Delivery

Description P.O. Date


Date

Building No 1 (Gate No.1) Security Room, Check Room and Guard Booth

Civil & Structural

Excavation Works

Slit Trenching & Manual Excavation

Mechanical Excavation works

Substructure Works

Ground Floor

CNB1C0140 Footing

CNB1C0160 Column Neck.

Biumen Painting

CNB1C0180 Back Filling & compaction

CNB1C0220 Ground Beam

Biumen Painting

Filling & compaction

CNB1C0270 Slab on Grade

Superstructure Works

Ground Floor

CNB1C0290 Columns
CNB1C0310 Roof Beam

CNB1C0330 Slab and topping

First Floor

CNB1C0610 Columns

CNB1C0640 Roof Beam

CNB1C0650 Slab and topping

Higher Roof

CNB1C0610 Columns

CNB1C0640 Roof Beam

CNB1C0650 Slab and topping

Stair Case and Parapet

CNB1C0350 Parapet

CNB1C0370 Stair Case

Roof Water Proofing System

Concrete Walk-way

Diesel Generator Shed

Architectural 15-Dec-16 31-Aug-17

Wall Finishing 10-May-17 31-Jul-17

CNB1A0100 Masonary work - Block wall

CNB1A0110 Plastering

CNB1A0120 Putty & Preliminary coat

CNB1A0130 Painting Coats


CNB1A0140 Lime Bricks with heat insulation for External Walls

CNB1A0150 Tiles for Walls

Floor Finishing 10-May-17 1-Aug-17

CNB1A0160 Surface Hardener

CNB1A0170 Self-leveling Screeds

CNB1A0180 Epoxy Paint for Hardenar

CNB1A0190 Non-slip Acid resistant ceramic floor tiles

CNB1A0200 Acid resistant ceramic coved skirting

CNB1A0210 Raised Flooring

CNB1A0220 Marble Flooring

Ceiling Finishing - False Ceiling 2-May-17 1-Jul-17

CNB1A0230 Install Acoustic Tiles / Gypsum Board

CNB1A0240 Install Acoustic Tiles with Waterproof painting

Windows & Doors Installation 15-May-17 15-Jul-17

CNB1A0250 Install Steel doors & Windows

CNB1A0260 Install Wooden Doors & Windows

CNB1A0270 Install Aluminium Doors & Windows

Chequered Plate

CNB1A0280 Installing Steel Angels

CNB1A0290 Installing Chequered Plate

Handrails & Cat Ladders 1-May-17 15-Aug-17

CNB1A0300 Installing Handrail


CNB1A0310 Installing Cat Ladder

CNB1A0320 Painting Handrail / Cat Ladder

Toilet Material Installation 1-Jun-17 31-Aug-17

Kirby Structural Works 15-Dec-16 30-Jun-17

CNB1A0360 Erect Steel Columns & Beams

CNB1A0370 Install Roof Kirby Cladding

CNB1A0380 Install Side Cladding

Diesel Generator Shed 15-Dec-16 2-Jul-17

CNB1A0390 Erect Steel Columns & Beams

CNB1A0400 Install Roof Kirby Sandwitch Panel

CNB1A0410 Install Side Kirby

Offsite Works

Asphalt Works

New Roundabout

New Entrance & Exit Roads

Hard and soft landscape works

Car Park

Gate-1

NOTE:
ALL THE ABOVE DATES ARE VALID PROVIDED THAT ALL THE REQUIRED RESOURCES AR
(DRAWINGS, MATERIALS, EQUIPMENT, MANPOWER, SUBCONTRACORS, PAYMENTS).
ANY LAK OF ANY RESOURCE WILL RESULT IN DELAYING THE ACCOMPLISHMENT OF TH
Duration Start Finish Remarks

