BARCHART

PENYELESAIAN PELEBARAN SEMPU - DUKUH KAWUNG ( SEMPU - CILAKU )


ID Task Name Start Finish April 2017 May 2017 June 2017 July 2017 August 2017
13 18 23 28 03 08 13 18 23 28 02 07 12 17 22 27 02 07 12 17 22 27 01 06 11 16 21 26
1 MULAI Fri 21/04/17 Fri 21/04/17 21/04
2 DIVISI 1. UMUM Fri 21/04/17 Fri 18/08/17
3 1.2 Mobilisasi Fri 21/04/17 Fri 18/08/17
4 1.8.1 Manajemen dan Keselamatan Lalu Lintas Fri 21/04/17 Fri 18/08/17
5 1.2.1 Manajemen Mutu Fri 12/05/17 Fri 18/08/17
6 DIVISI 2. DRAINASE Fri 21/04/17 Thu 01/06/17
7 2.1.(1) Galian Untuk Selokan Drainase dan Saluran Air Fri 21/04/17 Thu 04/05/17
8 2.3.(4) Gorong - gorong Pipa Beton Bertulang Persegi Lebar Dalam 100 cm HD Fri 12/05/17 Thu 01/06/17
Precast
9 2.3.(6) Gorong-gorong Pipa Beton Bertulang Persegi lebar dalam 120 cm Precast Fri 05/05/17 Thu 01/06/17
HD Box Utilitas
10 2.3.(11) Saluran berbentuk U Tipe DS 3 Fri 28/04/17 Thu 01/06/17
11 2.3.(12) Beton K250 (fc 20) untuk struktur drainase beton minor Fri 19/05/17 Thu 01/06/17
12 2.3.(13) Baja Tulangan untuk struktur drainase beton minor Fri 19/05/17 Thu 01/06/17
13 DIVISI 3. PEKERJAAN TANAH Fri 26/05/17 Thu 22/06/17
14 3.1.(1a) Galian Biasa Fri 26/05/17 Thu 15/06/17
15 3.1.(6) Galian Perkerasaan Beraspal Dengan Cold Milling Machine Fri 09/06/17 Thu 15/06/17
16 3.2 (1b) Timbunan Biasa dari Galian Fri 09/06/17 Thu 22/06/17
17 3.3.(1) Penyiapan Badan Jalan Fri 02/06/17 Thu 22/06/17
18 DIVISI 4. PELEBARAN PERKERASAAN DAN BAHU JALAN Fri 16/06/17 Thu 13/07/17
19 4.2.(2a) Lapis Pondasi Aggregat Klas B Fri 16/06/17 Thu 13/07/17
20 DIVISI 5. PERKERASAN BERBUTIR Fri 16/06/17 Thu 27/07/17
21 5.1.2 Lapis Pondasi Aggregat Klas B Fri 16/06/17 Thu 13/07/17
22 5.3.1 Perkerasan Beton Semen Fri 30/06/17 Thu 27/07/17
23 5.3.3 Lapis Pondasi Bawah Beton Kurus Fri 30/06/17 Thu 27/07/17
24 DIVISI 7. STRUKTUR Fri 30/06/17 Thu 10/08/17
25 7.3.(1) Baja Tulangan U 24 Polos Fri 30/06/17 Thu 27/07/17
26 7.3.(6) Anyaman Kawat Yang dilas (Welded Wire Mesh) Fri 30/06/17 Thu 27/07/17
27 7.9.(1) Pasangan Batu Fri 28/07/17 Thu 10/08/17
28 7.15.(1) Pembongkaran Pasangan Batu Fri 28/07/17 Thu 03/08/17
29 DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR Fri 21/07/17 Fri 18/08/17
30 8.1 (2) Lapis Pondasi Agregat Kelas B utk Pekerjaan Minor Fri 28/07/17 Thu 03/08/17
31 8.4.(1) Marka Jalan Termoplastik Fri 28/07/17 Thu 03/08/17
32 8.4.(10a) Kerb Pracetak Jenis 1 (Peninggi/Mountable) Fri 28/07/17 Thu 10/08/17
33 8.4.(12) Perkerasan Blok Beton pada Trotoar dan Median Fri 21/07/17 Fri 18/08/17
34 SELESAI Fri 18/08/17 Fri 18/08/17 18/08

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


PT. BANTEN KIDUL JAYA UTAMA
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone


BARCHART
PENYELESAIAN PELEBARAN SEMPU - DUKUH KAWUNG ( SEMPU - CILAKU )

September 2017 October 2017 November 2017 December 2017 January 2018 February 2018 March 2018 April 2018 May 2018
26 31 05 10 15 20 25 30 05 10 15 20 25 30 04 09 14 19 24 29 04 09 14 19 24 29 03 08 13 18 23 28 02 07 12 17 22 27 04 09 14 19 24 29 03 08 13 18 23 28 03 08 13

18/08

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


PT. BANTEN KIDUL JAYA UTAMA
Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone