Anda di halaman 1dari 13

Federal Register / Vol. 67, No.

219 / Wednesday, November 13, 2002 / Proposed Rules 68815

DEPARTMENT OF TRANSPORTATION the heading of this notice. Anyone who State pipeline safety agencies. Industry
wants confirmation of mailed comments commenters generally opposed most of
Research and Special Programs must include a self-addressed stamped NAPSR’s recommendations on grounds
Administration postcard. To file written comments that standards would be changed not for
electronically, after logging on to http:/ safety reasons or clarity but to make
49 CFR Part 192 /dms.dot.gov, click on ‘‘ES Submit.’’ compliance auditing easier. In contrast,
[Docket No. RSPA–02–13208; Notice 1] You can also read comments and other the State agencies generally supported
material in the docket at http:// NAPSR’s recommendations. NAPSR
RIN 2137–AD01 dms.dot.gov. General information about denied it was merely trying to simplify
our pipeline safety program is available the auditing process, and said its
Pipeline Safety: Further Regulatory at http://ops.dot.gov. experience provided a unique
Review; Gas Pipeline Safety Standards perspective on which standards are
Background
AGENCY: Research and Special Programs ineffective or inappropriate.
Administration (RSPA), DOT. NAPSR is a non-profit association of Because industry and State views
officials from State agencies that were so divergent, in October 1997, the
ACTION: Notice of proposed rulemaking.
participate with RSPA in the Federal American Gas Association (AGA), the
SUMMARY: RSPA is proposing to change pipeline safety regulatory program. Each American Public Gas Association
some of the safety standards for gas year NAPSR holds regional meetings to (APGA), and NAPSR formed SIRRC to
pipelines. The changes are based on discuss safety and administrative issues, iron out their differences over the
recommendations by the National culminating in resolutions for program recommendations. SIRRC agreed on all
Association of Pipeline Safety improvement. but eight of the recommendations
Representatives (NAPSR) and a review In 1990 we asked NAPSR to review scheduled for future consideration. A
of the recommendations by the State the gas pipeline safety standards in 49 copy of SIRRC’s report titled ‘‘Summary
Industry Regulatory Review Committee CFR part 192. The purpose of the review Report,’’ dated April 26, 1999, is in the
(SIRRC). We believe the changes will was to identify standards that NAPSR docket of the present proceeding.
improve the clarity and effectiveness of considered insufficient for safety or not
clear enough to enforce. NAPSR We have completed our review of
the present standards. NAPSR’s 1992 recommendations as
DATES: Persons interested in submitting compiled the results of its review in a
report titled ‘‘Report on updated by SIRRC’s 1999 Summary
written comments on the rules proposed Report. The review also covered a
in this notice must do so by January 13, Recommendations For Revision of 49
CFR part 192,’’ dated November 20, NAPSR resolution on the definition of
2003. Late filed comments will be ‘‘service line.’’ Although this resolution
considered so far as practicable. 1992. The report, a copy of which is in
the docket of the present proceeding, was not in NAPSR’s 1992 report, SIRRC
ADDRESSES: You may submit written dealt with the resolution in it’s
recommends changes to 40 sections in
comments by mailing or delivering an Summary Report.
part 192.
original and two copies to the Dockets By the time NAPSR completed its The purpose of the review was to
Facility, U.S. Department of report, we had published a notice of decide which, if any, of NAPSR’s
Transportation, Room PL–401, 400 proposed rulemaking to change many recommendations warrant inclusion in a
Seventh Street, SW., Washington, DC part 192 standards that we considered notice of proposed rulemaking. If SIRRC
20590–0001. The Dockets Facility is unclear or overly burdensome (Docket agreed to modify a recommendation, our
open from 10 a.m. to 5 p.m., Monday PS–124; 57 FR 39572; Aug. 31, 1992). review focused on that modification. If
through Friday, except on Federal Because a few of NAPSR’s SIRRC did not reach agreement, we
holidays when the facility is closed. Or recommendations related to standards focused on NAPSR’s recommendation
you may submit written comments to we had proposed to change, we in light of SIRRC’s discussion. Our
the docket electronically at the published the report for comment in the responses to the recommendations are
following Web address: http:// PS–124 proceeding (58 FR 59431; Nov. discussed in the next section of the
dms.dot.gov. See the SUPPLEMENTARY 9, 1993). The PS–124 Final Rule (61 FR preamble.
INFORMATION section for additional filing
28770; June 6, 1996) included four of Disposition of NAPSR’s
information. NAPSR’s recommended rule changes,
FOR FURTHER INFORMATION CONTACT: L.M. Recommendations
and we scheduled the remaining
Furrow by phone at 202–366–4559, by recommendations for future This section summarizes NAPSR’s
fax at 202–366–4566, by mail at U.S. consideration. Later, at a meeting on recommendations and SIRRC’s
Department of Transportation, 400 corrosion problems held in San consideration of those
Seventh Street, SW., Washington, DC Antonio, Texas on April 28, 1999, we recommendations. It also states our
20590, or by e-mail at opened NAPSR’s recommendations on responses to the recommendations. For
buck.furrow@rspa.dot.gov. corrosion control to further public ease of reference, we have numbered the
SUPPLEMENTARY INFORMATION: discussion (Docket RSPA–97–2762; 64 recommendations according to their
FR 16885; April 7, 1999). sequence in SIRRC’s Summary Report.
Filing Information, Electronic Access, In PS–124 we received 79 comments The following table categorizes the
and General Program Information on NAPSR’s recommendations, recommendations according to the
All written comments should identify primarily from pipeline trade rulemaking status indicated by our
the docket and notice numbers stated in associations, pipeline operators, and responses:

Recommendation No. Rulemaking status

7, 15, 17, 20, and 26 ................................................................................ Included in previous final rule actions.
8, 9, 30 ..................................................................................................... Proposed in ‘‘Periodic Updates to Pipeline Safety Regulations (1999)’’
(Docket RSPA–99–6106; 56 FR 15290; Mar. 22, 2000).

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00037 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
68816 Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules

Recommendation No. Rulemaking status

2, 5, 6, 11, 12, 13, 14, 29 (in part), 31, 32, 35 18, 24, 25, 28, 33 (in Proposed in present action. Alternative proposed in present action.
part) and 34 (in part).
1, 3, 4, 10, 16, 19, 21, 22, 23, 27, 29 (in part), 33 (in part), and 34 (in No rulemaking action.
part).

1. Section 192.3, Definitions of Main residential or small commercial Under the part 192 definitions of
and Transmission Line. (SIRRC customers, or to an aboveground meter ‘‘service line’’ and ‘‘main,’’ if an
Summary Report, p. 3) header supplying up to ten residential operator runs a single line from main to
Recommendation. To help distinguish or small commercial customer meters. A supply gas to two customers, the single
mains from transmission lines, revise service line terminates at the outlet of line is itself a main because it is a
the definition of ‘‘main’’ and the first the customer meter or at the connection common source of supply for more than
paragraph of the definition of to a customer’s piping, whichever is one service line.1 Typically such single-
‘‘transmission line’’ to read: further downstream, or at the line installations serve two or more
• ‘‘Main’’ means a pipeline installed connection to customer piping if there adjacent single-family residences
in a community to convey gas to is no meter. through branch lines connected to the
individual service lines or to other • ‘‘Service regulator’’ means the single line. They also serve apartment
mains. device on a service line which controls buildings and shopping centers through
• ‘‘Transmission line’’ means a the pressure of gas delivered from a high meter manifolds, or meter headers.
pipeline, or a series of pipelines, other pressure distribution system to the level Because these single lines are more
than a gathering line, that: (a) at which it is provided to the customer. like service lines than mains—their size
Transports gas from a gathering line, A service regulator may serve one is small, their pressure is low, and they
storage field or another transmission customer meter, or up to ten customer are located on private property rather
line to a storage field or to one or more meters grouped on an aboveground than under a public street or alley—
distribution systems or other load meter header. many State pipeline safety agencies
centers. SIRRC. The committee suggested have granted waivers for the lines,
SIRRC. The committee reached modification of the definitions as permitting operators to treat them as
consensus to modify the follows: service lines. Consequently, under most
recommendation as follows: • ‘‘Customer meter’’ means the meter State waivers, the single lines may be
• ‘‘Main’’ means a segment of that measures the transfer of gas from an designed, installed, operated, and
pipeline in a distribution system operator to a consumer. maintained as service lines. They do not
installed to transport gas to individual • ‘‘Service line’’ means a distribution have to meet any part 192 standard that
service lines or other mains. line that transports gas from a common applies strictly to mains. For example,
• In the present definition of source of supply to an individual § 192.327(b) requires a minimum burial
‘‘transmission line,’’ change customer, to two adjacent or adjoining depth for mains (24 in) that is greater
‘‘distribution center’’ to ‘‘distribution residential or small commercial than the depth § 192.361 requires for
system’’ to eliminate the only use of this customers, or to multiple residential or service lines (12 or 18 in). Single-line
undefined term in Part 192. small commercial customers served installations serving adjacent customers
Response: Part 192 defines through a meter header or manifold. A may also increase safety by minimizing
‘‘distribution line’’ but not ‘‘distribution service line terminates at the outlet of connections to mains. These
system.’’ So substituting ‘‘distribution the customer meter or at the connection connections are susceptible to leaks and
system’’ for ‘‘distribution line’’ in the to a customer’s piping, whichever is damage accidentally caused by street
present ‘‘main’’ definition and for further downstream, or at the excavation activities.
‘‘distribution center’’ in the present connection to customer piping if there Since SIRRC’s suggested definition of
‘‘transmission line’’ definition would is no meter. ‘‘service line’’ is consistent with State
not necessarily add clarity to either • ‘‘Service regulator’’ means the waivers we considered appropriate, we
definition. Also, by referring to device on a service line which controls are proposing to amend § 192.3 by
‘‘mains,’’ SIRRC’s definition of ‘‘main’’ the pressure of gas delivered from a revising the definition of ‘‘service line’’
loops back on itself. Therefore, we are higher pressure to the pressure provided as SIRRC suggested. Note, however, that
not proposing to adopt the SIRRC’s to the customer. A service regulator may the proposed definition uses the general
suggestion. serve one customer, or multiple term ‘‘meter manifold’’ instead of
customers through a meter header or ‘‘meter header or manifold.’’ If adopted
2. Section 192.3, Definitions of Service manifold. as final, the proposed definition would
Line and Service Regulator. (SIRRC Response. Although § 192.3 already eliminate the need for similar waivers in
Summary Report, p. 6) defines the term ‘‘customer meter,’’ the the future.
Recommendation. Adopt the definition of this term is included in the We are also proposing to adopt
following new and amended definitions definition of ‘‘service line.’’ SIRRC’s SIRRC’s suggested definition of ‘‘service
to bring Part 192 in line with acceptable suggestion would merely move the regulator.’’ SIRRC’s definition is
arrangements of service lines: ‘‘customer meter’’ definition to an 1 Section 192.3 defines ‘‘service line’’ as ‘‘a
• ‘‘Customer meter’’ means the meter alphabetical position in § 192.3. Since distribution line that transports gas from a common
that measures the transfer of gas from an ‘‘customer meter’’ is used in part 192 in source of supply to (1) a customer meter or the
operator to a consumer. places other than the ‘‘service line’’ connection to a customer’s piping, whichever is
• ‘‘Service line’’ means a distribution definition, we agree that an alphabetical farther downstream, or (2) the connection to a
customer’s piping if there is no customer meter.’’
line that transports gas from a common position is preferable. So we are In addition, ‘‘main’’ is defined as ‘‘a distribution
source of supply to an individual proposing to amend § 192.3 as SIRRC line that serves as a common source of supply for
customer, two adjacent or adjoining suggested. more than one service line.’’

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00038 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules 68817

consistent with state waivers that obsolete. However, the PS–124 Response. In Docket PS–124, we
distinguish regulators connected to comments indicated that several modified § 192.203(b)(2) by excepting
customer meter manifolds from utilities had inventories of plastic pipe takeoff lines that can be isolated from
regulating stations that must be manufactured before May 18, 1978, that sources of pressure by other valving.
inspected under § 192.739. they intended to use as replacement The SIRRC Summary Report indicates
We are particularly interested in pipe. In contrast, the SIRRC Summary this exception resolved NAPSR’s
receiving comments on how the term Report states that the committee concern about § 192.203(b)(2).
‘‘small commercial customers’’ might be members were unaware of any pre-1978 Therefore, we are adopting the SIRRC
stated differently or defined to minimize plastic pipe in operators’ stocks. consensus that the recommended
potential confusion in identifying the Moreover, the committee members had rulemaking action is not needed.
customers involved. Would it be reservations about using plastic pipe of
appropriate to consider a ‘‘small that vintage. 8. Section 192.225(a), Welding: General.
commercial customer’’ as a business Assuming the SIRRC Summary Report (SIRRC Summary Report, p. 13)
that receives volumes of gas similar to generally reflects the present status of
the volumes that a residential customer operators’ stocks of plastic pipe, we are Recommendation. Change
receives? proposing to delete the second sentence § 192.225(a) to require qualification of
of § 192.123(b)(2)(i) as obsolete. If this welding procedures according to
3. Section 192.55(a)(2), Steel Pipe. proposal were adopted as final, any ‘‘American Petroleum Institute (API),
(SIRRC Summary Report, p. 8) stockpiled pre-1978 thermoplastic pipe American Society of Mechanical
Recommendation. Delete whose long-term hydrostatic strength Engineers (ASME), or other standards.’’
§ 192.55(a)(2)(ii), which provides was determined at 73 °F could not be SIRRC. The committee agreed the
requirements for the use of new steel used above that temperature. We are recommended change is needed.
pipe manufactured before November 12, particularly interested in hearing from
However, it suggested the term ‘‘other
1970. industry commenters whether they still
SIRRC. The committee suggested that standards’’ should be changed to ‘‘other
have any stockpiles of this pipe that
§ 192.55(a)(2)(ii) should not be deleted. accepted pipeline welding standards.’’
they plan to use at temperatures above
Response. Although NAPSR initially 73 °F. Response. We proposed to adopt the
thought § 192.55(a)(2)(ii) was obsolete, core of NAPSR’s recommendation in the
several PS–124 commenters said the 6. Section 192.197(a), Control of the
proceeding called ‘‘Periodic Updates to
section should remain because operators Pressure of Gas Delivered From High-
Pipeline Safety Regulations (1999)’’ (56
have stockpiles of steel pipe pressure Distribution Systems. (SIRRC
FR 15290; Mar. 22, 2000). We proposed
manufactured before 1970. The SIRRC Summary Report, p. 11)
to amend § 192.225(a)to require
Summary Report indicates operators Recommendation. In § 192.197(a), operators to qualify welding procedures
continue to stock such pipe. We concur change ‘‘under 60 psig’’ to ‘‘60 psig or under either Section 5 of API 1104,
with SIRRC that § 192.55(a)(2)(ii) should less.’’ ‘‘Welding of Pipelines and Related
not be removed. SIRRC. The committee agreed that
Facilities,’’ or Section IX of the ASME
§ 192.197(a) should be changed as
4. Section 192.65, Transportation of Boiler and Pressure Vessel Code.
NAPSR recommended.
Pipe. (SIRRC Summary Report, p. 9) Response. Section 192.197(a) provides However, our proposal did not include
Recommendation. Delete § 192.65(b), that in distribution systems operated allowing the use of ‘‘other accepted
which provides requirements for the use ‘‘under 60 psig (414 kPa) gage,’’ if pipeline welding standards,’’ as SIRRC
of certain steel pipe transported by service regulators meet certain criteria, suggested, because we are not aware of
railroad before November 12, 1970. no other pressure limiting devices are any other generally accepted pipeline
SIRRC. The committee agreed that required. However, § 192.197(b) states welding standards.
§ 192.65(b) should not be deleted. that if those criteria are not met in 9. Section 192.241(a), Inspection and
Response. Although NAPSR initially systems operating at ‘‘60 psig (414 kPa)
Test of Welds. (SIRRC Summary Report,
thought § 192.55(b) was obsolete, gage, or less,’’ additional pressure
several PS–124 commenters said they p. 14)
control is required. Thus there is a 1 psi
had stockpiled pipe manufactured discrepancy between these two sections. Recommendation. Change
before 1970. In addition, the SIRRC We agree with SIRRC that § 192.197(a) § 192.241(a) to require that visual
Summary Report indicates that should be in sync with § 192.197(b), inspection of welding be conducted ‘‘by
operators still have this pipe and that it particularly since § 192.197(c) applies to an inspector qualified by appropriate
may have been transported by railroad. systems in which the operating pressure training and experience.’’
We concur with the SIRRC’s suggestion. ‘‘exceeds 60 psig (414 kPa) gage.’’
Therefore, we are proposing to change SIRRC. The committee agreed the
5. Section 192.123, Design Limitations recommended change is needed.
§ 192.197(a) as NAPSR recommended.
for Plastic Pipe. (SIRRC Summary However, it suggested the term
Report p. 10) 7. Section 192.203(b)(2), Instrument, ‘‘inspector’’ should be changed to
Recommendation. Delete the second Control, and Sampling Pipe and ‘‘person.’’
sentence of § 192.123(b)(2)(i), which Components. (SIRRC Summary Report,
p. 12) Response. In the proceeding called
allows plastic pipe manufactured before ‘‘Periodic Updates to Pipeline Safety
May 18, 1978, and strength rated at 73 Recommendation. In § 192.203(b)(2),
Regulations (1999)’’ (56 FR 15290; Mar.
°F to be used at temperatures up to 100 change ‘‘takeoff line’’ to ‘‘instrument,
22, 2000), we proposed to amend
°F. control, and sampling line’’ to clarify
SIRRC. The committee agreed that the the lines on which a shutoff valve must § 192.241(a) as NAPSR recommended.
second sentence of § 192.123(b)(2)(i) be installed. Although we overlooked SIRRC’s
should be deleted. SIRRC. The committee agreed the suggestion to use ‘‘person’’ instead of
Response. NAPSR thought the second recommended change to § 192.203(b)(2) ‘‘inspector,’’ we will consider the
sentence of § 192.123(b)(2)(i) was is not needed. suggestion in developing the final rule.