5-May-17 11-Nov-17

191 5-May-17 11-Nov-17


191 5-May-17 11-Nov-17

46 5-May-17 19-Jun-17

41 5-May-17 14-Jun-17

26 25-May-17 19-Jun-17

58 25-May-17 21-Jul-17

58 25-May-17 21-Jul-17

41 25-May-17 4-Jul-17

46 27-May-17 11-Jul-17

36 16-Jun-17 21-Jul-17

21 19-Jun-17 9-Jul-17

16 22-Jun-17 7-Jul-17 Earthing Works, Sleeves for ME&I to Start

6 2-Jul-17 7-Jul-17

9 5-Jul-17 13-Jul-17 Cable Trunking to Start

6 14-Jul-17 19-Jul-17

80 20-Jul-17 7-Oct-17

30 20-Jul-17 18-Aug-17

16 20-Jul-17 4-Aug-17
7 5-Aug-17 11-Aug-17

7 12-Aug-17 18-Aug-17 After 2 weeks - Start Cable Tray E&I

25 19-Aug-17 12-Sep-17

11 19-Aug-17 29-Aug-17

7 30-Aug-17 5-Sep-17

7 6-Sep-17 12-Sep-17

18 13-Sep-17 30-Sep-17

6 13-Sep-17 18-Sep-17

5 19-Sep-17 23-Sep-17

7 24-Sep-17 30-Sep-17

57 12-Aug-17 7-Oct-17

44 25-Aug-17 7-Oct-17

50 12-Aug-17 30-Sep-17

11 1-Nov-17 11-Nov-17

20 20-Oct-17 8-Nov-17

91 15-May-17 13-Aug-17 Sizing of DG Shed to be finalized

86 20-Aug-17 13-Nov-17

79 27-Aug-17 13-Nov-17

54 27-Aug-17 19-Oct-17 Start After 2 weeks of Ground Floor Concrete

49 11-Sep-17 29-Oct-17 Before Start Plastering, Related servicing to Finish

49 21-Sep-17 8-Nov-17

51 24-Sep-17 13-Nov-17
54 27-Aug-17 19-Oct-17

46 21-Sep-17 5-Nov-17 Plumbing, Electrical works to Start

55 18-Sep-17 11-Nov-17 To Start Equipment Room first

55 18-Sep-17 11-Nov-17 To Start Equipment Room first

55 18-Sep-17 11-Nov-17

15 8-Oct-17 22-Oct-17 3 Days after Can Start Equipment Erection

39 28-Sep-17 5-Nov-17

39 28-Sep-17 5-Nov-17

6 27-Sep-17 2-Oct-17

39 28-Sep-17 5-Nov-17

44 1-Oct-17 13-Nov-17

44 1-Oct-17 13-Nov-17

44 1-Oct-17 13-Nov-17

67 8-Sep-17 13-Nov-17

57 18-Sep-17 13-Nov-17

52 8-Sep-17 29-Oct-17

57 18-Sep-17 13-Nov-17

54 3-Sep-17 26-Oct-17

54 3-Sep-17 26-Oct-17

6 27-Sep-17 2-Oct-17

6 6-Nov-17 11-Nov-17

6 6-Nov-17 11-Nov-17
6 6-Nov-17 11-Nov-17

4 8-Nov-17 11-Nov-17

7 5-Nov-17 11-Nov-17

55 12-Sep-17 5-Nov-17 Material at Site and accepted by 30-Jun-17 (As


per Procurement Schedule)

50 12-Sep-17 31-Oct-17

47 17-Sep-17 2-Nov-17

20 17-Oct-17 5-Nov-17

32 20-Aug-17 20-Sep-17 DG Shed Material Arrival by Jul-17 (As per


Procurement Schedule)

30 20-Aug-17 18-Sep-17

30 22-Aug-17 20-Sep-17

30 22-Aug-17 20-Sep-17

124 4-Jul-17 4-Nov-17

46 4-Jul-17 18-Aug-17

31 30-May-17 29-Jun-17

46 4-Jul-17 18-Aug-17

81 25-Aug-17 13-Nov-17

121 7-Jul-17 4-Nov-17

121 7-Jul-17 4-Nov-17

D RESOURCES ARE AVAILABLE TIMELY AND CONTINUASLY


ORS, PAYMENTS).
PLISHMENT OF THE WORKS.
1-Apr 1-May 1-Jun 1-Jul 1-Aug 1-Sep 1-Oct 1-Nov

Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17

Where are the footings of the


steel shed?
Where are the column necks of
the steel shed?
Consider the steel shed footings
and column necks.
Consider the steel shed footings
and column necks.
Consider the GB on grids S2 & S3
for the steel shed.
gggg gggg gggg
gggg gggg
Delivery
Description P.O. Date
Date

Building No 2 (Gate No.2) Security Room, Check Room and Guard Booth

Civil & Structural

Excavation Works

Slit Trenching & Manual Excavation

Mechanical Excavation works

Substructure Works

Ground Floor

CNB2C0140 Footing

CNB2C0160 Column Neck.

