Incident Report
Summary
Specifically, what caused the incident (who, what, where, when, how)?
The fault cleared by installing Extra BPK Card
The Notification Process
Detail the flow of the incident response (i.e. John -> Jim -> Mike)
NOC-Mokete-NOC
Communication of resolution of the outage
The fault was attended and after its resolution NOC was contacted on order to update the network status.
COMPANY CONFIDENTIAL
The form to be completed and reach NOC within 24 hrs of fault clearance
COMPANY CONFIDENTIAL
Downtime .
Revenue producing.
COMPANY CONFIDENTIAL
The form to be completed and reach NOC within 24 hrs of fault clearance