A. Project :
B. Employer :
C. Contractor :
D. Contract Sum :
E. Date of Valuation :
F. Progress Bill No :
We forward herewith Bill No XX For the work done up to XXX 2015 on the above project, and request an interim certificate be issued
for an amount of Rs Sri Lankan Rupees XXXXXXXXXXXXX
ADD
2.0 80 % of value of material at site SLR
4.0 Variations
4.1 Additions SLR
7.0 LESS
7.1 Foreign component if any SLR
LESS
9.0 Advance recovery on 25% on work done SLR
In Words :
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
..
Contractor