Biumen Painting

CNB2C0180 Back Filling & compaction

CNB2C0220 Ground Beam

Biumen Painting

Filling & compaction

CNB2C0270 Slab on Grade

Superstructure Works

Ground Floor

CNB2C0290 Columns
CNB2C0310 Roof Beam

CNB2C0330 Slab and topping

First Floor

CNB2C0610 Columns

CNB2C0640 Roof Beam

CNB2C0650 Slab and topping

Higher Roof

CNB2C0610 Columns

CNB2C0640 Roof Beam

CNB2C0650 Slab and topping

Stair Case and Parapet

CNB2C0350 Parapet

CNB2C0370 Stair Case

Roof Water Proofing System

Concrete Walk-way

Diesel Generator Shed

Architectural 15-Dec-16 31-Aug-17

Wall Finishing 10-May-17 31-Jul-17

CNB2A0100 Masonary work - Block wall

CNB2A0110 Plastering

CNB2A0120 Putty & Preliminary coat

CNB2A0130 Painting Coats


CNB2A0140 Lime Bricks with heat insulation for External Walls

CNB2A0150 Tiles for Walls

Floor Finishing 10-May-17 1-Aug-17

CNB2A0160 Surface Hardener

CNB2A0170 Self-leveling Screeds

CNB2A0180 Epoxy Paint for Hardenar

CNB2A0190 Non-slip Acid resistant ceramic floor tiles

CNB2A0200 Acid resistant ceramic coved skirting

CNB2A0210 Raised Flooring

CNB2A0220 Marble Flooring

Ceiling Finishing - False Ceiling 2-May-17 1-Jul-17

CNB2A0230 Install Acoustic Tiles / Gypsum Board

CNB2A0240 Install Acoustic Tiles with Waterproof painting

Windows & Doors Installation 15-May-17 15-Jul-17

CNB2A0250 Install Steel doors & Windows

CNB2A0260 Install Wooden Doors & Windows

CNB2A0270 Install Aluminium Doors & Windows

Chequered Plate

CNB2A0280 Installing Steel Angels

CNB2A0290 Installing Chequered Plate

Handrails & Cat Ladders 1-May-17 15-Aug-17

CNB2A0300 Installing Handrail


CNB2A0310 Installing Cat Ladder

CNB2A0320 Painting Handrail / Cat Ladder

Toilet Material Installation 1-Jun-17 31-Aug-17

Kirby Structural Works 15-Dec-16 30-Jun-17

CNB2A0360 Erect Steel Columns & Beams

CNB2A0370 Install Roof Kirby Cladding

CNB2A0380 Install Side Cladding

Diesel Generator Shed 15-Dec-16 2-Jul-17

CNB2A0390 Erect Steel Columns & Beams

CNB2A0400 Install Roof Kirby Sandwitch Panel

CNB2A0410 Install Side Kirby

Offsite Works

Asphalt Works

Gate-2

Car Park

Gate-2

NOTE:
ALL THE ABOVE DATES ARE VALID PROVIDED THAT ALL THE REQUIRED RESOURCES AR
(DRAWINGS, MATERIALS, EQUIPMENT, MANPOWER, SUBCONTRACORS, PAYMENTS).
ANY LAK OF ANY RESOURCE WILL RESULT IN DELAYING THE ACCOMPLISHMENT OF TH
Duration Start Finish Remarks

