TECHNICAL JUSTIFICATION

1
CHAPTER
INTRODUCTION
1.1. BACKGROUND

The project named Cileunyi Sumedang Dawuan (Cisumdawu) Toll Road Project,
the location of the whole project is in 3 (three) districts, such as Bandung district, Sumedang
district and Majalengka district. The project started from Cileunyi to Dawuan (Majalengka).

Cisumdawu Toll Road Project itself have divided into 6 Sections, namely :
o Section I Sta.-2+245 9+750 (IC Cileunyi IC Ranca Kalong) (L=11,99 Km)
o Section II Sta.9+750 27+100 (IC Ranca Kalong IC Sumedang) (L=17,35 Km)
o Section III Sta.27+100 30+850 (IC Sumedang IC Cimalaka) (L=3,75 Km)
o Section IV Sta.30+850 38+050 (IC Cimalaka IC Legok) (L=7,2 Km)
o Section V Sta.38+050 53+950 (IC Legok IC Ujung Jaya) (L=15,9 Km)
o Section VI Sta.53+950 58+326.987 (IC Ujung Jaya IC Dawuan) (L=4,23 Km)

Cisumdawu Section II divided by 2 stage. Section II stage II, will be executed only for
10,7 Km from the total of 17,35 Km which is (Sta.12+000 Sta.13+.100 and Sta.17+200
Sta.26+800), with the following description :

Length of Main Road : 10,2 Km (Sta. 12+000 Sta. 12+628 & Sta. 17+200 26+800)
Length of Tunnel : 472 m (Sta. 12+628 13+100)
Plan of Speed : 80 Km/hr (Main Road)
Width of Lane : 3,6 meter
Number of Lane : 2 x 2 @ 3,6 m
Width of outter sideroad : 3.00 m
Width if inner sideroad : 1,50 m
Width of Median : 2,50 m (include barrier)
Lane Pavement : Rigid Pavement
Sideroad Pavement : Flexible Pavement
Number of Bridge : 2 Bridge
Number of Interchange : 1 Interchange

Supervisi/Pengawasan Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 1


TECHNICAL JUSTIFICATION

Number of Overpass : 5 Overpass


Number of Underpass : 5 Underpass
Toll Gate : 2 Location
Pedestrian Bridge : 3 Location

1.2. PURPOSE AND BENEFITS

The purpose and benefits of "Construction of Toll Road Cileunyi - Sumedang - Dawuan
(Cisumdawu)" project are :
1. To integrate Bandung city and Cirebon with planning of international airport in Majalengka
and Port in Cirebon as inlet/ outlet of West Java Province.
2. To increase the economic growth in the area around the toll road.
3. To encourage the development of the eastern province of West Java that relatively less
developed than the West.
4. As an alternative way for Cadas Pangeran street

1.3. LEGAL BASIS

1. Perpres No. 54 tahun 2010 tentang Pengadaan Barang/ Jasa


Pemerintah.

2. Kepmen Kimpraswil No.349/KPTS/M/2004, tentang Pedoman


Penyelenggaraan Kontrak Jasa Pelaksanaan Konstruksi (Pemborongan).

3. Permen PU No.07/PRT/M/2011 tentang Standar dan Pedoman


Pengadaan Pekerjaan Konstruksi dan Jasa Konsultasi.

4. Surat Dir. Jen. Bina Marga No. UM.01.03-Db/242, tanggal 26


Maret 2008.

5. Surat Dir. Jen. Bina Marga No. UM.01.03-Db/895, tanggal 30


November 2009.

6. SE Dirjen Bina Marga No.03/SE/Db/2012 tanggal 26 Januari


2012 tentang Tata Cara Perubahan Kontrak Konstruksi

Supervisi/Pengawasan Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 2


TECHNICAL JUSTIFICATION

1.4. PROJECT ADMINISTRATIVE DATA

No. DESCRIPTION EXPLANATION


A ADMINISTRATIVE DATA OF SUPERVISION AND DESIGN
1. Project Owner Directorate General of Highways
2. Package Name The Implementation of Cisumdawu Toll Road
Phase 2
3. Sub Project Managers Andi Bustami, ST
(PPK) name
Sub Project Manager of Supervision and Design
4. Position
of The Implementation of Cisumdawu Toll Road
Project
5. Address Jl. Winaya Mukti No. 01 Komplek ITB Kab.
Sumedang
6. Phone/ Fax/ Email Telp. (022) 7795597 Email
ppk_ppjbhc@yahoo.com