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00039 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
68818 Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules

10. Section 192.285(c) and (d), Plastic pipe. Still, there are various means However, operators commonly use
Pipe: Qualifying Persons to Make Joints. available to effect safe repairs, and we tracer wire for this purpose as they do
(SIRRC Summary Report, p. 15) do not think it’s necessary to limit the under existing § 192.321(e) for locating
Recommendation. In § 192.285, revise method of repair. Section 192.703(b) underground plastic mains and
paragraph(c) to require that persons who would forbid the use of any method that transmission lines.
join plastic pipe requalify annually to would result in an unsafe condition. So
13. Section 192.353(a), Customer Meters
make joints. Also, revise paragraph (d) we are proposing to amend § 192.311 as
and Regulators: Location. (SIRRC
to require that operators maintain NAPSR recommended.
Summary Report, p. 21)
certain records for use in monitoring 12. Section 192.321(e), Installation of Recommendation. Amend
personnel qualifications. Plastic Pipe; § 192.361(g), Service Lines: § 192.353(a) to emphasize that vehicular
SIRRC. The committee did not agree Installation. (SIRRC Summary Report, p. damage is a type of damage from which
that NAPSR’s recommended rule 19) meters and service regulators must be
changes were needed. However, the Recommendation. To prevent protected.
committee did agree that in § 192.285(d) underground plastic pipe from being SIRRC. Although the committee
the term ‘‘his’’ should be replaced by a damaged by electrically charged tracer members agreed that the existing rule
term that is not gender-specific. wire and to maintain wire integrity, implicitly requires protection from
Response. NAPSR was concerned that require separation between pipe and vehicular damage, they did not agree on
while most newly installed distribution wire, where practical, and require that the need to emphasize this type of
lines are made of plastic pipe, the tracer wire be protected against damage. Industry members thought
qualification requirements for persons corrosion. emphasizing vehicular damage would
who join plastic pipe are less stringent SIRRC. The committee agreed to cause more disputes with government
than the qualification requirements for accept NAPSR’s recommendation. It inspectors over what level of protection
persons who weld steel pipe. NAPSR also agreed that § 192.321, which is needed.
felt the plastic pipe joining and welder applies to mains and transmission lines, Response. In enforcing § 192.353(a),
qualification requirements should be and § 192.361, which applies to service our position has been that the provision
comparable because the consequences lines, should be changed as follows: that meters and service regulators must
of failure of a plastic pipe joint may be • Revise § 192.321(e) to read as be protected from ‘‘corrosion and other
just as severe as the consequences of follows: damage’’ requires reasonable protection
failure of a welded joint. (e) Plastic pipe that is not encased from vehicular damage where
We do not believe NAPSR’s reasoning must have an electrically conducting warranted. SIRRC’s Summary Report
is sufficient to justify stronger plastic wire or other means of locating the pipe supports this position. Furthermore,
pipe joining requirements. The skill while it is underground. Tracer wire AGA’s ‘‘Guide for Gas Transmission and
needed for joining plastic pipe is so shall not be wrapped around the pipe Distribution Piping Systems,’’ which
much simpler than the skill needed for and contact with the pipe shall be advises operators on compliance with
welding steel pipe that the welding minimized. Tracer wire or other Part 192, recognizes this requirement. It
requirements cannot reasonably serve as metallic elements installed for pipe states with regard to § 192.353(a) that if
a basis for establishing more stringent locating purposes shall be resistant to the potential for vehicular damage is
plastic pipe joining requirements. corrosion damage, either by use of evident, the meter or service regulator
Therefore, we are not proposing to coated copper wire or by other means. should be protected or an alternate
adopt NAPSR’s recommended rule • Establish § 192.361(g) to match location selected.
changes. proposed § 192.321(e). NAPSR reported that its members had
It is worth noting, though, that after Response. Although there have been found meter sets that were damaged by
SIRRC completed it’s report, we only a few instances where highly vehicles or were at serious risk of such
published new qualification of charged tracer wire damaged buried damage. When this information is
personnel rules in Subpart N of Part plastic pipe, we believe separating wire considered in light of the industry’s
192. The competency evaluations from pipe wherever practical is a apparent understanding of the present
required by these rules should enhance reasonable safeguard. It is also rule, it indicates some operators may
the qualifications of persons who make reasonable that tracer wire or other have been lax in providing needed
plastic pipe joints. metallic means of pipe locating be protection. Emphasizing vehicular
Section 192.285(d) now uses the term resistant to corrosion. Therefore, we are damage in the present rule should at
‘‘his.’’ As SIRRC suggested, we are proposing to adopt SIRRC’s consensus least cause operators to pay more
proposing to change this term to ‘‘the by revising § 192.321(e) and adding attention to the problem and perhaps
operator’s.’’ § 192.361(g) as set forth below in the reduce the risk of damage. So we are
proposed amendments section of this proposing to adopt NAPSR’s
11. Section 192.311, Repair of Plastic recommendation by amending
notice.
Pipe. (SIRRC Summary Report, p. 18) We recognize that continuous § 192.353(a) to emphasize vehicular
Recommendation. Remove the separation may not be ensured when damage.
requirement from § 192.311 that a wire and pipe are installed together in Although § 192.353(a) affects design
‘‘patching saddle’’ must be used to the same hole made by trenchless and does not apply to pipelines
repair harmful damage to new plastic technology. In fact, in such cases the constructed before it went into effect,
pipelines if the damaged pipe is not wire is often randomly taped to the pipe protection from vehicular damage is
removed. to control separation during installation. also a safety concern on earlier
SIRRC. The committee agreed the The proposed requirement to minimize constructed pipelines. These pipelines,
recommended change is needed. contact with the pipe should not deter however, are subject to the general
Response. We concur with NAPSR this common installation practice. maintenance standard of § 192.703(b),
that the meaning of ‘‘patching saddle’’ is Note that part 192 does not now which requires operators to correct any
unclear, although we have stated the require that underground plastic service pipeline that becomes unsafe. If the
term implies a plastic saddle adhered to lines have a means for locating the lines. safety of a meter set is jeopardized by

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00040 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules 68819

