Anda di halaman 1dari 42

RAB DAN RAP PROYEK GEDUNG

1. PEKERJAAN CUT AND FILL


RAB Cut and Fill
Tabel Analisa Harga Satuan

Total
Harga Satuan (Rp)
Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah
(Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
B. Pemasangan Pagar Sementara dari Kayu tinggi 2
6.1
m (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
6.4 C. Memasang Bouwplank (m)
SNI 03-2835-2002 Bahan
Kayu 5/7 M 0.012 1,700,000.00 20,400.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00

Iswati Septya (3336130275) 2


RAB DAN RAP PROYEK GEDUNG
Kayu Papan Bengkirai 3/20 M 0.007 3,541,666.00 24,791.66
Tenaga
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Pekerja Oh 0.100 36,000.00 3,600.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.005 40,000.00 200.00
Sub Total 54,391.66
ALS D. Memasang Papan Nama Proyek 80x120 cm (Bh)
Bahan
Kayu Meranti Btg 0.035 1,687,000.00 59,045.00
Paku Biasa 2"-5" Kg 0.600 10,000.00 6,000.00
Seng Lembaran 90 cm M 1.400 27,000.00 37,800.00
Cat kayu Kg 1.500 38,000.00 57,000.00
Semen Portland Kg 16.800 1,050.00 17,640.00
Pasir Beton M 0.027 125,000.00 3,375.00
Koral Beton M 0.041 135,000.00 5,535.00
Tenaga
Tukang Kayu Oh 1.000 47,500.00 47,500.00
Tukang Batu Oh 0.018 42,500.00 765.00
Tukang Cat Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.100 36,000.00 75,600.00
Mandor Oh 1.005 40,000.00 40,200.00
Sub Total 392,960.00
6.5 E. Membuat direksi keet & Gudang Sementara (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Kayu 5/7 M 0.180 1,700,000.00 306,000.00
Paku Biasa 2"-5" Kg 0.850 10,000.00 8,500.00
Besi Strip Kg 1.100 11,000.00 12,100.00
Semen Portland Kg 35.000 1,050.00 36,750.00
Pasir Pasang M 0.150 125,000.00 18,750.00
Pasir Beton M 0.100 125,000.00 12,500.00
Koral Beton M 0.150 135,000.00 20,250.00
Bata Merah Bh 30.000 500.00 15,000.00
Seng Plat Lbr 0.250 27,000.00 6,750.00

Iswati Septya (3336130275) 3


RAB DAN RAP PROYEK GEDUNG
Jendela Nako Bh 2.0000 12,500.00 25,000.00
Kaca Polos 3 mm M 0.080 50,000.00 4,000.00
Kunci Tanam Bh 0.150 25,000.00 3,750.00
Plywood 4 mm Lbr 0.060 50,000.00 3,000.00
Tenaga
Tukang Kayu Oh 2.000 47,500.00 95,000.00
Tukang Batu Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.000 36,000.00 72,000.00
Kepala Tukang Oh 0.800 45,000.00 36,000.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 751,100.00

II PEKERJAAN CUT and Fill


6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
6.9 B. Urugan Kembali (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00
6.11 C. Urugan Pasir Bawah Pondasi (m)
SNI 03-2835-2002 Bahan
Pasir Urug M 1.200 100,000.00 120,000.00
Tenaga
Pekerja Oh 0.300 36,000.00 10,800.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 131,200.00

Iswati Septya (3336130275) 4


RAB DAN RAP PROYEK GEDUNG
Tabel Rencana Anggaran Biaya

Harga Jumlah Total Harga


No Jenis Pekerjaan Satuan Volume
Satuan (Rp) Harga (Rp) (Rp)

A PEKERJAAN PERSIAPAN 42,188,844.26


1 Pembersihan Lahan m 308.120 5,600.00 1,725,472.00
2 Pemasangan Pagar Sementara dari Kayu tinggi 2 m m 72.740 188,715.00 13,727,129.10
3 Memasang Bouwplank m 38.000 54,391.66 2,066,883.16
4 Memasang Papan Nama Proyek 80x120 cm Bh 1.000 392,960.00 392,960.00
5 Membuat direksi keet & Gudang Sementara m 24.000 751,100.00 18,026,400.00
6 Listrik dan Air Kerja Ls 1.000 2,000,000.00 2,000,000.00
7 Mob & Demob Alat Ls 1.000 2,000,000.00 2,000,000.00
8 Tes Material Baja dan Beton Ls 1.000 1,500,000.00 1,500,000.00
9 Rambu - rambu lalu lintas dan keselamatan Kerja Ls 1.000 750,000.00 750,000.00

B PEKERJAAN TANAH 1,383,800.98


1 Galian Tanah Biasa sedalam 1 m m 52.788 16,000.00 844,608.00
2 Urugan Kembali m 13.197 7,672.00 101,247.38
3 Urugan Pasir Bawah Pondasi m 3.338 131,200.00 437,945.60

Tabel Rekapitulasi RAB

No Jenis Pekerjaan Harga (Rp)


I PEKERJAAN PERSIAPAN Rp 42,188,844.26
II PEKERJAAN TANAH Rp 1,383,800.98
JUMLAH Rp 43,572,645.24
PPN 10% Rp 4,357,264.52
TOTAL JUMLAH Rp 47,929,909.76

Iswati Septya (3336130275) 5


RAB DAN RAP PROYEK GEDUNG
Gravik Kurva S RAB Cut and Fill

Iswati Septya (3336130275) 6


RAB DAN RAP PROYEK GEDUNG
RAP Cut and Fill

Tabel Analisa Harga Satuan

Total
Harga Satuan (Rp)
Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah
(Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
Overhead 560.00
Jumlah tenaga - Over Head 5,040.00
B. Pemasangan Pagar Sementara dari Kayu tinggi 2 m
6.1
(m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
Overhead 18,871.50
Jumlah tenaga - Over Head 169,843.50
6.4 C. Memasang Bouwplank (m)

Iswati Septya (3336130275) 7


RAB DAN RAP PROYEK GEDUNG
SNI 03-2835-2002 Bahan
Kayu 5/7 M 0.012 1,700,000.00 20,400.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Kayu Papan Bengkirai 3/20 M 0.007 3,541,666.00 24,791.66
Tenaga
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Pekerja Oh 0.100 36,000.00 3,600.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.005 40,000.00 200.00
Sub Total 54,391.66
Overhead 5,439.17
Jumlah tenaga - Over Head 48,952.50
ALS D. Memasang Papan Nama Proyek 80x120 cm (Bh)
Bahan
Kayu Meranti Btg 0.035 1,687,000.00 59,045.00
Paku Biasa 2"-5" Kg 0.600 10,000.00 6,000.00
Seng Lembaran 90 cm M 1.400 27,000.00 37,800.00
Cat kayu Kg 1.500 38,000.00 57,000.00
Semen Portland Kg 16.800 1,050.00 17,640.00
Pasir Beton M 0.027 125,000.00 3,375.00
Koral Beton M 0.041 135,000.00 5,535.00
Tenaga
Tukang Kayu Oh 1.000 47,500.00 47,500.00
Tukang Batu Oh 0.018 42,500.00 765.00
Tukang Cat Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.100 36,000.00 75,600.00
Mandor Oh 1.005 40,000.00 40,200.00
Sub Total 392,960.00
Overhead 39,296.00
Jumlah tenaga - Over Head 353,664.00
6.5 E. Membuat direksi keet & Gudang Sementara (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Kayu 5/7 M 0.180 1,700,000.00 306,000.00
Paku Biasa 2"-5" Kg 0.850 10,000.00 8,500.00

