Total
Harga Satuan (Rp)
Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah
(Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
B. Pemasangan Pagar Sementara dari Kayu tinggi 2
6.1
m (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
6.4 C. Memasang Bouwplank (m)
SNI 03-2835-2002 Bahan
Kayu 5/7 M 0.012 1,700,000.00 20,400.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Total
Harga Satuan (Rp)
Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah
(Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
Overhead 560.00
Jumlah tenaga - Over Head 5,040.00
B. Pemasangan Pagar Sementara dari Kayu tinggi 2 m
6.1
(m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
Overhead 18,871.50
Jumlah tenaga - Over Head 169,843.50
6.4 C. Memasang Bouwplank (m)
II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
Overhead 1,600.00
Jumlah tenaga - Over Head 14,400.00
Total
Harga Satuan (Rp)
Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah
(Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-
Tenaga
2002
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
B. Pemasangan Pagar Sementara dari Kayu tinggi 2
6.1
m (m)
SNI 03-2835-
Bahan
2002
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
6.4 C. Memasang Bouwplank (m)
II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-
Tenaga
2002
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
6.9 B. Urugan Kembali (m)
SNI 03-2835-
Tenaga
2002
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00
6.11 C. Urugan Pasir Bawah Pondasi (m)
SNI 03-2835-
Bahan
2002
Pasir Urug M 1.200 100,000.00 120,000.00
Tenaga
II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
Overhead 1,600.00
Jumlah tenaga - Over Head 14,400.00
II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
6.9 B. Urugan Kembali (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00
6.11 C. Urugan Pasir Bawah Pondasi (m)
SNI 03-2835-2002 Bahan
Pasir Urug M 1.200 100,000.00 120,000.00
Tenaga
Pekerja Oh 0.300 36,000.00 10,800.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 131,200.00
IV PEKERJAAN BETON
A. Membuat sloof Beton Bertulang (200Kg
6.39
besi+bekisting) (m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.270 2,000,000.00 540,000.00
Paku Biasa 2"-5" Kg 2.000 10,000.00 20,000.00
Minyak Bekisting Lt 0.600 10,000.00 6,000.00
Besi Beton polos Kg 200.000 12,000.00 2,400,000.00
Kawat Beton Kg 3.000 13,000.00 39,000.00
Semen Portland Kg 323.000 1,050.00 339,150.00
Pasir Beton M 0.520 125,000.00 65,000.00
Koral Beton M 0.780 135,000.00 105,300.00
Tenaga
Pekerja Oh 4.850 36,000.00 174,600.00
Tukang Batu Oh 0.350 42,500.00 14,875.00
Tukang Kayu Oh 1.560 47,500.00 74,100.00
Tukang Besi Oh 1.400 45,000.00 63,000.00
Kepala Tukang Oh 0.331 45,000.00 14,895.00
Mandor Oh 0.170 40,000.00 6,800.00
Sub Total 3,862,720.00
B. Membuat Kolom Beton Bertulang (300Kg
6.40
besi+bekisting) (m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.400 2,000,000.00 800,000.00
V PEKERJAAN DINDING
A. Pasangan Tembok Bata 1Pc:4Ps (Trasraam)
6.11
(m)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 11.500 1,050.00 12,075.00
Pasir Pasang M 0.043 125,000.00 5,375.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 69,270.00
6.15 B. Pasangan Tembok Bata 1Pc:3Kp:10Ps (m)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 4.500 1,050.00 4,725.00
Pasir Pasang M 0.050 125,000.00 6,250.00
Kapur Padam M 0.015 45,000.00 675.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 63,470.00
Total
Harga Satuan (Rp)
Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah
(Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
Overhead 560.00
Jumlah tenaga - Over Head 5,040.00
6.1 B. Pemasangan Pagar Sementara dari Kayu tinggi 2 m (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
IV PEKERJAAN BETON
A. Membuat sloof Beton Bertulang (200Kg besi+bekisting)
6.39
(m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.270 2,000,000.00 540,000.00
Paku Biasa 2"-5" Kg 2.000 10,000.00 20,000.00
Minyak Bekisting Lt 0.600 10,000.00 6,000.00
Besi Beton polos Kg 200.000 12,000.00 2,400,000.00
Kawat Beton Kg 3.000 13,000.00 39,000.00
Semen Portland Kg 323.000 1,050.00 339,150.00
Pasir Beton M 0.520 125,000.00 65,000.00
Koral Beton M 0.780 135,000.00 105,300.00
Tenaga
Pekerja Oh 4.850 36,000.00 174,600.00
Tukang Batu Oh 0.350 42,500.00 14,875.00
Tukang Kayu Oh 1.560 47,500.00 74,100.00
Tukang Besi Oh 1.400 45,000.00 63,000.00
Kepala Tukang Oh 0.331 45,000.00 14,895.00
Mandor Oh 0.170 40,000.00 6,800.00
Sub Total 3,862,720.00
Overhead 386,272.00
Jumlah tenaga - Over Head 3,476,448.00
B. Membuat Kolom Beton Bertulang (300Kg besi+bekisting)
6.40
(m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.400 2,000,000.00 800,000.00
Paku Biasa 2"-5" Kg 4.000 10,000.00 40,000.00
V PEKERJAAN DINDING
6.11 A. Pasangan Tembok Bata 1Pc:4Ps (Trasraam) (m)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 11.500 1,050.00 12,075.00
Pasir Pasang M 0.043 125,000.00 5,375.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 69,270.00
Overhead 6,927.00
Jumlah tenaga - Over Head 62,343.00
6.15 B. Pasangan Tembok Bata 1Pc:3Kp:10Ps (m)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 4.500 1,050.00 4,725.00
Pasir Pasang M 0.050 125,000.00 6,250.00
Kapur Padam M 0.015 45,000.00 675.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00