vehicular traffic, the operator would shall, not less than every 3 years at and keep a record of the condition
have to take action under § 192.703(b) to intervals not exceeding 39 months, under § 192.491.
correct the problem. reevaluate its unprotected pipelines and SIRRC. The committee agreed that
cathodically protect them in accordance records of coating condition are
14. Section 192.457(b)(3), External
with this subpart in areas in which important in evaluating the overall
Corrosion Control: Buried or Submerged
active corrosion is found. The operator condition of a pipeline, and that this
Pipelines Installed Before August 1,
shall determine the areas of active information helps meet the continuing
1971; 192.465(e), External Corrosion
corrosion by electrical survey or by surveillance and active corrosion rules.
Control: Monitoring. (SIRRC Summary
analysis and review of the pipeline The committee suggested that § 192.459
Report, p. 23)
condition. Analysis and review shall be revised to read as follows:
Recommendation. Amend include, but is not limited to, leak repair Whenever an operator has knowledge that
§§ 192.457(b) and § 192.465(e) to clarify history, exposed pipe condition reports, any portion of a buried pipeline is exposed,
the meaning of ‘‘electrical survey’’ and and the pipeline environment. the exposed portion must be examined to
what circumstances make an electrical (iii) For the purpose of this section, an determine the condition of the coating, or if
survey ‘‘impractical.’’ Also, require electrical survey is a series of closely the pipeline is bare or the coating is
operators to consider all relevant spaced pipe-to-soil readings over a deteriorated, the exterior condition of the
information when using an alternative pipeline which are subsequently pipe. A record of the examination results
to an electrical survey. analyzed to identify any locations where shall be made in accordance with
SIRRC. The committee concluded that a corrosive current is leaving the pipe. § 192.491(c). If external corrosion is found,
electrical surveys are seldom used on SIRRC also agreed that ‘‘pipeline remedial action must be taken to the extent
distribution systems, so there is no required by § 192.483 and the applicable
environment’’ refers to whether soil
paragraphs of §§ 192.485, 192.487, or
advantage to requiring electrical surveys resistivity is high or low, wet or dry, 192.489.
as a preferred corrosion inspection contains contaminants that may
method on distribution systems. SIRRC promote corrosion, or has any other Response. In light of NAPSR’s
further concluded that if electrical known condition that might influence recommendation and an earlier
surveys are not used, all available the probability of active corrosion. recommendation by the National
information should be used to Response. We recently revised the Transportation Safety Board on
determine if active corrosion exists. The corrosion control regulations for inspecting exposed pipe, we revised
committee agreed that the second hazardous liquid and carbon dioxide § 192.459 to require that operators
sentence of § 192.457(b), as it relates to pipelines in 49 CFR part 195 (Docket determine the extent of any corrosion
distribution lines, and § 192.465(e) RSPA–97–2762; 66 FR 66994; Dec. 27, that is found on the exposed portion of
should be changed to read as follows: 2001). In doing so, we relied on SIRRC’s a pipeline (64 FR 56981, Oct. 22, 1999).
• § 192.457(b): suggestion on monitoring unprotected At a minimum, the present rule requires
The operator shall determine the areas gas transmission lines as a basis for that operators inspect exposed pipelines
of active corrosion by electrical survey revising the requirement to monitor to see if the coating on coated pipe has
or by analysis and review of the unprotected pipe (see 49 CFR deteriorated. In addition, § 192.491(c)
pipeline condition. Analysis and review 195.573(b)). Because we believe SIRRC’s requires a record of each inspection ‘‘in
shall include, but is not limited to, leak approach is reasonable for both sufficient detail to demonstrate the
repair history, exposed pipe condition transmission and distribution lines, we adequacy of corrosion control measures
reports, and the pipeline environment. are proposing to adopt the SIRRC or that a corrosive condition does not
For the purpose of this section, an suggestion on monitoring these lines by exist.’’ Thus we have essentially
electrical survey is a series of closely revising § 192.465(e) as set forth below adopted the SIRRC consensus, because
spaced pipe-to-soil readings over a in the proposed amendments section of the combination of § 192.459 and
pipeline which are subsequently this notice. § 192.491(c) adequately addresses the
analyzed to identify any locations where However, rather than change the need to examine and record the
a corrosive current is leaving the pipe. second sentence of § 192.457(b) as condition of coating on exposed coated
• § 192.465(e): SIRRC suggested, we are proposing to pipe.
(i) For transmission pipelines, after delete the second sentence because we
the initial evaluation required by 16. Section 192.467(d), External
think it’s unnecessary. This sentence,
paragraphs (b) and (c) of § 192.455 and Corrosion Control: Electrical Isolation
which is repeated in § 192.465(e), is no
paragraph (b) of § 192.457, each operator (SIRRC Summary Report, p. 28)
longer needed in § 192.457(b) because
shall, not less than every 3 years at the time for completing the initial Recommendation. Amend
intervals not exceeding 39 months, evaluation of the need for corrosion § 192.467(d) to require annual electrical
reevaluate its unprotected pipelines and control required by § 192.457(b) has tests on casings to determine if there is
cathodically protect them in accordance expired. All subsequent evaluations are contact with the encased pipe. Also,
with this subpart in areas in which required by § 192.465(e). Also, we are require remedial action according to
active corrosion is found. The operator proposing to move the definition of Recommendation No. 19 if contact is
shall determine the areas of active ‘‘active corrosion,’’ now in § 192.457(c), found.
corrosion by electrical survey, or where to § 192.465(e). SIRRC. The committee did not reach
an electrical survey is impractical, by agreement on the need to conduct
analysis and review of the pipeline 15. Section 192.459, External Corrosion annual tests for shorted casings,
condition. Analysis and review shall Control: Examination of Buried Pipeline although consensus was reached on
include, but is not limited to, leak repair When Exposed. (SIRRC Summary remedial action as discussed below
history, exposed pipe condition reports, Report, p. 27) regarding Recommendation No. 19.
and the pipeline environment. Recommendation. Amend § 192.459 Industry’s position on annual testing
(ii) For distribution pipelines, after to clarify that when an operator was that separate tests on casings are
the initial evaluation required by examines the exposed portion of a unnecessary as long as the pipe
paragraphs (b) and (c) of § 192.455 and buried pipeline, the operator must potential is above ¥850Mv. NAPSR’s
paragraph (b) of § 192.457, each operator determine the condition of the coating position was that because a shorted

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00041 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
68820 Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules

casing shields encased pipe from SIRRC. The committee agreed no required full protection of all pipelines
protective current, the encased pipe can further rulemaking action is needed. exposed to the atmosphere, regardless of
corrode regardless of the potential of Response. The PS–124 Final Rule the date of installation. Based on San
pipe outside the casing. included NAPSR’s recommended Antonio comments that the old rule was
Response. A large majority of PS–124 change to § 192.475(c). overly burdensome, we revised the rule
commenters opposed NAPSR’s to allow operators to avoid coating
18. Section 192.479, Atmospheric
recommendation on the ground that no pipelines they demonstrate will have
correlation had been found between Corrosion Control: General. (SIRRC
either a light surface oxide (a non-
shorted casings and corrosion of the Summary Report, p. 30)
damaging corrosion film) or
encased pipe. One commenter alleged Recommendation. Require all atmospheric corrosion that will not
that the purpose of § 192.467(c), which aboveground pipelines exposed to the affect safe operation before the next
requires isolation of gas pipe from atmosphere to meet the same scheduled inspection (§ 195.581).
casings, is to maintain protective atmospheric corrosion control and We believe § 195.581 is consistent
current levels. remedial requirements, no matter when with SIRRC’s suggested change of
Also, several commenters addressed the pipeline was installed. § 192.479. Section 195.581 requires the
the shorted casing issue in response to SIRRC. The resolution of the same level of protection for old and new
our San Antonio meeting notice. Five committee was that all exposed pipelines. Also the exceptions for a light
persons said shorts should be cleared aboveground pipe should be subject to surface oxide and corrosion that will not
because using more protective current to the same atmospheric protection need remedial action before the next
offset the short could have adverse standards. The committee agreed that scheduled inspection are equivalent to
effects. Two other commenters said that § 192.479 should be revised to read as SIRRC’s exception of non-active
clearing shorts can be costly if the line follows, and explained that ‘‘active corrosion. One of our goals in revising
must be taken out of service or replaced, corrosion’’ does not include non- the Part 195 corrosion control
and that there is no consensus on the damaging corrosive films: regulations was to establish similar
adequacy of other remedial measures. (a) Each aboveground pipeline or corrosion control requirements for gas
Another San Antonio commenter portion of a pipeline that is exposed to and liquid pipelines wherever
suggested the present electrical isolation the atmosphere must be cleaned and appropriate. Therefore, in keeping with
requirement of § 192.467(c) is not either coated or jacketed with a material this goal, we are proposing to use
needed since cathodic protection has to suitable for the prevention of § 195.581 instead of SIRRC’s suggestion
meet the part 192 criteria for adequacy. atmospheric corrosion. An operator as the basis for changing § 192.479. The
In this regard, AGA’s Gas Piping need not comply with this paragraph, if existing standards for remedial action,
Technology Committee (GPTC) has the operator can demonstrate by test, §§ 192.485, 192.487, and 192.489, will
submitted a rulemaking petition to investigation, or experience in the area provide a benchmark for any
rescind the requirement to isolate gas of application that active corrosion does demonstrations that protection is not
pipe from metallic casings, arguing not exist. required before the next inspection.
there are no safety benefit from clearing (b) If active corrosion is found on an NAPSR did not recommend any
shorted casings. aboveground pipeline or portion of change to the periodic monitoring
Considering the conflicting opinions pipeline, the operator shall— requirements of § 192.481. These
on the need to clear shorted casings to (1) take prompt remedial action requirements are comparable to the
prevent pipe corrosion, we have consistent with the severity of the monitoring requirements for hazardous
decided not to propose to adopt corrosion to the extent required by the liquid and carbon dioxide pipelines
NAPSR’s recommendation for annual applicable paragraphs of §§ 192.485, under § 195.583. Both sections require
testing. Instead we will consider the 192.487, or 192.489; and monitoring for atmospheric corrosion at
recommendation in a separate (2) clean and either coat or jacket the least every 3 years for onshore pipelines
rulemaking proceeding called ‘‘Pipeline areas of atmospheric corrosion with a and every year for offshore pipelines.
Safety: Controlling Corrosion on Gas material suitable for the prevention of And both sections require remedial
Pipelines’’ (RIN 2137–AD63). In that atmospheric corrosion. action if harmful atmospheric corrosion
proceeding, we will examine the need to Response. Section 192.479 prescribes is found. However, § 195.583 specifies
change part 192 to improve the atmospheric protection requirements particular pipeline features, such as
industry’s corrosion control practices in according to the date of pipeline soil-to-air interfaces, that must be
light of new technology and the new installation. Pipelines installed after inspected, and specifies what remedial
requirements for hazardous liquid and July 31, 1971, must be entirely protected action to take. Although these
carbon dioxide pipelines in 49 CFR part from atmospheric corrosion, except differences are minor, we think the
195. where the operator can demonstrate that monitoring requirements for gas and
Deferring the recommendation also a corrosive atmosphere does not exist. hazardous liquid pipelines should be in
will give us time to gather more In contrast, pipelines installed before accord. Therefore, we are proposing to
information on the shorted casing issue. August 1, 1971, need only be protected amend § 192.481 to comport with
We are particularly interested in where atmospheric corrosion has § 195.583.
receiving comments from anyone who progressed to the point that remedial PS–124 commenters representing
has empirical data on the relation of action is required under § 192.485, industry largely objected to NAPSR’s
shorted casings to pipe corrosion. § 192.487, or § 192.489. Periodic recommendation to treat old and new
monitoring to determine the need for pipelines alike. They feared they would
17. Section 192.475(c), Internal remedial action is required by § 192.481. have to fully protect all pre-August 1971
Corrosion Control: General. (SIRRC As previously stated, we recently pipelines regardless of whether harmful
Summary Report, p. 29) revised the corrosion control regulations corrosion was present. However, there is
Recommendation. Amend in 49 CFR part 195 governing hazardous no basis for this concern under
§ 192.475(c) to express the permissible liquid and carbon dioxide pipelines. proposed § 192.479. Operators would
level of hydrogen sulfide in parts-per- The old rule on protection from not have to protect any pre-1971
million as well as grains. atmospheric corrosion (§ 195.416(i)) pipeline or portion of pipeline for