Iswati Septya (3336130275) 8


RAB DAN RAP PROYEK GEDUNG
Besi Strip Kg 1.100 11,000.00 12,100.00
Semen Portland Kg 35.000 1,050.00 36,750.00
Pasir Pasang M 0.150 125,000.00 18,750.00
Pasir Beton M 0.100 125,000.00 12,500.00
Koral Beton M 0.150 135,000.00 20,250.00
Bata Merah Bh 30.000 500.00 15,000.00
Seng Plat Lbr 0.250 27,000.00 6,750.00
Jendela Nako Bh 2.0000 12,500.00 25,000.00
Kaca Polos 3 mm M 0.080 50,000.00 4,000.00
Kunci Tanam Bh 0.150 25,000.00 3,750.00
Plywood 4 mm Lbr 0.060 50,000.00 3,000.00
Tenaga
Tukang Kayu Oh 2.000 47,500.00 95,000.00
Tukang Batu Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.000 36,000.00 72,000.00
Kepala Tukang Oh 0.800 45,000.00 36,000.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 751,100.00
Overhead 75,110.00
Jumlah tenaga - Over Head 675,990.00

II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
Overhead 1,600.00
Jumlah tenaga - Over Head 14,400.00

6.9 B. Urugan Kembali (m)


SNI 03-2835-2002 Tenaga
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00

Iswati Septya (3336130275) 9


RAB DAN RAP PROYEK GEDUNG
Overhead 767.20
Jumlah tenaga - Over Head 6,904.80
6.11 C. Urugan Pasir Bawah Pondasi (m)
SNI 03-2835-2002 Bahan
Pasir Urug M 1.200 100,000.00 120,000.00
Tenaga
Pekerja Oh 0.300 36,000.00 10,800.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 131,200.00
Overhead 13,120.00
Jumlah tenaga - Over Head 118,080.00

Tabel Rencana Anggaran Pelaksanaan

Harga Jumlah Total Harga


No Jenis Pekerjaan Satuan Volume
Satuan (Rp) Harga (Rp) (Rp)

A PEKERJAAN PERSIAPAN 38,594,959.83


1 Pembersihan Lahan m 308.120 5,040.00 1,552,924.80
2 Pemasangan Pagar Sementara dari Kayu tinggi 2 m m 72.740 169,843.50 12,354,416.19
3 Memasang Bouwplank m 38.000 48,952.50 1,860,194.84
4 Memasang Papan Nama Proyek 80x120 cm Bh 1.000 353,664.00 353,664.00
5 Membuat direksi keet & Gudang Sementara m 24.000 675,990.00 16,223,760.00
6 Listrik dan Air Kerja Ls 1.000 2,000,000.00 2,000,000.00
7 Mob & Demob Alat Ls 1.000 2,000,000.00 2,000,000.00
8 Tes Material Baja dan Beton Ls 1.000 1,500,000.00 1,500,000.00
9 Rambu - rambu lalu lintas dan keselamatan Kerja Ls 1.000 750,000.00 750,000.00

B PEKERJAAN TANAH 1,245,420.89


1 Galian Tanah Biasa sedalam 1 m m 52.788 14,400.00 760,147.20
2 Urugan Kembali m 13.197 6,904.80 91,122.65
3 Urugan Pasir Bawah Pondasi m 3.338 118,080.00 394,151.04

Iswati Septya (3336130275) 10


RAB DAN RAP PROYEK GEDUNG
Tabel Rekapitulasi RAP

No Jenis Pekerjaan Harga (Rp)


I PEKERJAAN PERSIAPAN Rp 38,594,959.83
II PEKERJAAN TANAH Rp 1,245,420.89
TOTAL JUMLAH Rp 39,840,380.72
PPN 10% Rp 3,984,038.07
dibulatkan Rp 43,824,418.79

Gravik Kurva S RAP Cut n Fill

Iswati Septya (3336130275) 11


RAB DAN RAP PROYEK GEDUNG
2. PEKERJAAN PONDASI BATU KALI
RAB Pondasi Batu Kali

Tabel Analisa Harga Satuan

Total
Harga Satuan (Rp)
Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah
(Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-
Tenaga
2002
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
B. Pemasangan Pagar Sementara dari Kayu tinggi 2
6.1
m (m)
SNI 03-2835-
Bahan
2002
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
6.4 C. Memasang Bouwplank (m)

Iswati Septya (3336130275) 12


RAB DAN RAP PROYEK GEDUNG
SNI 03-2835-
Bahan
2002
Kayu 5/7 M 0.012 1,700,000.00 20,400.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Kayu Papan Bengkirai 3/20 M 0.007 3,541,666.00 24,791.66
Tenaga
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Pekerja Oh 0.100 36,000.00 3,600.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.005 40,000.00 200.00
Sub Total 54,391.66
ALS D. Memasang Papan Nama Proyek 80x120 cm (Bh)
Bahan
Kayu Meranti Btg 0.035 1,687,000.00 59,045.00
Paku Biasa 2"-5" Kg 0.600 10,000.00 6,000.00
Seng Lembaran 90 cm M 1.400 27,000.00 37,800.00
Cat kayu Kg 1.500 38,000.00 57,000.00
Semen Portland Kg 16.800 1,050.00 17,640.00
Pasir Beton M 0.027 125,000.00 3,375.00
Koral Beton M 0.041 135,000.00 5,535.00
Tenaga
Tukang Kayu Oh 1.000 47,500.00 47,500.00
Tukang Batu Oh 0.018 42,500.00 765.00
Tukang Cat Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.100 36,000.00 75,600.00
Mandor Oh 1.005 40,000.00 40,200.00
Sub Total 392,960.00
6.5 E. Membuat direksi keet & Gudang Sementara (m)
SNI 03-2835-
Bahan
2002
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Kayu 5/7 M 0.180 1,700,000.00 306,000.00
Paku Biasa 2"-5" Kg 0.850 10,000.00 8,500.00
Besi Strip Kg 1.100 11,000.00 12,100.00
Semen Portland Kg 35.000 1,050.00 36,750.00

Iswati Septya (3336130275) 13


RAB DAN RAP PROYEK GEDUNG
Pasir Pasang M 0.150 125,000.00 18,750.00
Pasir Beton M 0.100 125,000.00 12,500.00
Koral Beton M 0.150 135,000.00 20,250.00
Bata Merah Bh 30.000 500.00 15,000.00
Seng Plat Lbr 0.250 27,000.00 6,750.00
Jendela Nako Bh 2.0000 12,500.00 25,000.00
Kaca Polos 3 mm M 0.080 50,000.00 4,000.00
Kunci Tanam Bh 0.150 25,000.00 3,750.00
Plywood 4 mm Lbr 0.060 50,000.00 3,000.00
Tenaga
Tukang Kayu Oh 2.000 47,500.00 95,000.00
Tukang Batu Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.000 36,000.00 72,000.00
Kepala Tukang Oh 0.800 45,000.00 36,000.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 751,100.00

II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-
Tenaga
2002
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
6.9 B. Urugan Kembali (m)
SNI 03-2835-
Tenaga
2002
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00
6.11 C. Urugan Pasir Bawah Pondasi (m)
SNI 03-2835-
Bahan
2002
Pasir Urug M 1.200 100,000.00 120,000.00
Tenaga