19-Apr-17 13-Nov-17

209 19-Apr-17 13-Nov-17


209 19-Apr-17 13-Nov-17

20 19-Apr-17 8-May-17

9 19-Apr-17 27-Apr-17

10 29-Apr-17 8-May-17

72 11-May-17 21-Jul-17

72 11-May-17 21-Jul-17

41 11-May-17 20-Jun-17

46 13-May-17 27-Jun-17

41 23-May-17 2-Jul-17

31 2-Jun-17 2-Jul-17

16 12-Jun-17 27-Jun-17 Earthing Works, Sleeves for ME&I to Start

6 4-Jul-17 9-Jul-17

6 10-Jul-17 15-Jul-17 Cable Trunking to Start

6 16-Jul-17 21-Jul-17

80 22-Jul-17 9-Oct-17

30 22-Jul-17 20-Aug-17

16 22-Jul-17 6-Aug-17
7 7-Aug-17 13-Aug-17

7 14-Aug-17 20-Aug-17 After 2 weeks - Start Cable Tray E&I

25 21-Aug-17 14-Sep-17

11 21-Aug-17 31-Aug-17

7 1-Sep-17 7-Sep-17

7 8-Sep-17 14-Sep-17

18 15-Sep-17 2-Oct-17

6 15-Sep-17 20-Sep-17

5 21-Sep-17 25-Sep-17

7 26-Sep-17 2-Oct-17

57 14-Aug-17 9-Oct-17

44 27-Aug-17 9-Oct-17

50 14-Aug-17 2-Oct-17

11 3-Nov-17 13-Nov-17

20 22-Oct-17 10-Nov-17

91 15-May-17 13-Aug-17 Sizing of DG Shed to be finalized

88 20-Aug-17 15-Nov-17

79 29-Aug-17 15-Nov-17

54 29-Aug-17 21-Oct-17 Start After 2 weeks of Ground Floor Concrete

49 13-Sep-17 31-Oct-17 Before Start Plastering, Related servicing to Finish

49 23-Sep-17 10-Nov-17

51 26-Sep-17 15-Nov-17
54 29-Aug-17 21-Oct-17

46 23-Sep-17 7-Nov-17 Plumbing, Electrical works to Start

55 20-Sep-17 13-Nov-17 To Start Equipment Room first

55 20-Sep-17 13-Nov-17 To Start Equipment Room first

55 20-Sep-17 13-Nov-17

15 10-Oct-17 24-Oct-17 3 Days after Can Start Equipment Erection

39 30-Sep-17 7-Nov-17

39 30-Sep-17 7-Nov-17

6 29-Sep-17 4-Oct-17

39 30-Sep-17 7-Nov-17

44 3-Oct-17 15-Nov-17

44 3-Oct-17 15-Nov-17

44 3-Oct-17 15-Nov-17

67 10-Sep-17 15-Nov-17

57 20-Sep-17 15-Nov-17

52 10-Sep-17 31-Oct-17

57 20-Sep-17 15-Nov-17

54 5-Sep-17 28-Oct-17

54 5-Sep-17 28-Oct-17

6 29-Sep-17 4-Oct-17

6 8-Nov-17 13-Nov-17

6 8-Nov-17 13-Nov-17
6 8-Nov-17 13-Nov-17

4 10-Nov-17 13-Nov-17

7 7-Nov-17 13-Nov-17

55 14-Sep-17 7-Nov-17 Material at Site and accepted by 30-Jun-17 (As


per Procurement Schedule)

50 14-Sep-17 2-Nov-17

47 19-Sep-17 4-Nov-17

20 19-Oct-17 7-Nov-17

32 20-Aug-17 20-Sep-17 DG Shed Material Arrival by Jul-17 (As per


Procurement Schedule)

30 20-Aug-17 18-Sep-17

30 22-Aug-17 20-Sep-17

30 22-Aug-17 20-Sep-17

106 12-Jul-17 25-Oct-17

11 21-Sep-17 1-Oct-17

11 21-Sep-17 1-Oct-17

106 12-Jul-17 25-Oct-17

106 12-Jul-17 25-Oct-17

D RESOURCES ARE AVAILABLE TIMELY AND CONTINUASLY


ORS, PAYMENTS).
PLISHMENT OF THE WORKS.
1-Apr 1-May 1-Jun 1-Jul 1-Aug 1-Sep 1-Oct 1-Nov

Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17

Where are the footings of the


steel shed?
Where are the column necks of
the steel shed?
Consider the steel shed footings
and column necks.
Consider the steel shed footings
and column necks.
Consider the GB on grids S2 & S3
for the steel shed.
gggg gggg gggg
gggg gggg
Delivery
Description P.O. Date
Date

Building No 3 (Gate No.3) Security Room, Check Room and Guard Booth

Civil & Structural

Excavation Works

Slit Trenching & Manual Excavation

Mechanical Excavation works

Substructure Works

Ground Floor

CNB3C0140 Footing

CNB3C0160 Column Neck.