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00042 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules 68821

which the operator demonstrates by test, SIRRC. The committee agreed that the mains and service lines should be the
investigation, or experience appropriate problem of graphitization should be same because mains and service lines
to the environment of the pipeline that addressed case-by-case rather than by are operated together. NAPSR also felt
corrosion will only be a light surface changing § 192.489 as NAPSR the resulting safety factors should not
oxide or not affect safe operation before recommended. diminish as operating pressures
the next scheduled inspection. We Response. New technology may result increase, as they do under the present
believe this approach is consistent with in liners that strengthen as well as seal rules. Many PS–124 commenters,
the present rule. pipe. Therefore, we agree with SIRRC including some operators, agreed with
that § 192.489(b) should not be changed NAPSR. However, AGA and other
19. Section 192.483(d), Remedial
as NAPSR recommended. operators said there is no need to leak
Measures: General. (SIRRC Summary
test steel mains and service lines
Report, p. 32) 22. Sections 192.505(a) and 192.507,
operating at less than 100 psig at 1.5
Recommendation. Specify what Test Requirements. (SIRRC Summary
times operating pressure. These
operators must do to protect carrier pipe Report, p. 36)
commenters argued that the purpose of
when a shorted casing cannot be Recommendation. Amend §§ 192.505 leak tests is not to assure the pipeline
cleared. and 192.507 to clarify that the test is unlikely to fail at operating pressure,
SIRRC. The committee agreed that pressure must be high enough to but to verify that the pipeline does not
§ 192.483(d) should be established to substantiate the maximum allowable leak.
read as follows: operating pressure (MAOP) under The regulatory history does not
(d) If it is determined that a casing is § 192.619(a)(2)(ii). explain why minimum leak test
electrically shorted to a pipeline, the SIRRC. The committee did not reach pressures under §§ 192.509(b) and
operator shall: an agreement on this recommendation. 192.511(b) and (c) are not consistent.
(1) Clear the short, if practical; NAPSR members contended some Nevertheless, lack of consistency, by
(2) Fill the casing with a corrosion operators have not substantiated MAOP itself, does not justify additional or
inhibiting material; because §§ 192.505 and 192.507 do not more stringent test requirements. A link
(3) Monitor for leakage with leak specify a minimum test pressure. On the between inconsistency and safety would
detection equipment at least once each other hand, industry members thought be needed, and NAPSR did not establish
calendar year with intervals not that because § 192.503(a)(1) already such a link. Also, because only tests for
exceeding 15 months; or requires that pressure tests substantiate leaks rather than pipeline integrity are
(4) Conduct an initial inspection with
MAOP under § 192.619, there is no need at issue, we do not think safety factors
an internal inspection device capable of
to repeat the requirement in §§ 192.505 are relevant to determining if the
detecting external corrosion in a cased
and 192.507. present leak test pressures are
pipeline, and repeat at least every 5
Response. We addressed this issue appropriate. Therefore, we are not
years at intervals not exceeding 63
once before. In 1988 we amended proposing to adopt NAPSR’s
months.
Response. As stated above in response § 192.503(a)(1) specifically to indicate recommendation.
to Recommendation No. 16, there is that § 192.619 prescribes the minimum
24. Section 192.517, Records. (SIRRC
conflicting information on the need to test pressure needed to substantiate
Summary Report, p. 39)
clear shorted casings. Therefore, we are MAOP (53 FR 1635). We think this
earlier action adequately clarified the Recommendation. To aid compliance
not now proposing to adopt SIRRC’s investigations, amend § 192.517 to
suggested options for dealing with minimum test pressures, and no further
action is needed. require that operators keep records of
shorted casings. Instead, as with leak tests done under § 192.509 for
Recommendation No. 16, we will 23. Sections 192.509(b) and 192.511(b) pipelines to operate below 100 psig, of
consider this recommendation in a and (c), Test Requirements. (SIRRC leak tests done under § 192.511 for
separate rulemaking proceeding called Summary Report, p. 37) service lines, and of leak tests done
‘‘Pipeline Safety: Controlling Corrosion
Recommendation. To establish under § 192.513 for plastic pipelines.
on Gas Pipelines’’ (RIN 2137–AD63). SIRRC. The committee disagreed
consistent leak test pressures for mains
20. Section 192.483(e), Remedial and service lines, require that non- about what information is needed in
Measures: General. (SIRRC Summary plastic service lines operated at less leak test records. Also, industry
Report, p. 34) than 1 psig be tested to at least 10 psig. members were concerned that
Recommendation. Amend § 192.483 Also, require that each main and service distribution operators would have to
to refer to appropriate consensus line operated at 1 psig or more be tested keep a very large volume of individual
standards that are to be used in to 90 psig or 1.5 times the intended records of limited use.
determining the remaining strength of operating pressure, whichever is higher. Response. Section 192.517 requires
corroded pipe. SIRRC. The committee did not reach operators to record certain information
SIRRC. The committee agreed that a consensus on this recommendation. about pressure tests done under
further rulemaking action is not needed. Industry members were concerned that §§ 192.505 and 192.507 to qualify steel
Response. The Final Rule in Docket additional equipment would be needed pipelines to operate at 100 psig or more.
PS–124 covered NAPSR’s to test above 90 psig, and that testing NAPSR recommended that we extend
recommendation in an amendment to existing service lines at higher pressures this requirement to other pipelines that
§ 192.485(c). Thus, we agree with SIRRC (as when service is reinstated or are pressure tested for leaks. While a
that further action is not needed. connected to a new main) could cause few PS–124 commenters supported the
failures. NAPSR countered that recommendation, most did not. Those
21. Section 192.489(b), Remedial operators could use plastic pipe test who opposed the recommendation
Measures: Cast Iron and Ductile Iron equipment, and that a test failure generally argued that since leak tests are
Pipe. (SIRRC Summary Report, p. 35) indicates the line is unsafe. not as significant as tests done under
Recommendation. Clarify that Response. NAPSR felt the minimum §§ 192.505 and 192.507, it is
internal sealing of graphitized pipe is leak test pressures prescribed by unnecessary to maintain the same
not a method of strengthening the pipe. §§ 192.509(b) and 192.511(b) and (c) for information about both types of tests.

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00043 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
68822 Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules

Without appropriate records, because we feel the requirement to base effort, we will propose the necessary
government inspection personnel have a any increase in MAOP on a test pressure rule changes.
difficult job of determining if required is clear under § 192.553(d). This section
28. Section 192.615(a)(3)(i), Emergency
leak tests were indeed done. They may limits any increase in MAOP to the
Plans. (SIRRC Summary Report, p. 45)
have to interview witnesses or draw maximum allowed for new pipelines,
inferences from related information. On which, under § 192.619(a)(2)(ii), must be Recommendation. Amend
the other hand, government’s need for based on a pressure test. However, we § 192.615(a)(3)(i) to require that
records must be weighed against the are proposing to adopt SIRRC’s operators’ procedures for handling
burden on operators to produce and suggested change to clarify § 192.553(d). emergencies provide for prompt and
maintain the records. By and large, PS– effective response to reports of gas odor
26. Section 192.607, Determination of
124 commenters and SIRRC industry inside or near buildings.
Class Location and Confirmation of
members did not object to keeping SIRRC. The committee did not reach
Maximum Allowable Operating
records of leak tests. In fact, the SIRRC consensus on the recommended change
Pressure. (SIRRC Summary Report, p.
Summary Report states that keeping to § 192.615(a)(3)(i), because many
43)
some type of leak test record is a operators consider gas-odor reports to be
common industry practice. It was the Recommendation. Remove expired potential, but not actual, emergencies.
extent and volume of the records that compliance deadlines from § 192.607. Instead, the committee agreed that
SIRRC’s industry members found SIRRC. The committee agreed the operating and maintenance manuals
objectionable. recommendation was no longer needed. under § 192.605(b) are a better place for
In our view, NAPSR’s recommended Response. The Final Rule in PS–124
procedures on responding to gas-odor
leak test records would be too repealed § 192.607.
reports.
burdensome, because the safety 27. Section 192.614(b)(2), Damage Response. We agree that not all
significance of leak tests is less than that Prevention Program. (SIRRC Summary reports of gas odor indicate that gas has
of pressure tests done to establish the Report, p. 44) actually been detected. Some reports
MAOP of pipelines operating above 100 may merely indicate that someone
psig. At the same time, it seems that Recommendation. Require that
operators notify the public and known smells what is thought to be gas but
industry’s voluntary practices may which upon investigation cannot be
satisfy the need for records to excavators about excavation damage
prevention programs at least once a confirmed as gas. If operators had to
demonstrate compliance with leak test
year. treat all reports of gas odor as
requirements. Therefore, while we are
SIRRC. The committee agreed to defer emergencies, their ability to respond to
not proposing to adopt NAPSR’s
the recommendation to RSPA’s damage true emergencies might decline. Thus
recommendation, we are proposing to
prevention improvement team. (The we are not proposing to adopt NAPSR’s
amend § 192.517 to require that
work of that team has been assumed by recommendation.
operators maintain a record of each test
required by §§ 192.509, 192.511, and the Dig Safely division of the Common Regardless of whether a gas odor
192.513 for at least 5 years. This Ground Alliance, a nonprofit report is an emergency, both PS–124
proposal should accommodate the organization that promotes best commenters and SIRRC recognized the
industry’s various voluntary practices in damage prevention.) need for prompt investigation of gas
recordkeeping practices, and allow time Response. The present rule requires odor reports to determine if a hazardous
for government inspectors to view the operators to notify the public and situation exists. We believe that by and
records. The proposed rule would apply known excavators ‘‘as often as needed’’ large operators respond promptly to gas
to leak tests done after the rule takes to make them aware of the operator’s odor reports and have procedures for
effect. program. This open-ended frequency doing so. Nevertheless, to insure that
permits operators to vary the timing and operators have adequate procedures for
25. Section 192.553, Uprating: General number of notices to recipients responding promptly to gas odor
Requirements; § 192.557 Uprating: Steel according to the results of their reports, we are proposing to adopt
Pipelines to a Pressure That Will programs. Presumably fewer notices SIRRC’s suggested alternative by
Produce a Hoop Stress Less Than 30% would be needed in an area where the establishing § 192.605(b)(11). Because
of SMYS: Plastic, Cast Iron, and Ductile incidence of excavation damage is low some operators may prefer to apply their
Iron Pipelines. (SIRRC Summary Report, or dropping. Conversely, more would be emergency procedures to all reports of
P. 41) needed if the incidence is high or gas odor, the proposed rule allows them
Recommendation. Clarify that increasing. Although NAPSR felt the to do so.
§ 192.557 does not allow MAOP to be rule should prescribe a minimum rate of
29. Section 192.625 (f), Odorization of
increased without substantiation by notification, it did not explain why
Gas. (SIRRC Summary Report, p. 47)
pressure testing. annual notification is appropriate in all
SIRRC. The committee did not reach situations. And we do not have data to Recommendation. Require that
a resolution on this recommendation. support such an across-the-board rule operators sample gas to assure proper
Industry members were concerned that change. Nevertheless, we think odorant concentration at least six times
NAPSR’s recommended changes to NAPSR’s concern is mitigated by the a year with an instrument capable of
§ 192.557 would unintentionally authority of RSPA and state agencies determining the percentage of gas in air.
prohibit the uprating of some pipelines under § 192.603(c) to require operators SIRRC. The committee did not agree
that could be uprated under the present to modify their damage prevention on the frequency of sampling. Industry
rule. However, the committee did agree procedures on a case-by-case basis as members wanted to maintain the
that in § 192.553(d) the reference to needed for safety. Meanwhile, we are flexibility of the current rule, which
‘‘this part’’ should be changed to working with the Common Ground allows operators to determine frequency
‘‘§§ 192.619 and 192.621’’ to specify the Alliance to help operators improve their based on need. NAPSR members wanted
sections that limit MAOP. public education programs. If the need to add certainty to the rule by requiring
Response. We decided not to propose for rulemaking on notification frequency a sampling frequency that is in keeping
to adopt NAPSR’s recommendation becomes apparent as a result of that with common practice.

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00044 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules 68823

Nevertheless, the members did agree authorized to challenge any sampling 32. Section 192.743(a) and (b), Pressure
the rule should require use of an frequencies they consider deficient on Limiting and Regulating Stations:
instrument, although they recognized the basis of safety data. They may also Testing of Relief Devices. (SIRRC
that sampling for odorant concentration require operators to amend their Summary Report, p. 52)
could not be done without an procedures after considering any Recommendation. In view of the
instrument. They also agreed the master relevant information the operator disadvantages of testing relief devices in
meter exception should be relocated to provides. We believe this review and place (cost, noise, and potential safety
minimize the potential for confusion amendment process serves as a check on hazards from escaping gas), change
over the acceptability of using ‘‘sniff’’ any possible misuse of sampling § 192.743 to allow operators to use
tests. flexibility. Therefore, we are not calculations to determine if relief
Response. The present rule requires proposing to establish a minimum devices are of sufficient capacity
operators to conduct periodic sampling sampling frequency. without first having to determine that
to assure the proper concentration of testing the devices in place is not
odorant. However, operators of master 30. Section 192.723(b)(2), Distribution
feasible.
meter systems (which exist mainly in Systems: Leak Surveys. (SIRRC SIRRC. The committee members
mobile home parks and multifamily Summary Report, p. 49) agreed to accept NAPSR’s
housing) do not have to conduct recommendation.
sampling if the operator verifies the Recommendation. Amend
§ 192.723(b)(2) to allow leeway in Response. Under the present rule,
system receives properly odorized gas operators may not use calculations to
and performs ‘‘sniff’’ tests to confirm the meeting the leakage survey intervals.
determine necessary relief capacity until
presence of odorant at the ends of the SIRRC. The committee members they determine that testing existing
system. agreed that NAPSR’s recommendation relief devices in place is not feasible. In
NAPSR intended its recommendation was appropriate. addition to SIRRC, most PS–124
to address two concerns. The first was commenters supported NAPSR’s
Response. In the proceeding called
that some operators, other than master recommendation. For the reasons
‘‘Periodic Updates to Pipeline Safety
meter operators, used ‘‘sniff’’ tests rather NAPSR advanced, we also believe the
Regulations (1999)’’ (56 FR 15290; Mar.
than instruments to determine odorant recommended change is appropriate.
22, 2000), we proposed to amend
concentration. The second was that the Therefore, we are proposing to change
required sampling frequency is vague. § 192.723(b)(2) as NAPSR
recommended. §§ 192.743(a) and (b) to remove the
Regarding the first concern, both PS– present preference for testing relief
124 commenters and SIRRC recognized 31. Section 192.739(c), Pressure devices in place.
that the present sampling requirement Limiting and Regulating Stations:
cannot be satisfied without using an Inspection and Testing; § 192.743(c), 33. Section 192.745, Valve
appropriate test instrument. Indeed we Pressure Limiting and Regulating Maintenance: Transmission Lines.
believe use of an instrument is common Stations: Testing of Relief Devices. (SIRRC Summary Report, p. 53)
industry practice, because a sniff test (SIRRC Summary Report, p. 50) Recommendation. For each
cannot accurately determine the transmission line valve inspected under
concentration of odorant. Therefore, we Recommendation. Clarify the § 192.745, require that operators take
are proposing to amend § 192.625(f) to meaning of ‘‘correct pressure’’ in immediate remedial action on any valve
state specifically that an instrument § 192.739(c) and ‘‘insufficient capacity’’ found to be inoperable, inaccessible,
must be used to determine odorant in § 192.743(c) by cross-referencing improperly supported, subject to
concentration. In addition, we are not § 192.201, which limits the overpressure external loads or unusual stresses, or
proposing to relocate the master meter of pipelines protected by pressure inadequately protected from
exception, because we do not think its relieving and limiting stations. unauthorized operation, tampering, or
present location confuses the acceptable damage.
SIRRC. The committee agreed that
use of ‘‘sniff’’ tests. SIRRC. The committee did not reach
both sections should cross-reference
As to NAPSR’s second concern, we a resolution on this recommendation.
are certainly mindful of the importance § 192.201. However, the committee
revised NAPSR’s recommended Industry members questioned the need
of clarity in regulations. Yet we are for the recommended changes.
uneasy about proposing a minimum wording to clarify that the set point of
Response. Section 192.745 requires
sampling frequency that is not backed overpressure protective devices may be
annual inspection of transmission line
by consensus or a safety justification above the downstream MAOP.
valves that might be needed during an
that supports the frequency. At the same Response. We are proposing to change emergency. Because § 192.745 requires
time, we are persuaded by PS–124 §§ 192.739(c) and 192.743(c) consistent each inspection to include partial
commenters and SIRRC’s industry with SIRRC’s suggestions. The proposed operation of the valve, there is no
members’ view that sampling frequency changes would require that relief question operators must maintain these
is more appropriately determined on the devices at existing pressure limiting and valves in an operable condition.
basis of system conditions. A system regulating stations meet the same Section 192.745 does not regulate
might need sampling more often than standards for operation and relieving how soon a valve must be corrected if
six times a year in problem locations but capacity as newly installed relief it is found inoperable. NAPSR
less often at locations where odorant devices. The PS–124 comments and recommended immediate remedial
concentration consistently meets SIRRC’s perspective indicate that action. Most PS–124 industry
requirements. Also, under industry practices are generally in commenters preferred to act ‘‘as soon as
§ 192.605(b)(1), each operator’s accord with this approach to practical,’’ so they would not have to
operating and maintenance procedures compliance with §§ 192.739(c) and disrupt other essential services. But
must provide odorant sampling 192.743(c). So we believe the proposed NAPSR did not think this phrase
frequencies, and operators must be able changes would clarify these regulations reflected the urgency of the situation.
to justify the frequencies. Finally, under and not add significantly to the costs of In the absence of a specified time
§ 192.603(c), government regulators are compliance. limit for remedial action, operators may

