1.0 General:
Name of Developer –M/s Sasan Power Limited (Reliance Power Ltd.)
Date of LOI – 01.08.2007
Date of Transfer of SPV to developer – 07.08.2007
Date of signing of PPA (Effective date) –07.08.2007
Unit Months from Schedule COD as Revised schedule of COD as Scheduled COD as
No. the date of PPA worked out from date per supplemental PPA informed during
signing of signing of PPA signed by SPL and presentation in MOP on
(7.8.2007) Procurers on 15.10.2008 15.10.09*
1. 69 06.05.2013 Dec. 2011 March. 2012
2. 76 06.12.2013 Mar. 2012 June , 2012
3. 83 06.07.2014 Jun. 2012 Sept , 2012
4. 90 06.02.2015 Sept. 2012 Dec, 2012
5. 97 06.09.2015 Dec. 2012 March, 2013
6. 104 06.04.2016 Mar. 2013 June, 2013
3.2 MOEF Clearance for Forest Land: Final Clearance from MOEF received on 16.04.09
for forest land of 773.1acres. Forest area of 363 acres has been handed over to SPL.
-2-
4.2 Environment Clearance for Coal Mine (Mohar and Mohar Amlohri): Environment
Clearance received on 10.12.08.
Forest Clearance for Coal Mine (Mohar and Mohar Amlohri): Stage I Clearance
received on Nov,09. Compliance report along with payment submitted to DFO
Singrauli on 8.2.2010.
Environment Clearance for Coal Mine (Chhatrasal): Presentation to EAC made
on 25.11.2009. MOEF querries raised are being addressed.
Forest Clearance for Coal Mine (Chhatrasal): Application for forest clearance
submitted to DFO Singarauli on 16.7.09.
6.0 Others:
Remarks
Financial Closure Achieved on 20.04.09
Order for Main Plant Order placed on M/s SEC China, NTP issued to EPC contractor on 1.7.08.
Order for BOP Civil works awarded. Contract for Chimney, CW pipes, Structural steel,
BTG erection, road and drains awarded. Other BOPs yet to be awarded
MGR Coal will be transported to site by using coal conveyor instead of MGR.
8.0 The activity wise time schedule communicated by SPL vide their letter dt 21.01.10:
-3-
13 DM Plant commissioning (part) 15-Jan-11 Revised to 15-Apr-11
14 Boiler Hydro Test Complete 01-Mar-11 Revised to 31-Jul-11
15 Chimney Complete 30-Apr-11 Revised to 30-Jul-11
16 Boiler Light up 30-Jun-11 Revised to 31-0ct-11
17 Turbine Box UP 01-Aug-11 Revised to 01-Nov-11
18 Fuel Transportation System Ready 31-Aug-11 Revised to 31-Nov-11
19 Cooling Tower Ready 15-Sep-11 Revised to 15-Dec-11
20 TG Oil Flushing & Restoration 20-Sep-11 Revised to 20-Dec-11
21 TG on Barring Gear 22-Sep-11 Revised to 22-Dec-11
22 Ash Handling Plant Ready 30-Sep-11 Revised to 30-Dec-11
23 Coal Handling Plant Ready 30-Sep-11 Revised to 30-Dec-11
24 Steam Blow, SVF & Restoration 25-0ct-11 Revised to 25-Jan-12
25 Ash Dyke Ready 31-0ct-11 Revised to 31-Jan-12
26 Synchronization Unit 1 31-0ct-11 Revised to 31-Jan-12
27 COD Unit 1 31-Dec-11 Revised to March 2012
28 Synchronization Unit 2 31-Jan-12 Revised to 31-Apr-12
29 COD Unit2 31-Mar-12 Revised to June 2012
30 Synchronization Unit 3 30-Apr-12 Revised to 31-Jul-12
31 COD Unit 3 30-Jun-12 Revised to Sep. 2012
32 Synchronization Unit 4 31-Jul-12 Revised to 31-Oct-12
33 COD Unit4 30-Sep-12 Revised to Dec. 2012
34 Synchronization Unit 5 31-0ct-12 Revised to 31-Jan- 2013
35 COD Unit 5 31-Dec-12 Revised to March 2013
36 Synchronization Unit 6 31-Jan-13 Revised to 30-Apr- 2013
37 COD Unit 6 31-Mar-13 Revised to June 2013
-4-
Brief status of Progress of activities for Mundra UMPP
1.0 General:
Name of Developer –Coastal Gujarat power Ltd (CGPL) of Tata Power Ltd.
Date of LOI – 28.12.2006
Date of Transfer of SPV to developer – 22.04.2007
Date of signing of PPA (Effective date) – 23.04.2007
3.2 MOEF Clearance for Forest Land: Final Forest Clearance received on 10.6.09.
5.0 Others:
Financial Achieved on 24.4.08.
Closure
Order for Main i) For Turbo Generator – order placed on Toshiba Corporation of Japan on
Plant 20.8.07
ii) For Steam Generator order placed on Doosan Heavy Industries &
Construction Company, Korea on 15.5.07.
Order for BOP All packages awarded.
6.0 Progress of work at site:
S. Activity Schedule Actual Status/Remarks
-5-
No. date Date
6.1.0 Boiler Structural
Erection
6.1.1 Unit-1 12.05.08 5.06.08 The hydraulic test for boiler completed in March,
2010. Coal mills and bunkers erected. Balance
erection in progress, ,
6.1.2 Unit-2 21.08.08 2.09.08 Balance Structural Erection and pressure parts in
progress. Coal mills and bunkers erected. Balance
mechanical erection in progress,
6.1.3 Unit-3 25.12.08 12.02.09 Balance Structural Erection and pressure parts in
progress. Mechanical erection in progress. Coal
bunkers erected.