Iswati Septya (3336130275) 14


RAB DAN RAP PROYEK GEDUNG
Pekerja Oh 0.300 36,000.00 10,800.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 131,200.00

III PEKERJAAN PONDASI


6.6 D. Pasangan Pondasi Batu Kali 1 Pc: 5 Ps (m)
SNI 03-2835-
Bahan
2002
Batu Belah 15/20 cm M 1.100 85,000.00 93,500.00
Semen Portland Kg 136.000 1,050.00 142,800.00
Pasir Pasang M 0.544 125,000.00 68,000.00
Tenaga
Pekerja Oh 1.500 36,000.00 54,000.00
Tukang Batu Oh 0.600 42,500.00 25,500.00
Kepala Tukang Oh 0.060 45,000.00 2,700.00
Mandor Oh 0.075 40,000.00 3,000.00
Sub Total 389,500.00

Tabel Rencana Anggaran Biaya

Harga Jumlah Total Harga


No Jenis Pekerjaan Satuan Volume
Satuan (Rp) Harga (Rp) (Rp)

A PEKERJAAN PERSIAPAN 42,188,844.26


1 Pembersihan Lahan m 308.120 5,600.00 1,725,472.00
2 Pemasangan Pagar Sementara dari Kayu tinggi 2 m m 72.740 188,715.00 13,727,129.10
3 Memasang Bouwplank m 38.000 54,391.66 2,066,883.16
4 Memasang Papan Nama Proyek 80x120 cm Bh 1.000 392,960.00 392,960.00
5 Membuat direksi keet & Gudang Sementara m 24.000 751,100.00 18,026,400.00
6 Listrik dan Air Kerja Ls 1.000 2,000,000.00 2,000,000.00
7 Mob & Demob Alat Ls 1.000 2,000,000.00 2,000,000.00
8 Tes Material Baja dan Beton Ls 1.000 1,500,000.00 1,500,000.00
9 Rambu - rambu lalu lintas dan keselamatan Kerja Ls 1.000 750,000.00 750,000.00

Iswati Septya (3336130275) 15


RAB DAN RAP PROYEK GEDUNG

B PEKERJAAN TANAH 1,383,800.98


1 Galian Tanah Biasa sedalam 1 m m 52.788 16,000.00 844,608.00
2 Urugan Kembali m 13.197 7,672.00 101,247.38
3 Urugan Pasir Bawah Pondasi m 3.338 131,200.00 437,945.60

C PEKERJAAN PONDASI 11,049,725.50


1 Pasangan Pondasi Batu Kali 1 Pc: 5 Ps m 28.369 389,500.00 11,049,725.50

Tabel Rekapitulasi RAB

No Jenis Pekerjaan Harga (Rp)


I PEKERJAAN PERSIAPAN Rp 42,188,844.26
II PEKERJAAN TANAH Rp 1,383,800.98
III PEKERJAAN PONDASI Rp 11,049,725.50
JUMLAH Rp 54,622,370.74
PPN 10% Rp 5,462,237.07
TOTAL JUMLAH Rp 60,084,607.81

Iswati Septya (3336130275) 16


RAB DAN RAP PROYEK GEDUNG
Grafik Kurva S RAB PONDASI

Iswati Septya (3336130275) 17


RAB DAN RAP PROYEK GEDUNG
RAP Pondasi

Tabel Analisa Harga Satuan

Harga Satuan (Rp) Total


Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah (Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
Overhead 560.00
Jumlah tenaga - Over Head 5,040.00
B. Pemasangan Pagar Sementara dari Kayu tinggi 2 m
6.1
(m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
Overhead 18,871.50
Jumlah tenaga - Over Head 169,843.50
6.4 C. Memasang Bouwplank (m)

Iswati Septya (3336130275) 18


RAB DAN RAP PROYEK GEDUNG
SNI 03-2835-2002 Bahan
Kayu 5/7 M 0.012 1,700,000.00 20,400.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Kayu Papan Bengkirai 3/20 M 0.007 3,541,666.00 24,791.66
Tenaga
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Pekerja Oh 0.100 36,000.00 3,600.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.005 40,000.00 200.00
Sub Total 54,391.66
Overhead 5,439.17
Jumlah tenaga - Over Head 48,952.50
ALS D. Memasang Papan Nama Proyek 80x120 cm (Bh)
Bahan
Kayu Meranti Btg 0.035 1,687,000.00 59,045.00
Paku Biasa 2"-5" Kg 0.600 10,000.00 6,000.00
Seng Lembaran 90 cm M 1.400 27,000.00 37,800.00
Cat kayu Kg 1.500 38,000.00 57,000.00
Semen Portland Kg 16.800 1,050.00 17,640.00
Pasir Beton M 0.027 125,000.00 3,375.00
Koral Beton M 0.041 135,000.00 5,535.00
Tenaga
Tukang Kayu Oh 1.000 47,500.00 47,500.00
Tukang Batu Oh 0.018 42,500.00 765.00
Tukang Cat Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.100 36,000.00 75,600.00
Mandor Oh 1.005 40,000.00 40,200.00
Sub Total 392,960.00
Overhead 39,296.00
Jumlah tenaga - Over Head 353,664.00
6.5 E. Membuat direksi keet & Gudang Sementara (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Kayu 5/7 M 0.180 1,700,000.00 306,000.00
Paku Biasa 2"-5" Kg 0.850 10,000.00 8,500.00

Iswati Septya (3336130275) 19


RAB DAN RAP PROYEK GEDUNG
Besi Strip Kg 1.100 11,000.00 12,100.00
Semen Portland Kg 35.000 1,050.00 36,750.00
Pasir Pasang M 0.150 125,000.00 18,750.00
Pasir Beton M 0.100 125,000.00 12,500.00
Koral Beton M 0.150 135,000.00 20,250.00
Bata Merah Bh 30.000 500.00 15,000.00
Seng Plat Lbr 0.250 27,000.00 6,750.00
Jendela Nako Bh 2.0000 12,500.00 25,000.00
Kaca Polos 3 mm M 0.080 50,000.00 4,000.00
Kunci Tanam Bh 0.150 25,000.00 3,750.00
Plywood 4 mm Lbr 0.060 50,000.00 3,000.00
Tenaga
Tukang Kayu Oh 2.000 47,500.00 95,000.00
Tukang Batu Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.000 36,000.00 72,000.00
Kepala Tukang Oh 0.800 45,000.00 36,000.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 751,100.00
Overhead 75,110.00
Jumlah tenaga - Over Head 675,990.00

II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
Overhead 1,600.00
Jumlah tenaga - Over Head 14,400.00

6.9 B. Urugan Kembali (m)


SNI 03-2835-2002 Tenaga
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00

Iswati Septya (3336130275) 20


RAB DAN RAP PROYEK GEDUNG
Overhead 767.20
Jumlah tenaga - Over Head 6,904.80
6.11 C. Urugan Pasir Bawah Pondasi (m)
SNI 03-2835-2002 Bahan
Pasir Urug M 1.200 100,000.00 120,000.00
Tenaga
Pekerja Oh 0.300 36,000.00 10,800.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 131,200.00
Overhead 13,120.00
Jumlah tenaga - Over Head 118,080.00

