 2421.675 0 OK
160 605.419 54.592 2421.675 0 OK
Y
170 605.419 54.592 2421.675 0 OK
180 605.419 54.592 2421.675 0 OK
190 605.419 54.592 2421.675 0 OK
60 605.419 54.592 2421.675 0 OK
70 605.419 54.592 2421.675 0 OK
80 605.419 54.592 2421.675 0 OK
90 605.419 54.592 2421.675 0 OK

Copyright (c) GS E&C. All Rights Reserved