1. Introduction
1.1. Standards
2. Any work which is carried out in an untidy fashion shall be removed and
replaced to the Project Managers satisfaction at no extra cost to the
Purchaser.
1. The Contractor shall determine from the drawings and from site visits prior
to tendering, the lengths and sizes of all cables necessary to complete this
Contract.
2. The design current of each cable shall be at least 10% in excess of the full load
current of drive or appliance being supplied. The cable current carrying
capacity shall be derived from the relevant tables of the I.E.T. Wiring
Regulations 17th Edition (BS 7671:2008).
3. The voltage drop for any cable run must be such that the total voltage drop
from the origin of the circuit to the furthest point on the circuit shall not
exceed 2.5% of the nominal voltage.
2. All control cables from the MCC to the various items of equipment shall be
600/1000 volt multi-core PVC insulated copper conductors, steel wire
armoured, PVC over sheathed cable, conforming to BS 6346:1997. Each core
shall be individually coloured or white with black numerals.
2. All Digital and Analogue Input/ Output signals may be carried in the same
cable to the valve actuators.
5. Fibre optic cable shall be an 8- core 62. 5 /125 internal gel filled / unitube / pe
/ swa lszh. With ST terminations connections. Fibre optic cables shall be
installed in a 100 mm duct system.
1. Cabling shall be in straight runs, plumb and square to the structure lines, and a
neat installation should be ensured.
2. The Contractor shall provide "as installed" records of the complete cable
installation which should include a schedule showing cable numbers; sizes;
types; installed lengths; termination details; cable site test certificates and "as
installed" drawing.
5. Cables shall not be transported to site in loose coils, but a number of short
lengths may be transported on the same drum. The Contractor shall be
responsible for the costs of cable drums and shall remove empty drums from
site promptly.
6. The Contractor shall make available the facility to withdraw and re-draw in
conductors from any conduit or trunking, as specified in the I.E.T. Wiring
Regulations 17th Edition (BS 7671:2008).
7. Any cables that are damaged during installation shall be replaced by the
Contractor. Under no circumstances will repairs to damaged cables be
accepted.
9. Fibre optic cables shall be installed as per the manufacturers instructions and
shall not have a bending radius less than 150mm
3. Power cables shall not be extended/jointed such that a cable length has the
new and the old cable/phase colour schemes.
4. Where cables have to be box jointed e.g. level switches, the cable joint shall
be enclosed in an IP65 (BS EN 60529:1999) enclosure and shall have an
engraved label on the lid identify the connections.
1. Where PVC insulated steel wire armoured and PVC sheathed cables terminate
at fused-switches; isolators; distribution boards; switchgear; panels; motors,
etc. purpose-made brass compression glands shall be provided complying
with BS 6121:2005 and/or BS EN 50262:1999 complete with an outer sheath
seal, locknut and earth tag. All cable glands shall be protected with approved
shrouds as a protection against corrosion.
2. Gland plates and other equipment entries shall be positioned such that cable
glands may be fitted or removed without removal of other cable glands.
3. All cable cores shall be neatly tied and loomed together so that all core
identification numbers are clearly visible where the wire enters the terminal
block. All cable cores shall be fitted with approved numbered circuit
reference ferrules, reading from the terminal outwards, in accordance with the
numbering shown on schematics and connection diagrams.
5. Cable cores shall be the crimped type and shall be the correct size and current
rating for the core being terminated. The correctly sized
crimping/compression tool shall be employed to complete the crimped
termination.
6. All lugs shall be securely bolted or screwed to the termination point to which
it is connected and brass, or tinned plain washers plus spring washers shall be
fitted.
7. No more than two wires are to be connected to any one terminal or to any one
point on copper bars, e.g. bus-bars and earth bars.
2. Each gland shall be fitted with an earth ring, shall be fixed to the frame and
shall have a plastic/neoprene protecting shroud.
1.10. Cable Routing
1. The Contractor shall determine, from the Tender drawings and/or from site
visits prior to tendering, the lengths and sizes of all cables necessary to
complete the contract in order to calculate his Tender prices.
1. Cables shall be permanently labelled at each end and where they pass into
ducts or under any inspection covers. The labels and fixings shall be
manufactured from material to prevent deterioration from all sources. The
cable identification number shall correspond with those shown on the relevant
cable schedules and drawings provided by the Contractor.