III PEKERJAAN PONDASI


6.6 D. Pasangan Pondasi Batu Kali 1 Pc: 5 Ps (m)
SNI 03-2835-2002 Bahan
Batu Belah 15/20 cm M 1.100 85,000.00 93,500.00
Semen Portland Kg 136.000 1,050.00 142,800.00
Pasir Pasang M 0.544 125,000.00 68,000.00
Tenaga
Pekerja Oh 1.500 36,000.00 54,000.00
Tukang Batu Oh 0.600 42,500.00 25,500.00
Kepala Tukang Oh 0.060 45,000.00 2,700.00
Mandor Oh 0.075 40,000.00 3,000.00
Sub Total 389,500.00
Overhead 38,950.00
Jumlah tenaga - Over Head 350,550.00

Iswati Septya (3336130275) 21


RAB DAN RAP PROYEK GEDUNG
Tabel Rencana Anggaran Pelaksanaan

Harga Jumlah Total Harga


No Jenis Pekerjaan Satuan Volume
Satuan (Rp) Harga (Rp) (Rp)

A PEKERJAAN PERSIAPAN 38,594,959.83


1 Pembersihan Lahan m 308.120 5,040.00 1,552,924.80
2 Pemasangan Pagar Sementara dari Kayu tinggi 2 m m 72.740 169,843.50 12,354,416.19
3 Memasang Bouwplank m 38.000 48,952.50 1,860,194.84
4 Memasang Papan Nama Proyek 80x120 cm Bh 1.000 353,664.00 353,664.00
5 Membuat direksi keet & Gudang Sementara m 24.000 675,990.00 16,223,760.00
6 Listrik dan Air Kerja Ls 1.000 2,000,000.00 2,000,000.00
7 Mob & Demob Alat Ls 1.000 2,000,000.00 2,000,000.00
8 Tes Material Baja dan Beton Ls 1.000 1,500,000.00 1,500,000.00
9 Rambu - rambu lalu lintas dan keselamatan Kerja Ls 1.000 750,000.00 750,000.00

B PEKERJAAN TANAH 1,245,420.89


1 Galian Tanah Biasa sedalam 1 m m 52.788 14,400.00 760,147.20
2 Urugan Kembali m 13.197 6,904.80 91,122.65
3 Urugan Pasir Bawah Pondasi m 3.338 118,080.00 394,151.04

C PEKERJAAN PONDASI 9,944,752.95


1 Pasangan Pondasi Batu Kali 1 Pc: 5 Ps m 28.369 350,550.00 9,944,752.95

Iswati Septya (3336130275) 22


RAB DAN RAP PROYEK GEDUNG
Tabel Rekapitulasi RAP

No Jenis Pekerjaan Harga (Rp)


I PEKERJAAN PERSIAPAN Rp 38,594,959.83
II PEKERJAAN TANAH Rp 1,245,420.89
III PEKERJAAN PONDASI Rp 9,944,752.95
TOTAL JUMLAH Rp 49,785,133.67
PPN 10% Rp 4,978,513.37
dibulatkan Rp 54,763,647.03

Grafik Kurva RAP PONDASI

Iswati Septya (3336130275) 23


RAB DAN RAP PROYEK GEDUNG
3. PEKERJAAN TURAP BETON
RAB Turap Beton

Tabel Analisa Harga Satuan

Harga Satuan (Rp)


Total Harga
No Jenis Pekerjaan Sat Indeks
Satuan (Rp)
Bahan Upah
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
B. Pemasangan Pagar Sementara dari Kayu tinggi 2
6.1
m (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
6.4 C. Memasang Bouwplank (m)
SNI 03-2835-2002 Bahan
Kayu 5/7 M 0.012 1,700,000.00 20,400.00

Iswati Septya (3336130275) 24


RAB DAN RAP PROYEK GEDUNG
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Kayu Papan Bengkirai 3/20 M 0.007 3,541,666.00 24,791.66
Tenaga
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Pekerja Oh 0.100 36,000.00 3,600.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.005 40,000.00 200.00
Sub Total 54,391.66
ALS D. Memasang Papan Nama Proyek 80x120 cm (Bh)
Bahan
Kayu Meranti Btg 0.035 1,687,000.00 59,045.00
Paku Biasa 2"-5" Kg 0.600 10,000.00 6,000.00
Seng Lembaran 90 cm M 1.400 27,000.00 37,800.00
Cat kayu Kg 1.500 38,000.00 57,000.00
Semen Portland Kg 16.800 1,050.00 17,640.00
Pasir Beton M 0.027 125,000.00 3,375.00
Koral Beton M 0.041 135,000.00 5,535.00
Tenaga
Tukang Kayu Oh 1.000 47,500.00 47,500.00
Tukang Batu Oh 0.018 42,500.00 765.00
Tukang Cat Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.100 36,000.00 75,600.00
Mandor Oh 1.005 40,000.00 40,200.00
Sub Total 392,960.00
6.5 E. Membuat direksi keet & Gudang Sementara (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Kayu 5/7 M 0.180 1,700,000.00 306,000.00
Paku Biasa 2"-5" Kg 0.850 10,000.00 8,500.00
Besi Strip Kg 1.100 11,000.00 12,100.00
Semen Portland Kg 35.000 1,050.00 36,750.00
Pasir Pasang M 0.150 125,000.00 18,750.00
Pasir Beton M 0.100 125,000.00 12,500.00
Koral Beton M 0.150 135,000.00 20,250.00
Bata Merah Bh 30.000 500.00 15,000.00

Iswati Septya (3336130275) 25


RAB DAN RAP PROYEK GEDUNG
Seng Plat Lbr 0.250 27,000.00 6,750.00
Jendela Nako Bh 2.0000 12,500.00 25,000.00
Kaca Polos 3 mm M 0.080 50,000.00 4,000.00
Kunci Tanam Bh 0.150 25,000.00 3,750.00
Plywood 4 mm Lbr 0.060 50,000.00 3,000.00
Tenaga
Tukang Kayu Oh 2.000 47,500.00 95,000.00
Tukang Batu Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.000 36,000.00 72,000.00
Kepala Tukang Oh 0.800 45,000.00 36,000.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 751,100.00

II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
6.9 B. Urugan Kembali (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00
6.11 C. Urugan Pasir Bawah Pondasi (m)
SNI 03-2835-2002 Bahan
Pasir Urug M 1.200 100,000.00 120,000.00
Tenaga
Pekerja Oh 0.300 36,000.00 10,800.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 131,200.00

III PEKERJAAN PONDASI


6.6 A. Pasangan Pondasi Batu Kali 1 Pc: 5 Ps (m)
SNI 03-2835-2002 Bahan

Iswati Septya (3336130275) 26


RAB DAN RAP PROYEK GEDUNG
Batu Belah 15/20 cm M 1.100 85,000.00 93,500.00
Semen Portland Kg 136.000 1,050.00 142,800.00
Pasir Pasang M 0.544 125,000.00 68,000.00
Tenaga
Pekerja Oh 1.500 36,000.00 54,000.00
Tukang Batu Oh 0.600 42,500.00 25,500.00
Kepala Tukang Oh 0.060 45,000.00 2,700.00
Mandor Oh 0.075 40,000.00 3,000.00
Sub Total 389,500.00