Biumen Painting

CNB3C0180 Back Filling & compaction

CNB3C0220 Ground Beam

Filling & compaction

CNB3C0270 Slab on Grade

Superstructure Works

Ground Floor

CNB3C0290 Columns

CNB3C0310 Roof Beam


CNB3C0330 Slab and topping

First Floor

CNB3C0610 Columns

CNB3C0640 Roof Beam

CNB3C0650 Slab and topping

Higher Roof

CNB3C0610 Columns

CNB3C0640 Roof Beam

CNB3C0650 Slab and topping

Stair Case and Parapet

CNB3C0350 Parapet

CNB3C0370 Stair Case

Roof Water Proofing System

Concrete Walk-way

Diesel Generator Shed

Architectural 15-Dec-16 31-Aug-17

Wall Finishing 10-May-17 31-Jul-17

CNB3A0100 Masonary work - Block wall

CNB3A0110 Plastering

CNB3A0120 Putty & Plemenary coat

CNB3A0130 Painting Coats

CNB3A0140 Lime Bricks with heat insulation for External Walls


CNB3A0150 Tiles for Walls

Floor Finishing 10-May-17 1-Aug-17

CNB3A0160 Surface Hardener

CNB3A0170 Self-leveling Screeds

CNB3A0180 Epoxy Paint for Hardenar

CNB3A0190 Non-slip Acid resistant ceramic floor tiles

CNB3A0200 Acid resistant ceramic coved skirting

CNB3A0210 Raised Flooring

CNB3A0220 Marble Flooring

Ceiling Finishing - False Ceiling 2-May-17 1-Jul-17

CNB3A0230 Install Acoustic Tiles / Gypsum Board

CNB3A0240 Install Acoustic Tiles with Waterproof painting

Windows & Doors Installation 15-May-17 15-Jul-17

CNB3A0250 Install Steel doors & Windows

CNB3A0260 Install Wooden Doors & Windows

CNB3A0270 Install Aluminium Doors & Windows

Chequered Plate

CNB3A0280 Installing Steel Angels

CNB3A0290 Installing Chequered Plate

Handrails & Cat Ladders 1-May-17 15-Aug-17

CNB3A0300 Installing Handrail

CNB3A0310 Installing Cat Ladder


CNB3A0320 Painting Handrail / Cat Ladder

Toilet Material Installation 1-Jun-17 31-Aug-17

Kirby Structural Works 15-Dec-16 30-Jun-17

CNB3A0360 Erect Steel Columns & Beams

CNB3A0370 Install Roof Kirby Cladding

CNB3A0380 Install Side Cladding

Diesel Generator Shed 15-Dec-16 2-Jul-17

CNB3A0390 Erect Steel Columns & Beams

CNB3A0400 Install Roof Kirby Sandwitch Panel

CNB3A0410 Install Side Kirby

Offsite Works

Asphalt Works

Gate-3

Car Park

Gate-3

NOTE:
ALL THE ABOVE DATES ARE VALID PROVIDED THAT ALL THE REQUIRED RESOURCES AR
(DRAWINGS, MATERIALS, EQUIPMENT, MANPOWER, SUBCONTRACORS, PAYMENTS).
ANY LAK OF ANY RESOURCE WILL RESULT IN DELAYING THE ACCOMPLISHMENT OF TH
1-May 1-Jun 1-Jul