B ADMINISTRATIVE DATA OF THE IMPLEMENTATION


1. Pemilik Kegiatan Directorate General of Highways
2. Package Name The Implementation of Cisumdawu Toll Road
Phase 2
3. Sub Project Managers Ratno Adi Setiawan, ST., MT.
(PPK) name
4. Position Sub Project Manager of The Implementation of
Cisumdawu Toll Road Project
5. Address Jl. Winaya Mukti No. 01 Komplek ITB Kab.
Sumedang
6. Phone/ Fax/ Email Telp. (022) 7795597 Email
cisumdawuphase2@gmail.com

C ADMINISTRATIVE DATA OF SUPERVISION CONSULTANT


1. Supervision Consultant CECI (China Engineering Consultant,Inc.)
Cooperates with :

Supervisi/Pengawasan Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 3


TECHNICAL JUSTIFICATION

PT. Ciriatama Nusawidya Consultant, PT. Daya


Creasi Mitrayasa, PT. Indra Karya (Persero), PT.
Parama Karya Mandiri, PT. Seecons.
No. DESCRIPTION EXPLANATION
2. Representative Director Van Go
3. Address Wolter Monginsidi 122-124 Tendean Square No.
27, Kelurahan Petogogan, Kecamatan Kebayoran
Baru, Jakarta Selatan
4. Phone/ Fax Telp. (021) 72784046 Fax. (021) 72786905
5. Contract No. HK.02.03/PK-P2JBHC/I/2016/20
6. Contract Date 22th January 2016
7. Amandment No. 01 18th August 2016
8. Contract Price Rp. 65.196.021.000,00 (including VAT)
(Original Contract) (Sixty Five Billion One Hundred Ninety Six
Million Twenty One Thousand Rupiah)
9. Contract Price Rp. 65.196.021.000,00 (termasuk PPN)
(Amandment No. 01) (Sixty Five Billion One Hundred Ninety Six
Million Twenty One Thousand Rupiah)
10. SPMK No. HK.02.03/PK-P2JBHC/VIII/2016/188
11. SPMK Date 22th August 2016
12. Maintenance Period 36 (Thirty Six) months

D ADMINISTRATIVE DATA OF THE CONTRACTOR


1. Contractor Metallurgical Corporation of China Ltd.
Consortium PT. Wika PT. Nindya Karya - PT.
Waskita joint operation
2. General Superintendent Hu Yinglin
3. Address Jalan Dangdeur Dusun Ciawi Larangan Desa
Ciherang - Sumedang Regency, West Java
Province
4. Phone/ Fax Telp. (022) Fax. (022)
5. Contract No. KU.03.01/PJBHCP-II/16
6. Contact Date 15th September 2015
7. Contract Price Rp. 3.485.999.660.965,00 (termasuk PPN)
(Original Contract) (Three Trillions Four Hundred Eighty Five
Billions Nine Hundred Ninety Nine Millions Six
Hundred and Sixty Thousand Nine Hundred
Sixty Five Rupiah)

Supervisi/Pengawasan Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 4


TECHNICAL JUSTIFICATION

8. SPMK No. KU.03.01/PJBHC/II/31


9. SPMK Date 18th August 2016
No. DESCRIPTION EXPLANATION
10. End of Original Contract September 12th 2019
11. Maintenance Period 730 (Seven Hundred and Thirty) Calendar Days

E DATA TEKNIS
1. Length of Main Road 58,2 km
2. Handling Treatment : 10,2 km

- Main Road 10,2 km


(Sta. 12+000 - 12+628 & Sta. 17+200 26+800)
- Tunnel 472 m (Sta. 12+628 13+100)
3. Speed Plan 80 km/jam (main road)
4. Band width 2 X 3,60 m
5. Outside Road Width 3,00 m
6. Inside Road Width 1,50 m
7. Median Width 2,50 m
8. Pavement Traffic Road Rigid Pavement
9. Pavement Road Flexible Pavement

D Location Kabupaten Sumedang Provinsi Jawa Barat


E Source of Funds Loan China

Supervisi/Pengawasan Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 5


TECHNICAL JUSTIFICATION

1.5. SITE LOCATION

The site location of toll road Cileunyi Sumedang Dawuan (Cisumdawu) is located in
the province of West Java. For more information can be seen on a map location :

Picture 1.1 Site Location

Supervisi/Pengawasan Pembangunan Jalan Bebas Hambatan Cisumdawu Phase II 6