IV PEKERJAAN BETON
A. Membuat sloof Beton Bertulang (200Kg
6.39
besi+bekisting) (m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.270 2,000,000.00 540,000.00
Paku Biasa 2"-5" Kg 2.000 10,000.00 20,000.00
Minyak Bekisting Lt 0.600 10,000.00 6,000.00
Besi Beton polos Kg 200.000 12,000.00 2,400,000.00
Kawat Beton Kg 3.000 13,000.00 39,000.00
Semen Portland Kg 323.000 1,050.00 339,150.00
Pasir Beton M 0.520 125,000.00 65,000.00
Koral Beton M 0.780 135,000.00 105,300.00
Tenaga
Pekerja Oh 4.850 36,000.00 174,600.00
Tukang Batu Oh 0.350 42,500.00 14,875.00
Tukang Kayu Oh 1.560 47,500.00 74,100.00
Tukang Besi Oh 1.400 45,000.00 63,000.00
Kepala Tukang Oh 0.331 45,000.00 14,895.00
Mandor Oh 0.170 40,000.00 6,800.00
Sub Total 3,862,720.00
B. Membuat Kolom Beton Bertulang (300Kg
6.40
besi+bekisting) (m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.400 2,000,000.00 800,000.00

Iswati Septya (3336130275) 27


RAB DAN RAP PROYEK GEDUNG
Paku Biasa 2"-5" Kg 4.000 10,000.00 40,000.00
Minyak Bekisting Lt 2.000 10,000.00 20,000.00
Besi Beton polos Kg 300.000 12,000.00 3,600,000.00
Kawat Beton Kg 4.500 13,000.00 58,500.00
Semen Portland Kg 323.000 1,050.00 339,150.00
Pasir Beton M 0.520 125,000.00 65,000.00
Koral Beton M 0.780 135,000.00 105,300.00
Kayu Borneo Balok M 0.150 8,500,000.00 1,275,000.00
Plywood 9 mm Lbr 3.500 95,000.00 332,500.00
Dolken Kayu 8-10/400 cm Btg 20.000 25,000.00 500,000.00
Tenaga
Pekerja Oh 7.300 36,000.00 262,800.00
Tukang Batu Oh 0.350 42,500.00 14,875.00
Tukang Kayu Oh 3.300 47,500.00 156,750.00
Tukang Besi Oh 2.100 45,000.00 94,500.00
Kepala Tukang Oh 0.570 45,000.00 25,650.00
Mandor Oh 0.250 40,000.00 10,000.00
Sub Total 7,700,025.00
C. Membuat Ring Balok Beton Bertulang (10X15cm)
6.46
(m)
SNI 03-2835-2002 Bahan
Kayu Albasiah M 0.003 3,000,000.00 9,000.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Besi Beton polos Kg 3.600 13,000.00 46,800.00
Kawat Beton Kg 0.050 13,000.00 650.00
Semen Portland Kg 5.500 1,050.00 5,775.00
Pasir Beton M 0.009 125,000.00 1,125.00
Koral Beton M 0.015 135,000.00 2,025.00
Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Tukang Batu Oh 0.033 42,500.00 1,402.50
Tukang Kayu Oh 0.033 47,500.00 1,567.50
Tukang Besi Oh 0.033 45,000.00 1,485.00
Kepala Tukang Oh 0.010 45,000.00 450.00

Iswati Septya (3336130275) 28


RAB DAN RAP PROYEK GEDUNG
Mandor Oh 0.005 40,000.00 200.00
Sub Total 74,280.00
6.5 D. Membuat Plat Beton 1Pc:2Ps:3Kr (m)
SNI 03-2835-2002 Bahan
Semen Portland Kg 232.000 1,050.00 243,600.00
Pasir Beton M 0.520 125,000.00 65,000.00
Koral Beton M 0.780 135,000.00 105,300.00
Tenaga
Pekerja Oh 1.650 36,000.00 59,400.00
Tukang Batu Oh 0.250 42,500.00 10,625.00
Kepala Tukang Oh 0.025 45,000.00 1,125.00
Mandor Oh 0.080 40,000.00 3,200.00
Sub Total 488,250.00
6.25 E. Pembesian Besi Polos dan Ulir plat beton(Kg)
SNI 03-2835-2002 Bahan
Besi Beton (Polos/Ulir) Kg 1.050 12,000.00 12,600.00
Kawat Beton Kg 0.015 13,000.00 195.00
Tenaga
Pekerja Oh 0.007 36,000.00 252.00
Tukang Besi Oh 0.007 45,000.00 315.00
Kepala Tukang Oh 0.001 45,000.00 31.50
Mandor Oh 0.000 40,000.00 12.00
Sub Total 13,405.50
6.32 F. Pasang Bekisting untuk Plat Beton (m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.040 2,000,000.00 80,000.00
Paku Biasa 2"-5" Kg 0.400 10,000.00 4,000.00
Minyak Bekisting Lt 0.200 10,000.00 2,000.00
Balok Kayu borneo M 0.015 8,500,000.00 127,500.00
Plywood tebal 9 mm Lbr 0.350 95,000.00 33,250.00
Dolken Kayu galam 8-10/4 m Btg 6.000 25,000.00 150,000.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang kayu Oh 0.330 47,500.00 15,675.00

Iswati Septya (3336130275) 29


RAB DAN RAP PROYEK GEDUNG
Kepala Tukang Oh 0.033 45,000.00 1,485.00
Mandor Oh 0.006 40,000.00 240.00
Sub Total 425,670.00

V PEKERJAAN DINDING
A. Pasangan Tembok Bata 1Pc:4Ps (Trasraam)
6.11
(m)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 11.500 1,050.00 12,075.00
Pasir Pasang M 0.043 125,000.00 5,375.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 69,270.00
6.15 B. Pasangan Tembok Bata 1Pc:3Kp:10Ps (m)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 4.500 1,050.00 4,725.00
Pasir Pasang M 0.050 125,000.00 6,250.00
Kapur Padam M 0.015 45,000.00 675.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 63,470.00

VI PEKERJAAN PLESTERAN DINDING


6.14 A. Plesteran Dinding 1Pc:3Ps (m) tebal 20 mm
SNI 03-2835-2002 Bahan
Semen Portland Kg 10.800 1,050.00 11,340.00

Iswati Septya (3336130275) 30


RAB DAN RAP PROYEK GEDUNG
Pasir Pasang M 0.026 125,000.00 3,250.00
Tenaga
Pekerja Oh 0.250 36,000.00 9,000.00
Tukang Batu Oh 0.200 42,500.00 8,500.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.013 40,000.00 500.00
Sub Total 33,490.00
6.9 B. Plesteran Dinding 1Pc:3Kp:10Ps (m) tebal 15 mm
SNI 03-2835-2002 Bahan
Semen Portland Kg 1.840 1,050.00 1,932.00
Kapur Padam M 0.006 45,000.00 270.00
Pasir Pasang M 0.014 125,000.00 1,750.00
Tenaga
Pekerja Oh 0.200 36,000.00 7,200.00
Tukang Batu Oh 0.150 42,500.00 6,375.00
Kepala Tukang Oh 0.015 45,000.00 675.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 18,602.00

Tabel Rencana Anggaran Biaya

Harga Jumlah Total Harga


No Jenis Pekerjaan Satuan Volume
Satuan (Rp) Harga (Rp) (Rp)

A PEKERJAAN PERSIAPAN 42,188,844.26


1 Pembersihan Lahan m 308.120 5,600.00 1,725,472.00
2 Pemasangan Pagar Sementara dari Kayu tinggi 2 m m 72.740 188,715.00 13,727,129.10
3 Memasang Bouwplank m 38.000 54,391.66 2,066,883.16
4 Memasang Papan Nama Proyek 80x120 cm Bh 1.000 392,960.00 392,960.00
5 Membuat direksi keet & Gudang Sementara m 24.000 751,100.00 18,026,400.00
6 Listrik dan Air Kerja Ls 1.000 2,000,000.00 2,000,000.00
7 Mob & Demob Alat Ls 1.000 2,000,000.00 2,000,000.00