Duration Start Finish Remarks May-17 Jun-17 Jul-17

19-Apr-17 11-Nov-17

207 19-Apr-17 11-Nov-17


207 19-Apr-17 11-Nov-17

20 19-Apr-17 8-May-17

9 19-Apr-17 27-Apr-17

10 29-Apr-17 8-May-17

89 11-May-17 7-Aug-17

89 11-May-17 7-Aug-17

41 11-May-17 20-Jun-17

6 22-Jun-17 27-Jun-17

3 30-Jun-17 2-Jul-17

15 3-Jul-17 17-Jul-17

9 18-Jul-17 26-Jul-17 Earthing Works, Sleeves for ME&I to Start

6 27-Jul-17 1-Aug-17 Cable Trunking to Start

6 2-Aug-17 7-Aug-17

72 8-Aug-17 18-Oct-17

21 8-Aug-17 28-Aug-17

7 8-Aug-17 14-Aug-17

7 15-Aug-17 21-Aug-17
7 22-Aug-17 28-Aug-17 After 2 weeks - Start Cable Tray E&I

21 29-Aug-17 18-Sep-17

7 29-Aug-17 4-Sep-17

7 5-Sep-17 11-Sep-17

7 12-Sep-17 18-Sep-17

21 19-Sep-17 9-Oct-17

7 19-Sep-17 25-Sep-17

7 26-Sep-17 2-Oct-17

7 3-Oct-17 9-Oct-17

58 22-Aug-17 18-Oct-17

7 12-Oct-17 18-Oct-17

49 22-Aug-17 9-Oct-17

11 1-Nov-17 11-Nov-17

20 22-Oct-17 10-Nov-17

91 15-May-17 13-Aug-17 Sizing of DG Shed to be finalized

84 20-Aug-17 11-Nov-17

66 7-Sep-17 11-Nov-17

45 7-Sep-17 21-Oct-17 Start After 2 weeks of Ground Floor Concrete

45 15-Sep-17 29-Oct-17 Before Start Plastering, Related servicing to Finish

45 25-Sep-17 8-Nov-17

45 28-Sep-17 11-Nov-17

25 27-Sep-17 21-Oct-17
42 25-Sep-17 5-Nov-17 Plumbing, Electrical works to Start

51 22-Sep-17 11-Nov-17 To Start Equipment Room first

51 22-Sep-17 11-Nov-17 To Start Equipment Room first

51 22-Sep-17 11-Nov-17

15 12-Oct-17 26-Oct-17 3 Days after Can Start Equipment Erection

35 2-Oct-17 5-Nov-17

35 2-Oct-17 5-Nov-17

6 1-Oct-17 6-Oct-17

35 2-Oct-17 5-Nov-17

38 5-Oct-17 11-Nov-17

38 5-Oct-17 11-Nov-17

38 5-Oct-17 11-Nov-17

54 19-Sep-17 11-Nov-17

51 22-Sep-17 11-Nov-17

43 19-Sep-17 31-Oct-17

51 22-Sep-17 11-Nov-17

45 14-Sep-17 28-Oct-17

45 14-Sep-17 28-Oct-17

6 1-Oct-17 6-Oct-17

6 6-Nov-17 11-Nov-17

6 6-Nov-17 11-Nov-17

6 6-Nov-17 11-Nov-17
4 8-Nov-17 11-Nov-17

7 5-Nov-17 11-Nov-17

55 18-Sep-17 11-Nov-17 Material at Site and accepted by 30-Jun-17 (As


per Procurement Schedule)

50 18-Sep-17 6-Nov-17

47 23-Sep-17 8-Nov-17

20 23-Oct-17 11-Nov-17

32 20-Aug-17 20-Sep-17 DG Shed Material Arrival by Jul-17 (As per


Procurement Schedule)

30 20-Aug-17 18-Sep-17

30 22-Aug-17 20-Sep-17

30 22-Aug-17 20-Sep-17

106 29-Jul-17 11-Nov-17

11 21-Sep-17 1-Oct-17

11 21-Sep-17 1-Oct-17

106 29-Jul-17 11-Nov-17

106 29-Jul-17 11-Nov-17

D RESOURCES ARE AVAILABLE TIMELY AND CONTINUASLY


ORS, PAYMENTS).
PLISHMENT OF THE WORKS.
1-Aug 1-Sep 1-Oct 1-Nov

Aug-17 Sep-17 Oct-17 Nov-17