6.1.4 Unit-4 30.04.09 12.05.09 Balance Structural Erection and pressure parts in
progress. Mechanical erection in progress. Coal
bunkers erected.
6.1.5 Unit-5 03.09.09 - Balance Structural Erection in progress. Coal
bunkers erected.
6.2.0 TG Structural
Erection
6.2.1 Unit-1 14.08.08 13.08.08 Concreting almost completed. Structure erection in
advance stage.
6.2.2 Unit-2 19.12 08 12.02.09 Concreting almost completed. Structure erection in
advanced stage.
6.2.3 Unit-3 24.04.09 29.05.09 Concreting almost completed. Structure erection in
progress.
6.2.4 Unit-4 1.7.08 10.10.08 Concreting, structure fabrication and erection in
progress.
6.2.5 Unit-5 4.11.09 20.11.08 Concreting, structure fabrication and erection in
progress.
6.3.0 Chimney(Shell
concreting)
6.3.1 No.1(2-flue) 2.01.09 8.12.08 Flue Can fabrication completed. Insulation work in
progress..
6.3.2 No.1(3-flue) 3.06.09 24.03.09 Shell concreting completed
6.4 400 kV Switch
Yard
6.4.1 Tower Erection 13.1.10 3.12.09 Erection completed. Equipment erection and
stringing in progress.
6.5 Internal CHP
6.5.1 Concreting 10.8.08 2.4.09 Excavation in balance area in progress. Concreting
in coal runway pit and conveyor foundation beam in
progress.
-6-
Brief status of Progress of activities for Krishnapatnam UMPP
1.0 General:
Name of Developer -Coastal Andhra Power Ltd. (CAPL) Reliance Power Ltd.
Date of LOI – 30.11.2007
Date of Transfer of SPV to developer – 29.1.2008
Date of signing of PPA (Effective date) – 23.03.2007
Unit No. Months from the Schedule COD as Scheduled COD as informed
effective date i.e. worked out from the during presentation in MOP on
Transfer of SPV(29.1.08) date of Transfer of SPV 15.10.09
1. 68 September, 2013 First Unit - September, 2013
2. 75 April, 2014 Last Unit - June 2015
3. 81 October, 2014
4. 87 April, 2015
5. 93 October, 2015
The developer has informed that the order for supply of main plant equipment have been
placed for 6x660 MW units.
5.0 Others:
Status
Financial Closure Yet to be achieved
Order for Main Plant BTG awarded by R Infra in Oct. 2009.
Order for BOP Yet to be placed
Progress at site: For Boundary Wall / Fencing-Foundation, Plinth beam works and brick
wall in progress. Area grading in Main Plant – completed. .BTG area
ready for piling work. Leveling in other area is in progress. Batching plant
completed. Site office and store completed.
-7-
Date
6.1.0 Studies & Investigation
6.1.1 Soil Investigation Mar 09 May 09 Draft Final report received.
6.1.2 Area Drainage Studies Mar 09 Jan 10 Draft Report received and SGL, area
drainage finalized
6.1.3 Water intake study Dec 08 Dec. 08 MoEF(CRZ) clearance obtained on
12.06.09 for on shore pump house.
6.1.4 Testing of construction Jan 09 Jan 09 Completed
material and mix design
6.1.5 Seismic study Sep 08 Sep 08 Completed
6.1.6 Ash pond leaching study Mar 09 Nov. 09 Draft report received
6.1.7 Fuel Logistic study Dec 08 Dec 08 Completed
6.1.8 Railway Siding study Mar 09 Feb,09 In principle approval received from South
Central Railway on 17.07.09.
6.2.0 Engineering
6.2.1 Main Plant Equipment As per - a. LOI for BTG issued by EPC Contractor.
PPA b. Plant Engineering being finalized
c. Orders for BOPs yet to be placed.
6.2.2 Appointment of Issue taken up with the lead procurer. Lead
Independent Engineer procurer to take necessary action.
6.3.0 Pre-Award Works
6.3.1 Site Office, Stores & Apr 09 June 09 Completed
Miscellaneous Civil
Works
6.3.2 Boundary Wall/Fencing Sep,10 Sep, 10 Work in progress. Work stopped by land
owners at some places due to non payment
for CJFS land disputes
6.3.3 Area grading in main Dec.09 Dec.09 In progress. BTG area filled upto 2-9 m and
plant area ready for pilling work.
6.3.4 Construction power Mar 09 May. 09 1st line-6.5 Km out of 10 Km completed.
substation (Within Plant Works for balance route stopped by private
boundary) land owners for which land acquisition is to
be expedited by Distt. Administration.
Based on last JMC meeting APSPDCL
agreed to extend construction power supply
from neighboring APGENCO plant. Pole
erection and stringing completed.
6.4.0 Financing
6.4.1 Appointment of Dec 08 Dec 08 IDBI appointed as lead arranger for Rupee
advisor/arranger loan. PFC as Co lead arranger.
6.4.2 Appointment Lender’s Oct 08 Oct 08 M/s Mott Mac Donald conducting Lenders
Engineer Engineer due diligence.
6.4.3 Financial Closure Appraisal in progress. .IDBI and PFC have
sanctioned Rupee Loan (Part).
6.5.0 Others
6.5.1 Escrow Account Feb.08 Procurers Opening of Escrow Account by procurers
to open awaited.
Escrow
Account
-8-
Brief status of Progress of activities for Tilaiya (Jharkhand) UMPP
1.0 General:
-9-