PMP EXAM FORMULAS (PMBOK Guide Fifth Edition)

Beta Distribution (from traditional PERT technique) tE = (tO + 4 tM + tP) / 6 Where: tO (Optimistic) = The activity duration based on
analysis of the best-case scenario for the activity.
Triangular Distribution tE D = (tO + tM + tP) / 3
tM (Most Likely) = This estimate is based on the duration of the
activity, given the resources likely to be assigned, their
productivity, realistic expectations of availability for the activity,
Standard Deviation [ tP tO ] / 6 dependencies on other participants, and interruptions.

tP (Pessimistic) = The activity duration based on analysis of the


Variance = [ tP tO ] / 6 worst-case scenario for the activity.

How to calculate a Task Slack in a Network Diagram


Slack = LS ES Where LS = Task Late Start ES = Task Early Start
Slack = LF EF LF = Task Late Finish, EF = Task Early Finish

Earned Value Formulas


Cost Variance (CV) = EV AC Where EV = Earned Value
Schedule Variance (SV) = EV PV AC = Actual Cost
Cost Performance Index (CPI) = EV / AC PV = Present Value
Schedule Performance Index (SPI) = EV / PV EAC = Estimate at Completion
Estimate to Completion (ETC) = EAC AC BAC = Budget at Completion
Variance at Completion (VAC) = BAC EAC
Estimate at Completion (EAC) = BAC / CPI
To Complete Performance Index (TCPI) = (BAC EV) / (BAC AC)

Present Value (PV) = FV /(1+r ) n Where FV = Future Value


r = Interest Rate
n = number of time periods

2
Communication Channels = N (N - 1) / 2 or (N - N)/2 Where: N = Number of people

Expected Monetary Value (EMV) = P X I Where P = Probability and I = Impact

Point of Total Assumption (PTA) = (Ceiling Price Target Price)


+ Target Cost
Buyers Share Ratio

Prepared by: Javeed Khan