2. Main and sub-cables shall carry the phase colouring as indicated from the
supply authority's main cables using the new BS 7671:2008, Amendment
No. 2:2004 colour schematics, Brown/Black/Grey/ with Blue for the neutral.
ALL CABLES, ASSOCIATED TERMINATIONS AND HOUSINGS ARE
TO BE CLEARLY MARKED THAT THE CABLE IS USING THE NEW
SCHEMATICS.
4. All cable sheaths and core numbers shall be submitted to the Project
Manager by the Contractor prior to installation of the cables.
7. Where cables pass through floors or walls, they shall be protected by a short
length of heavy gauge tube and shall be bushed in an approved manner at each
end. When rising through a floor the protecting tube shall be finished at floor
level. The Contractor shall thoroughly and effectively seal all voids formed
between the cables and openings against the ingress of moisture and gas. The
Contractor shall ensure that the materials used are fire resisting and will not
have a deleterious affect on the cables.
8. The Contractor shall be responsible for marking out all cable routes.
10. Where more than one cable will be installed in a common trench or route, they
shall be spaced at the following minimum spacing.
1. All Drives shall have an on-load isolating switch fixed adjacent to the motor.
i. The lid of the on-load switch shall be interlocked, preventing the lid
being removed, in the "ON" position.
ii. The isolating handle shall have padlocking facility to padlock in the
"OFF" position.
iii. Each on-load isolating switch shall have a set of normally closed
contacts, wired back to their respective cubicles and shall be
interlocked with the control circuit such that if the isolating switch is
turned "OFF" the associated pump or drive unit shall be tripped.
iv. Each on-load isolating switch shall have a set of contacts, wired back
to their respective cubicles and shall be indicated back to the Control
and Telemetry section when the On - Load Isolator is turned "OFF"
as per Section 16.
v. The enclosure shall be manufactured from stainless steel.
1. All drives shall have an emergency latched type, twist -release mushroom
head Stop button. This shall be fixed on a post adjacent to the motor,
manufactured from polycarbonate and have IP65 (BS EN 60529:1999)
protection.
1. Actuated valves shall be wired in a ring main system and each valve actuator
shall be protected by a suitably rated M.C.B.
2. The M.C.B shall be enclosed in an IP65 (BS EN 60529:1999) rated box and
shall have a set of auxiliary contacts wired back to the Control and Telemetry
section to indicate when the M.C.B. is isolated and connected.
3. The IP65 (BS EN 60529:1999) box shall be mounted adjacent to the actuator
and shall have labels clearly showing the valve reference.
1. All electrical equipment shall be zone 2 rated, and shall be protected against
gas corrosion. All equipment shall be fully compliant with the ATEX
directive 94/9/EC.
1.17.1. Lighting
1. The general walkways and access ladders around the new plant shall have a
lighting level of 50 lux.
2. All Treatment plant lighting cabling shall be steel wired armoured and the
light fittings and fixtures shall be corrosion resistant.
3. The Contractor shall provide emergency lighting around the treatment works
in accordance with BS 5266-1:1988.
4. All internal lights shall be operated by PIR movement detectors with timers
adjustable up to 30 minutes duration. Each set of lights shall be activated by
the PIR detectors if selected. Each set of lights shall have a manual override
switch to select - on / off / PIR operation.
5 All external lighting shall be activated by PIR detectors with timers adjustable
up to 30 minutes duration. Photocell sensors shall be provided to ensure that
the lights do not come on in daylight. Override switches shall be provided
inside the building adjacent to the primary access door to allow manual
override of the PIR controls and switch on the lighting regardless of external
conditions.
1. Where appropriate the Contractor shall wire all instruments on a ring main
system. Each individual instrument shall be protected by a 2A M.C.B. and be
installed in an IP65 (BS EN 60529:1999) enclosure.
1.17.3. Earthing
1. The whole of the electrical installation shall comply with Chapter 54 of the
I.E.T. Regulations 17th Edition (BS 7671:2008), "Earthing Arrangements and
Protective Conductors".
1. The Contractor shall test the complete electrical installation in the presence
of the Engineer and shall be in accordance with inspection and testing of the
I.E.T. Wiring Regulations 17th Edition (BS 7671:2008).
2. All necessary labour and instruments for carrying out these tests shall be
provided by the Contractor.
3. Duplicate type written copies of the completed test report shall be forwarded
to the Engineer within 7 days of the date of the tests being carried out.