Iswati Septya (3336130275) 31


RAB DAN RAP PROYEK GEDUNG
8 Tes Material Baja dan Beton Ls 1.000 1,500,000.00 1,500,000.00
9 Rambu - rambu lalu lintas dan keselamatan Kerja Ls 1.000 750,000.00 750,000.00

B PEKERJAAN TANAH 1,383,800.98


1 Galian Tanah Biasa sedalam 1 m m 52.788 16,000.00 844,608.00
2 Urugan Kembali m 13.197 7,672.00 101,247.38
3 Urugan Pasir Bawah Pondasi m 3.338 131,200.00 437,945.60

C PEKERJAAN PONDASI 11,049,725.50


1 Pasangan Pondasi Batu Kali 1 Pc: 5 Ps m 28.369 389,500.00 11,049,725.50

D PEKERJAAN BETON 12,564,350.50


1 Membuat sloof beton bertulang (200kg besi+bekisting) m 308.120 200.00 3,862,720.00
2 Membuat kolom beton bertulang (300 kg besi+bekisting) m 72.740 3,375.00 7,700,025.00
3 Membuat ring balok beton bertulang (10x15 cm) (m) m 38.000 31,250.00 74,280.00
4 Membuat Plat Beton 1Pc:2Ps:3Kr (m) Bh 1.000 42,500.00 488,250.00
5 Pembesian Besi Polos dan Ulir plat beton(Kg) m 24.000 131,200.00 13,405.50
6 Pasang Bekisting untuk Plat Beton (m) Ls 1.000 425,670.00 425,670.00

E PEKERJAAN DINDING 25,960,280.20


1 Pasangan Tembok Bata 1Pc:4Ps (Trasraam) (m) m 308.120 69,270.00 21,343,472.40
2 Pasangan Tembok Bata 1Pc:3Kp:10Ps (m) m 72.740 63,470.00 4,616,807.80

F PEKERJAAN PLESTERAN DINDING 11,672,048.28


1 Plesteran Dinding 1Pc:3Ps (m) tebal 20 mm m 308.120 33,490.00 10,318,938.80
2 Plesteran Dinding 1Pc:3Kp:10Ps (m) tebal 15 mm m 72.740 18,602.00 1,353,109.48

Iswati Septya (3336130275) 32


RAB DAN RAP PROYEK GEDUNG
Tabel Rekapitulasi RAB

No Jenis Pekerjaan Harga (Rp)


I PEKERJAAN PERSIAPAN Rp 42,188,844.26
II PEKERJAAN TANAH Rp 1,383,800.98
V PEKERJAAN PONDASI Rp 11,049,725.50
IV PEKERJAAN BETON Rp 12,564,350.50
V PEKERJAAN DINDING Rp 25,960,280.20
VI PEKERJAAN PLESTERAN DINDING Rp 11,672,048.28
JUMLAH Rp 93,147,001.44
PPN 10% Rp 9,314,700.14
TOTAL JUMLAH Rp 102,461,701.58

RAP Turap Beton

Tabel Analisa Harga Satuan

Total
Harga Satuan (Rp)
Harga
No Jenis Pekerjaan Sat Indeks
Satuan
Bahan Upah
(Rp)
I PEKERJAAN PERSIAPAN
6.8 A. Pembersihan Lahan (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 5,600.00
Overhead 560.00
Jumlah tenaga - Over Head 5,040.00
6.1 B. Pemasangan Pagar Sementara dari Kayu tinggi 2 m (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Semen Portland Kg 2.500 1,050.00 2,625.00

Iswati Septya (3336130275) 33


RAB DAN RAP PROYEK GEDUNG
Pasir Beton M 0.005 125,000.00 625.00
Koral Beton M 0.009 135,000.00 1,215.00
Kayu 5/7 M 0.072 1,700,000.00 122,400.00
Paku Biasa 2"-5" Kg 0.060 10,000.00 600.00
Residu Lt 0.400 11,000.00 4,400.00
Tenaga
Tukang Kayu Oh 0.200 47,500.00 9,500.00
Pekerja Oh 0.400 36,000.00 14,400.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.020 40,000.00 800.00
Sub Total 188,715.00
Overhead 18,871.50
Jumlah tenaga - Over Head 169,843.50
6.4 C. Memasang Bouwplank (m)
SNI 03-2835-2002 Bahan
Kayu 5/7 M 0.012 1,700,000.00 20,400.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Kayu Papan Bengkirai 3/20 M 0.007 3,541,666.00 24,791.66
Tenaga
Tukang Kayu Oh 0.100 47,500.00 4,750.00
Pekerja Oh 0.100 36,000.00 3,600.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.005 40,000.00 200.00
Sub Total 54,391.66
Overhead 5,439.17
Jumlah tenaga - Over Head 48,952.50
ALS D. Memasang Papan Nama Proyek 80x120 cm (Bh)
Bahan
Kayu Meranti Btg 0.035 1,687,000.00 59,045.00
Paku Biasa 2"-5" Kg 0.600 10,000.00 6,000.00
Seng Lembaran 90 cm M 1.400 27,000.00 37,800.00
Cat kayu Kg 1.500 38,000.00 57,000.00
Semen Portland Kg 16.800 1,050.00 17,640.00
Pasir Beton M 0.027 125,000.00 3,375.00

Iswati Septya (3336130275) 34


RAB DAN RAP PROYEK GEDUNG
Koral Beton M 0.041 135,000.00 5,535.00
Tenaga
Tukang Kayu Oh 1.000 47,500.00 47,500.00
Tukang Batu Oh 0.018 42,500.00 765.00
Tukang Cat Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.100 36,000.00 75,600.00
Mandor Oh 1.005 40,000.00 40,200.00
Sub Total 392,960.00
Overhead 39,296.00
Jumlah tenaga - Over Head 353,664.00
6.5 E. Membuat direksi keet & Gudang Sementara (m)
SNI 03-2835-2002 Bahan
Dolken Kayu 8-10/400 cm Btg 1.250 25,000.00 31,250.00
Kayu 5/7 M 0.180 1,700,000.00 306,000.00
Paku Biasa 2"-5" Kg 0.850 10,000.00 8,500.00
Besi Strip Kg 1.100 11,000.00 12,100.00
Semen Portland Kg 35.000 1,050.00 36,750.00
Pasir Pasang M 0.150 125,000.00 18,750.00
Pasir Beton M 0.100 125,000.00 12,500.00
Koral Beton M 0.150 135,000.00 20,250.00
Bata Merah Bh 30.000 500.00 15,000.00
Seng Plat Lbr 0.250 27,000.00 6,750.00
Jendela Nako Bh 2.0000 12,500.00 25,000.00
Kaca Polos 3 mm M 0.080 50,000.00 4,000.00
Kunci Tanam Bh 0.150 25,000.00 3,750.00
Plywood 4 mm Lbr 0.060 50,000.00 3,000.00
Tenaga
Tukang Kayu Oh 2.000 47,500.00 95,000.00
Tukang Batu Oh 1.000 42,500.00 42,500.00
Pekerja Oh 2.000 36,000.00 72,000.00
Kepala Tukang Oh 0.800 45,000.00 36,000.00
Mandor Oh 0.050 40,000.00 2,000.00
Sub Total 751,100.00
Overhead 75,110.00
Jumlah tenaga - Over Head 675,990.00