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00045 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
68824 Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules

take a reasonable time. Although a improperly supported, subject to which distribution system valves are
reasonable time may be satisfactory for external loads or unusual stresses, or subject to § 192.747. If an identified
some maintenance duties, we agree with inadequately protected from safety valve is paved over without
NAPSR that emergency valves found unauthorized operation, tampering, or notice between annual inspections, the
inoperable need priority attention. damage. operator should discover the problem
Therefore, we are proposing to amend SIRRC. Although the committee did no later than the next annual inspection.
§ 192.745 to require operators to take not reach consensus on this At that time the operator would have to
prompt remedial action if any valve is recommendation, it agreed that either correct the problem in order to
found inoperable. Requiring prompt remediation could include designation carry out the inspection or revise its
action rather than immediate action of an alternate emergency valve. procedures to designate an alternative
should allow operators the latitude they Industry members were particularly safety valve.
sought in scheduling maintenance concerned that partial operation could
activities, yet assure a timely response. cause some valves to close 35. Section 192.753, Caulked Bell and
Part 192 design and construction inadvertently, with potentially Spigot Joints. (SIRRC Summary Report,
regulations already address most of dangerous consequences, and could p. 57)
NAPSR’s other objectives. For instance, damage valves not designed for frequent Recommendation. Correct the conflict
§ 192.179(b), a design rule, requires that operation. between § 192.621(a)(3), which allows a
onshore transmission line block valves Response. NAPSR’s rationale for pressure as high as 25 psig in cast iron
be readily accessible, protected from limiting the present rule to designated pipe with unreinforced bell and spigot
tampering and damage, and adequately emergency valves was to make clear joints, and § 192.753(a), which requires
supported. In addition, § 192.317, a which valves are to be inspected. cast-iron bell and spigot joints subject to
construction rule, requires protection of However, we think § 192.605(b)(1), pressures of 25 psig or more to be
transmission lines from external loads which requires operators to have sealed.
and unusual stresses. Moreover, if for procedures for complying with SIRRC. The committee members
any reason an emergency valve becomes § 192.747, adequately addresses agreed the conflict should be corrected.
unsafe, such as by damage or loss of NAPSR’s concern. Operators’ Response. We are proposing to change
support, § 192.703(b) would require procedures should not only explain how § 192.753 to remove the conflict.
remedial action. While § 192.703 does to inspect and service valves, but also
not establish a time limit for remedial identify which valves are to be Regulatory Analyses and Notices
action, we think a reasonable time is inspected and serviced. In addition, Executive Order 12866 and DOT
sufficient for any deficiency that does valves intended for safe operation of a Policies and Procedures
not make the valve inoperable. distribution system may not be the same
Therefore, we are not proposing to valves operators might designate for use RSPA does not consider this proposed
adopt NAPSR’s recommendation to in an emergency. So limiting the present rulemaking to be a significant regulatory
shorten the allowable response time to rule to emergency valves for the sake of action under Section 3(f) of Executive
deficiencies that do not make an clarity could inadvertently narrow the Order 12866 (58 FR 51735; Oct. 4,
emergency valve inoperable. rule. 1993). Therefore, the Office of
Part 192 does not regulate the Still we think that any valve that may Management and Budget (OMB) has not
protection of transmission line valves be needed for safe operation of a received a copy of this rulemaking to
from unauthorized operation. However, distribution system should receive review. RSPA also does not consider
operators commonly provide valve priority attention if it is found this proposed rulemaking to be
security. And unauthorized operation of inoperable. Therefore, we are proposing significant under DOT regulatory
valves has not been a significant to amend § 192.747 to require prompt policies and procedures (44 FR 11034:
problem on transmission lines. Also, remedial action if any such valve is February 26, 1979).
operators of large systems can detect found inoperable, unless the operator We prepared a Draft Regulatory
unauthorized operation of valves designates an alternate valve. For the Evaluation of the proposed rules, and a
through monitoring of system pressures. reasons stated above in response to copy is in the docket. This regulatory
Following the events of September 11, Recommendation No. 33, we are not evaluation concludes that the proposed
2001, we began working with operators proposing to adopt NAPSR’s changes to existing rules may actually
and other federal agencies to consider recommendation to require immediate reduce operators’ costs to comply with
the need to improve the security of remedial action on deficient valves that those rules because some proposals
critical pipeline facilities. Given these remain operable. Further, because of the have compliance options. If you
circumstances, we are not now possibility of adverse consequences to disagree with this conclusion, please
proposing to regulate the unauthorized the valve or others, we are not provide information to the public
operation of transmission line valves. proposing to require partial operation of docket described above.
valves.
34. Section 192.747 Valve Maintenance: The accessibility of distribution Regulatory Flexibility Act
Distribution Systems. (SIRRC Summary system valves has been a safety problem The proposed rules are consistent
Report, p. 54) in some situations. For instance, if a with customary practices in the gas
Recommendation. Change § 192.747, valve essential to stop the flow of gas in pipeline industry. Therefore, based on
which requires annual inspection and an emergency is found to be paved over, the facts available about the anticipated
servicing of each valve that may be the resulting delay in operating the impacts of this proposed rulemaking, I
needed for safe operation of a valve can worsen the emergency. We certify, pursuant to Section 605 of the
distribution system, to apply only to think § 192.605(b)(1) addresses this Regulatory Flexibility Act (5 U.S.C.
valves that operators designate for use problem. This rule requires distribution 605), that this proposed rulemaking
in an emergency. Also, require partial operators to have and follow procedures would not have a significant impact on
operation of each emergency valve, and to carry out the safety valve a substantial number of small entities. If
immediate remedial action if the valve maintenance requirements of § 192.747. you have any information that this
is found to be inoperable, inaccessible, And these procedures should identify conclusion about the impact on small

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00046 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules 68825

entities is not correct, please provide environmental assessment document is ‘‘Customer meter’’ means the meter
that information to the public docket available for review in the docket. A that measures the transfer of gas from an
described above. final determination on environmental operator to a consumer.
impact will be made after the end of the * * * * *
Executive Order 13084
comment period. If you disagree with
The proposed rules have been ‘‘Service line’’ means a distribution
our preliminary conclusion, please
analyzed in accordance with the line that transports gas from a common
submit your comments to the docket as
principles and criteria contained in source of supply to an individual
described above.
Executive Order 13084, ‘‘Consultation customer, to two adjacent or adjoining
and Coordination with Indian Tribal Impact on Business Processes and residential or small commercial
Governments.’’ Because the proposed Computer Systems customers, or to multiple residential or
rules would not significantly or We do not want to impose new small commercial customers served
uniquely affect the communities of the requirements that would mandate through a meter manifold. A service line
Indian tribal governments and would business process changes when the terminates at the outlet of the customer
not impose substantial direct resources necessary to implement those meter or at the connection to a
compliance costs, the funding and requirements would otherwise be customer’s piping, whichever is further
consultation requirements of Executive applied to ‘‘Y2K’’ or related computer downstream, or at the connection to
Order 13084 do not apply. problems. The proposed rules would customer piping if there is no meter.
not mandate business process changes ‘‘Service regulator’’ means the device
Paperwork Reduction Act on a service line which controls the
or require modifications to computer
Proposed §§ 192.517(b) and systems. Because the proposed rules pressure of gas delivered from a higher
192.605(b)(11) contain minor additional would not affect the ability of pressure to the pressure provided to the
information collection requirements. organizations to respond to those customer. A service regulator may serve
Operators would be required under problems, we are not proposing to delay one customer or multiple customers
§ 192.517(b) to maintain for 5 years the effectiveness of the requirements. through a meter header or manifold.
records of certain leak tests, and under * * * * *
§ 192.605(b)(11) to have procedures for Executive Order 13132
responding promptly to a report of gas The proposed rules have been § 192.123 [Amended]
odor inside or near a building. However, analyzed in accordance with the 3. Remove the second sentence in
we believe most operators already principles and criteria contained in § 192.123(b)(2)(i).
maintain records of leak tests and have Executive Order 13132 (‘‘Federalism’’).
procedures for responding to reports of The proposed rules do not propose any § 192.197 [Amended]
gas odor inside or near buildings. Also, regulation that: (1) Has substantial 4. In § 192.197(a), remove the term
we believe the burden of retaining these direct effects on the States, the ‘‘under 60 p.s.i. (414 kPa) gage’’ and add
records is minimal. These records are relationship between the National the term ‘‘60 psi (414 kPa) gage, or less,’’
largely computerized. Maintaining these government and the States, or the in its place.
records on a floppy disk or computer distribution of power and
file represents very minimal costs. So, responsibilities among the various § 192.285 [Amended]
because the additional paperwork levels of government; (2) imposes 5. In § 192.285(d), remove the term
burdens of this proposed rule are likely substantial direct compliance costs on ‘‘his’’ and add the term ‘‘the operator’s’’
to be minimal, we believe that State and local governments; or (3) in its place.
submitting an analysis of the burdens to preempts state law. Therefore, the
OMB under the Paperwork Reduction consultation and funding requirements 6. Revise § 192.311 to read as follows:
Act is unnecessary. If you disagree with of Executive Order 13132 do not apply. § 192.311 Repair of plastic pipe.
this conclusion, please submit your
comments to the public docket. List of Subjects in 49 CFR Part 192 Each imperfection or damage that
Natural gas, Pipeline safety, Reporting would impair the serviceability of
Unfunded Mandates Reform Act of 1995 and recordkeeping requirements. plastic pipe must be repaired or
This proposed rulemaking would not For the reasons discussed in the removed.
impose unfunded mandates under the preamble, RSPA proposes to amend 49 7. Revise § 192.321(e) to read as
Unfunded Mandates Reform Act of CFR part 192 as follows: follows:
1995. It would not result in costs of
$100 million or more to either State, PART 192—TRANSPORTATION OF § 192.321 Installation of plastic pipe.
local, or tribal governments, in the NATURAL AND OTHER GAS BY * * * * *
aggregate, or to the private sector, and PIPELINE: MINIMUM FEDERAL (e) Plastic pipe that is not encased
would be the least burdensome SAFETY STANDARDS must have an electrically conducting
alternative that achieves the objective of wire or other means of locating the pipe
the rule. 1. The authority citation for part 192
continues to read as follows: while it is underground. Tracer wire
National Environmental Policy Act may not be wrapped around the pipe
Authority: 49 U.S.C. 5103, 60102, 60104,
and contact with the pipe must be
We have analyzed the proposed rules 60108, 60109, 60110, 60113, and 60118; and
49 CFR 1.53. minimized. Tracer wire or other
for purposes of the National
metallic elements installed for pipe
Environmental Policy Act (42 U.S.C. 2. Amend § 192.3 by adding locating purposes must be resistant to
4321 et seq.). Because the proposed definitions of ‘‘customer meter’’ and corrosion damage, either by use of
rules parallel present requirements or ‘‘service regulator’’ and by revising the coated copper wire or by other means.
practices, we have preliminarily definition of ‘‘service line’’ as follows:
determined that the proposed rules * * * * *
would not significantly affect the § 192.3 Definitions. 8. Revise the first sentence of
quality of the human environment. An * * * * * § 192.353(a) to read as follows:

