This Project Quality Plan document provides a checklist for reinforcing steel with 12 points to verify including receiving material approval, using the correct material sizes and spacers, properly installing rebar with ties and hooks, and special requirements. The checklist requires sign off from site engineers, MEP engineers, project engineers, project managers, HSEQ staff, and QA/QC personnel.
This Project Quality Plan document provides a checklist for reinforcing steel with 12 points to verify including receiving material approval, using the correct material sizes and spacers, properly installing rebar with ties and hooks, and special requirements. The checklist requires sign off from site engineers, MEP engineers, project engineers, project managers, HSEQ staff, and QA/QC personnel.
This Project Quality Plan document provides a checklist for reinforcing steel with 12 points to verify including receiving material approval, using the correct material sizes and spacers, properly installing rebar with ties and hooks, and special requirements. The checklist requires sign off from site engineers, MEP engineers, project engineers, project managers, HSEQ staff, and QA/QC personnel.
Project No. 19 Project Name Project detail/ Location
Check list for Reinforcement
Location : Drawing Ref : Sheet No .
S. No. Points to be verified Yes No N/A Remarks
1 Is the material approval received 2 Is the material as per the approval 3 Has the approval for Bar bending schedule taken 4 Are the rebars free from rust corrosion 5 Are all the bars of the correct sizes as per drawing & specs. 6 Is the spacing as per drawing & specs. 7 Is the inspection of reinforcement after placing in position done 8 Has the additional steel around cutouts / ducts / sleeves / lap lengths been checked 9 Whether chairs are provided to keep the top bar horizontal for footings/slabs etc., stirrups, hooks etc. if any 10 Whether binding wire properly tightened 11 Whether proper spacers are installed & are sufficient 12 Are all the starter bars and splices of correct sizes & number Other special requirements/Remarks:
NAME SIGNATURE DATE
Site Engineer MEP Engineer NA Project Engineer Project Manager HSEQ QA/QC Incharge