Iswati Septya (3336130275) 35


RAB DAN RAP PROYEK GEDUNG
II PEKERJAAN TANAH
6.1 A. Galian Tanah Biasa sedalam 1 m (m)
SNI 03-2835-2002 Tenaga
Pekerja Oh 0.400 36,000.00 14,400.00
Mandor Oh 0.040 40,000.00 1,600.00
Sub Total 16,000.00
Overhead 1,600.00
Jumlah tenaga - Over Head 14,400.00

6.9 B. Urugan Kembali (m)


SNI 03-2835-2002 Tenaga
Pekerja Oh 0.192 36,000.00 6,912.00
Mandor Oh 0.019 40,000.00 760.00
Sub Total 7,672.00
Overhead 767.20
Jumlah tenaga - Over Head 6,904.80
6.11 C. Urugan Pasir Bawah Pondasi (m)
SNI 03-2835-2002 Bahan
Pasir Urug M 1.200 100,000.00 120,000.00
Tenaga
Pekerja Oh 0.300 36,000.00 10,800.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 131,200.00
Overhead 13,120.00
Jumlah tenaga - Over Head 118,080.00

III PEKERJAAN PONDASI


6.6 D. Pasangan Pondasi Batu Kali 1 Pc: 5 Ps (m)
SNI 03-2835-2002 Bahan
Batu Belah 15/20 cm M 1.100 85,000.00 93,500.00
Semen Portland Kg 136.000 1,050.00 142,800.00
Pasir Pasang M 0.544 125,000.00 68,000.00
Tenaga
Pekerja Oh 1.500 36,000.00 54,000.00

Iswati Septya (3336130275) 36


RAB DAN RAP PROYEK GEDUNG
Tukang Batu Oh 0.600 42,500.00 25,500.00
Kepala Tukang Oh 0.060 45,000.00 2,700.00
Mandor Oh 0.075 40,000.00 3,000.00
Sub Total 389,500.00
Overhead 38,950.00
Jumlah tenaga - Over Head 350,550.00

IV PEKERJAAN BETON
A. Membuat sloof Beton Bertulang (200Kg besi+bekisting)
6.39
(m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.270 2,000,000.00 540,000.00
Paku Biasa 2"-5" Kg 2.000 10,000.00 20,000.00
Minyak Bekisting Lt 0.600 10,000.00 6,000.00
Besi Beton polos Kg 200.000 12,000.00 2,400,000.00
Kawat Beton Kg 3.000 13,000.00 39,000.00
Semen Portland Kg 323.000 1,050.00 339,150.00
Pasir Beton M 0.520 125,000.00 65,000.00
Koral Beton M 0.780 135,000.00 105,300.00
Tenaga
Pekerja Oh 4.850 36,000.00 174,600.00
Tukang Batu Oh 0.350 42,500.00 14,875.00
Tukang Kayu Oh 1.560 47,500.00 74,100.00
Tukang Besi Oh 1.400 45,000.00 63,000.00
Kepala Tukang Oh 0.331 45,000.00 14,895.00
Mandor Oh 0.170 40,000.00 6,800.00
Sub Total 3,862,720.00
Overhead 386,272.00
Jumlah tenaga - Over Head 3,476,448.00
B. Membuat Kolom Beton Bertulang (300Kg besi+bekisting)
6.40
(m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.400 2,000,000.00 800,000.00
Paku Biasa 2"-5" Kg 4.000 10,000.00 40,000.00

Iswati Septya (3336130275) 37


RAB DAN RAP PROYEK GEDUNG
Minyak Bekisting Lt 2.000 10,000.00 20,000.00
Besi Beton polos Kg 300.000 12,000.00 3,600,000.00
Kawat Beton Kg 4.500 13,000.00 58,500.00
Semen Portland Kg 323.000 1,050.00 339,150.00
Pasir Beton M 0.520 125,000.00 65,000.00
Koral Beton M 0.780 135,000.00 105,300.00
Kayu Borneo Balok M 0.150 8,500,000.00 1,275,000.00
Plywood 9 mm Lbr 3.500 95,000.00 332,500.00
Dolken Kayu 8-10/400 cm Btg 20.000 25,000.00 500,000.00
Tenaga
Pekerja Oh 7.300 36,000.00 262,800.00
Tukang Batu Oh 0.350 42,500.00 14,875.00
Tukang Kayu Oh 3.300 47,500.00 156,750.00
Tukang Besi Oh 2.100 45,000.00 94,500.00
Kepala Tukang Oh 0.570 45,000.00 25,650.00
Mandor Oh 0.250 40,000.00 10,000.00
Sub Total 7,700,025.00
Overhead 770,002.50
Jumlah tenaga - Over Head 6,930,022.50
6.46 C. Membuat Ring Balok Beton Bertulang (10X15cm) (m)
SNI 03-2835-2002 Bahan
Kayu Albasiah M 0.003 3,000,000.00 9,000.00
Paku Biasa 2"-5" Kg 0.020 10,000.00 200.00
Besi Beton polos Kg 3.600 13,000.00 46,800.00
Kawat Beton Kg 0.050 13,000.00 650.00
Semen Portland Kg 5.500 1,050.00 5,775.00
Pasir Beton M 0.009 125,000.00 1,125.00
Koral Beton M 0.015 135,000.00 2,025.00
Tenaga
Pekerja Oh 0.100 36,000.00 3,600.00
Tukang Batu Oh 0.033 42,500.00 1,402.50
Tukang Kayu Oh 0.033 47,500.00 1,567.50
Tukang Besi Oh 0.033 45,000.00 1,485.00
Kepala Tukang Oh 0.010 45,000.00 450.00

Iswati Septya (3336130275) 38


RAB DAN RAP PROYEK GEDUNG
Mandor Oh 0.005 40,000.00 200.00
Sub Total 74,280.00
Overhead 7,428.00
Jumlah tenaga - Over Head 66,852.00
6.5 D. Membuat Plat Beton 1Pc:2Ps:3Kr (m)
SNI 03-2835-2002 Bahan
Semen Portland Kg 232.000 1,050.00 243,600.00
Pasir Beton M 0.520 125,000.00 65,000.00
Koral Beton M 0.780 135,000.00 105,300.00
Tenaga
Pekerja Oh 1.650 36,000.00 59,400.00
Tukang Batu Oh 0.250 42,500.00 10,625.00
Kepala Tukang Oh 0.025 45,000.00 1,125.00
Mandor Oh 0.080 40,000.00 3,200.00
Sub Total 488,250.00
Overhead 48,825.00
Jumlah tenaga - Over Head 439,425.00
6.25 E. Pembesian Besi Polos dan Ulir plat beton(Kg)
SNI 03-2835-2002 Bahan
Besi Beton (Polos/Ulir) Kg 1.050 12,000.00 12,600.00
Kawat Beton Kg 0.015 13,000.00 195.00
Tenaga
Pekerja Oh 0.007 36,000.00 252.00
Tukang Besi Oh 0.007 45,000.00 315.00
Kepala Tukang Oh 0.001 45,000.00 31.50
Mandor Oh 0.000 40,000.00 12.00
Sub Total 13,405.50
Overhead 1,340.55
Jumlah tenaga - Over Head 12,064.95
6.32 F. Pasang Bekisting untuk Plat Beton (m)
SNI 03-2835-2002 Bahan
Kayu Terentang M 0.040 2,000,000.00 80,000.00
Paku Biasa 2"-5" Kg 0.400 10,000.00 4,000.00
Minyak Bekisting Lt 0.200 10,000.00 2,000.00