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00047 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
68826 Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules

§ 192.353 Customer meters and § 192.479 Atmospheric corrosion control: 15. In the first sentence in
regulators: Location. General. § 192.553(d), remove the term ‘‘this
(a) Each meter and service regulator, (a) Each operator must clean and coat part’’ and add the term ‘‘§§ 192.619 and
whether inside or outside of a building, each pipeline or portion of pipeline that 192.621’’ in its place.
must be installed in a readily accessible is exposed to the atmosphere, except 16. Add § 192.605(b)(11) to read as
location and be protected from pipelines under paragraph (c) of this follows:
corrosion, vehicular, and other damage. section.
(b) Coating material must be suitable § 192.605 Procedural manual for
* * * operations, maintenance, and emergencies.
* * * * * for the prevention of atmospheric
corrosion. * * * * *
9. Add § 192.361(g) to read as follows: (b) * * *
(c) Except portions of pipelines in
§ 192.361 Service lines: Installation. offshore splash zones or soil-to-air (11) Responding promptly to a report
interfaces, the operator need not protect of gas odor inside or near a building,
* * * * *
against atmospheric corrosion any unless the operator’s emergency
(g) Locating underground service procedures under § 192.615(a)(3)
lines. Each underground service line pipeline for which the operator
demonstrates by test, investigation, or specifically apply to these reports.
that is not encased must have a means
of locating the pipe that complies with experience appropriate to the * * * * *
§ 192.321(e). environment of the pipeline that 17. Revise the first sentence of
corrosion will— § 192.625(f) introductory text to read as
§ 192.457 [Amended] (1) Only be a light surface oxide; or follows:
10. Amend § 192.457 as follows: (2) Not affect the safe operation of the
§ 192.625 Odorization of gas.
a. Remove the second sentence in pipeline before the next scheduled
inspection. * * * * *
paragraph (b)(3); and
13. Revise § 192.481 to read as (f) To assure the proper concentration
b. Remove paragraph (c). of odorant in accordance with this
11. Revise § 192.465(e) to read as follows:
section, each operator must conduct
follows: § 192.481 Atmospheric corrosion control: periodic sampling of combustible gases
Monitoring. using an instrument capable of
§ 192.465 External corrosion control:
Monitoring. (a) Each operator must inspect each determining the percentage of gas in air
* * * * * pipeline or portion of pipeline that is at which the odor becomes readily
exposed to the atmosphere for evidence detectable. * * *
(e) After the initial evaluation
of atmospheric corrosion, as follows: * * * * *
required by §§ 192.455(b) and (c) and
192.457(b), each operator must, not less 18. Revise § 192.739(c) to read as
(1) If the pipe- Then the frequency of in- follows:
than every 3 years at intervals not line is lo- spection is:
exceeding 39 months, reevaluate its cated: § 192.739 Pressure limiting and regulating
unprotected pipelines and cathodically (2) Onshore At least once every 3 cal- stations: Inspection and testing.
protect them in accordance with this endar years, but with inter- * * * * *
subpart in areas in which active vals not exceeding 39
(c) Set to control or relieve at the
corrosion is found. The operator must months
(3) Offshore At least once each calendar correct pressures consistent with the
determine the areas of active corrosion pressure limits of § 192.201(a); and
by electrical survey. However, on year, but with intervals not
distribution lines and where an exceeding 15 months. * * * * *
electrical survey is impractical on 19. Revise § 192.743 to read as
(b) During inspections the operator follows:
transmission lines, areas of active
must give particular attention to pipe at
corrosion may be determined by other § 192.743 Pressure limiting and regulating
soil-to-air interfaces, under thermal
means that include review and analysis stations: Capacity of relief devices.
insulation, under disbonded coatings, at
of leak repair and inspection records, (a) Pressure relief devices at pressure
pipe supports, in splash zones, at deck
corrosion monitoring records, exposed limiting stations and pressure regulating
penetrations, and in spans over water.
pipe inspection records, and the stations must have sufficient capacity to
(c) If atmospheric corrosion is found
pipeline environment. In this section: protect the facilities to which they are
during an inspection, the operator must
(1) Active corrosion means continuing provide protection against the corrosion connected consistent with the pressure
corrosion which, unless controlled, as required by § 192.479. limits of § 192.201(a). This capacity
could result in a condition that is 14. Amend § 192.517 as follows: must be determined at intervals not
detrimental to public safety or the a. Designate the introductory text as exceeding 15 months, but at least once
environment. paragraph (a); each calendar year, by testing the
(2) Electrical survey means a series of b. In newly designated paragraph (a), devices in place or by review and
closely spaced pipe-to-soil readings over redesignate paragraphs (a), (b), (c), (d), calculations.
a pipeline that are subsequently (e), (f), and (g) as (a)(1), (2), (3), (4), (5), (b) If review and calculations are used
analyzed to identify locations where a (6), and (7), respectively; and to determine if a device has sufficient
corrosive current is leaving the pipeline. c. Add paragraph (b) to read as capacity, the calculated capacity must
(3) Pipeline environment includes soil follows: be compared with the rated or
resistivity (high or low), soil moisture experimentally determined relieving
(wet or dry), soil contaminants that may § 192.517 Records. capacity of the device for the conditions
promote corrosive activity, and other * * * * * under which it operates. After the initial
known conditions that could affect the (b) Each operator must maintain a calculations, subsequent calculations
probability of active corrosion. record of each test required by need not be made if the annual review
12. Revise § 192.479 to read as §§ 192.509, 192.511, and 192.513 for at documents that parameters have not
follows: least 5 years. changed so as to cause the rated or

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00048 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1
Federal Register / Vol. 67, No. 219 / Wednesday, November 13, 2002 / Proposed Rules 68827

experimentally determined relieving 21. Amend § 192.747 as follows: § 192.753 Caulked bell and spigot joints.
capacity to be insufficient. a. Designate the existing text as (a) Each cast iron caulked bell and
(c) If a relief device is of insufficient spigot joint that is subject to pressures
paragraph (a); and
capacity, a new or additional device of more than 25 psi (172kPa) gage must
must be installed to provide the b. Add paragraph (b) to read as
be sealed with:
capacity required by paragraph (a) of follows:
this section. * * * * *
§ 192.747 Valve maintenance: Distribution (b) Each cast iron caulked bell and
20. Amend § 192.745 as follows:
a. Designate the existing text as systems. spigot joint that is subject to pressures
paragraph (a); and * * * * * of 25 psi (172kPa) gage or less and is
b. Add paragraph (b) to read as (b) Each operator must take prompt exposed for any reason must be sealed
follows: remedial action to correct any valve by a means other than caulking.
§ 192.745 Valve maintenance: found inoperable, unless the operator Issued in Washington, DC, on October 31,
Transmission lines. designates an alternate valve. 2002.
* * * * * Stacey L. Gerard,
22. In § 192.753, revise the
(b) Each operator must take prompt introductory text of paragraph (a) and Associate Administrator for Pipeline Safety.
remedial action to correct any valve revise paragraph (b) to read as follows: [FR Doc. 02–28240 Filed 11–12–02; 8:45 am]
found inoperable. BILLING CODE 4910–60–P

VerDate 0ct<31>2002 15:00 Nov 12, 2002 Jkt 200001 PO 00000 Frm 00049 Fmt 4702 Sfmt 4702 E:\FR\FM\13NOP1.SGM 13NOP1

Anda mungkin juga menyukai