Iswati Septya (3336130275) 39


RAB DAN RAP PROYEK GEDUNG
Balok Kayu borneo M 0.015 8,500,000.00 127,500.00
Plywood tebal 9 mm Lbr 0.350 95,000.00 33,250.00
Dolken Kayu galam 8-10/4 m Btg 6.000 25,000.00 150,000.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang kayu Oh 0.330 47,500.00 15,675.00
Kepala Tukang Oh 0.033 45,000.00 1,485.00
Mandor Oh 0.006 40,000.00 240.00
Sub Total 425,670.00
Overhead 42,567.00
Jumlah tenaga - Over Head 383,103.00

V PEKERJAAN DINDING
6.11 A. Pasangan Tembok Bata 1Pc:4Ps (Trasraam) (m)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 11.500 1,050.00 12,075.00
Pasir Pasang M 0.043 125,000.00 5,375.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 69,270.00
Overhead 6,927.00
Jumlah tenaga - Over Head 62,343.00
6.15 B. Pasangan Tembok Bata 1Pc:3Kp:10Ps (m)
SNI 03-2835-2002 Bahan
Bata Merah 5 X 11 X 22 cm Bh 70.000 500.00 35,000.00
Semen Portland Kg 4.500 1,050.00 4,725.00
Pasir Pasang M 0.050 125,000.00 6,250.00
Kapur Padam M 0.015 45,000.00 675.00
Tenaga
Pekerja Oh 0.320 36,000.00 11,520.00

Iswati Septya (3336130275) 40


RAB DAN RAP PROYEK GEDUNG
Tukang Batu Oh 0.100 42,500.00 4,250.00
Kepala Tukang Oh 0.010 45,000.00 450.00
Mandor Oh 0.015 40,000.00 600.00
Sub Total 63,470.00
Overhead 6,347.00
Jumlah tenaga - Over Head 57,123.00

VI PEKERJAAN PLESTERAN DINDING


6.14 A. Plesteran Dinding 1Pc:3Ps (m) tebal 20 mm
SNI 03-2835-2002 Bahan
Semen Portland Kg 10.800 1,050.00 11,340.00
Pasir Pasang M 0.026 125,000.00 3,250.00
Tenaga
Pekerja Oh 0.250 36,000.00 9,000.00
Tukang Batu Oh 0.200 42,500.00 8,500.00
Kepala Tukang Oh 0.020 45,000.00 900.00
Mandor Oh 0.013 40,000.00 500.00
Sub Total 33,490.00
Overhead 3,349.00
Jumlah tenaga - Over Head 30,141.00
6.9 B. Plesteran Dinding 1Pc:3Kp:10Ps (m) tebal 15 mm
SNI 03-2835-2002 Bahan
Semen Portland Kg 1.840 1,050.00 1,932.00
Kapur Padam M 0.006 45,000.00 270.00
Pasir Pasang M 0.014 125,000.00 1,750.00
Tenaga
Pekerja Oh 0.200 36,000.00 7,200.00
Tukang Batu Oh 0.150 42,500.00 6,375.00
Kepala Tukang Oh 0.015 45,000.00 675.00
Mandor Oh 0.010 40,000.00 400.00
Sub Total 18,602.00
Overhead 1,860.20
Jumlah tenaga - Over Head 16,741.80

Iswati Septya (3336130275) 41


RAB DAN RAP PROYEK GEDUNG
Tabel Rencana Anggaran Pelaksanaan

Harga Jumlah Total Harga


No Jenis Pekerjaan Satuan Volume
Satuan (Rp) Harga (Rp) (Rp)

A PEKERJAAN PERSIAPAN 38,594,959.83


1 Pembersihan Lahan m 308.120 5,040.00 1,552,924.80
2 Pemasangan Pagar Sementara dari Kayu tinggi 2 m m 72.740 169,843.50 12,354,416.19
3 Memasang Bouwplank m 38.000 48,952.50 1,860,194.84
4 Memasang Papan Nama Proyek 80x120 cm Bh 1.000 353,664.00 353,664.00
5 Membuat direksi keet & Gudang Sementara m 24.000 675,990.00 16,223,760.00
6 Listrik dan Air Kerja Ls 1.000 2,000,000.00 2,000,000.00
7 Mob & Demob Alat Ls 1.000 2,000,000.00 2,000,000.00
8 Tes Material Baja dan Beton Ls 1.000 1,500,000.00 1,500,000.00
9 Rambu - rambu lalu lintas dan keselamatan Kerja Ls 1.000 750,000.00 750,000.00

B PEKERJAAN TANAH 1,245,420.89


1 Galian Tanah Biasa sedalam 1 m m 52.788 14,400.00 760,147.20
2 Urugan Kembali m 13.197 6,904.80 91,122.65
3 Urugan Pasir Bawah Pondasi m 3.338 118,080.00 394,151.04

C PEKERJAAN PONDASI 9,944,752.95


1 Pasangan Pondasi Batu Kali 1 Pc: 5 Ps m 28.369 350,550.00 9,944,752.95

D PEKERJAAN BETON 12,521,783.50


1 Membuat sloof beton bertulang (200kg besi+bekisting) m 308.120 3,476,448.00 3,862,720.00
2 Membuat kolom beton bertulang (300 kg besi+bekisting) m 72.740 6,930,022.50 7,700,025.00
3 Membuat ring balok beton bertulang (10x15 cm) (m) m 38.000 66,852.00 74,280.00
4 Membuat Plat Beton 1Pc:2Ps:3Kr (m) Bh 1.000 439,425.00 488,250.00
5 Pembesian Besi Polos dan Ulir plat beton(Kg) m 24.000 12,064.95 13,405.50
6 Pasang Bekisting untuk Plat Beton (m) Ls 1.000 383,103.00 383,103.00

E PEKERJAAN DINDING 23,364,252.18

Iswati Septya (3336130275) 42


RAB DAN RAP PROYEK GEDUNG
1 Pasangan Tembok Bata 1Pc:4Ps (Trasraam) (m) m 308.120 62,343.00 19,209,125.16
2 Pasangan Tembok Bata 1Pc:3Kp:10Ps (m) m 72.740 57,123.00 4,155,127.02

F PEKERJAAN PLESTERAN DINDING 10,504,843.45


1 Plesteran Dinding 1Pc:3Ps (m) tebal 20 mm m 308.120 30,141.00 9,287,044.92
2 Plesteran Dinding 1Pc:3Kp:10Ps (m) tebal 15 mm m 72.740 16,741.80 1,217,798.53

Tabel Rekapitulasi RAP

No Jenis Pekerjaan Harga (Rp)


I PEKERJAAN PERSIAPAN Rp 38,594,959.83
II PEKERJAAN TANAH Rp 1,245,420.89
III PEKERJAAN PONDASI Rp 9,944,752.95
IV PEKERJAAN BETON Rp 12,521,783.50
V PEKERJAAN DINDING Rp 23,364,252.18
VI PEKERJAAN PLESTERAN DINDING Rp 10,504,843.45
JUMLAH Rp 96,176,012.80
PPN 10% Rp 9,617,601.28
TOTAL JUMLAH Rp 105,793,614.08

Rekapitulasi RAB dan RAP

No Jenis Pekerjaan RAB RAP


1 Pek. Cut and Fill Rp 47,929,909.76 Rp 43,824,418.79
2 Pek. Pondasi Batu Kali Rp 60,084,607.81 Rp 54,763,647.03
3 Pek.Turap Beton Rp 102,461,701.58 Rp 105,793,614.08

Iswati Septya (3336130275) 43