I TENAGA
1 Tukang Kayu org/hr 2 Rp100,000.00 Rp200,000.00
2 Tukang Batu org/hr 1 Rp100,000.00 Rp100,000.00
3 Pekerja org/hr 2 Rp80,000.00 Rp160,000.00
4 kepala tukang org/hr 0.3 Rp120,000.00 Rp36,000.00
5 mandor org/hr 0.05 Rp110,000.00 Rp5,500.00
II BAHAN
1 kayu dolken Btg 1.25 Rp4,500.00 Rp5,625.00
2 kayu ^30.18 Rp2,000,000.00 Rp360,000.00
3 paku biasa 2"-5" Kg 0.85 Rp14,000.00 Rp11,900.00
4 besi strip (3/4 x 4 Kg 1.1 Rp15,000.00 Rp16,500.00
5 semen PC Kg 35 Rp1,400.00 Rp49,000.00
6 Pasir pasang ^30.15 Rp80,000.00 Rp12,000.00
7 Pasir beton ^3 0.1 Rp92,846.00 Rp9,284.60
^3
^3
8 koral beton ^30.15 Rp120,000.00 Rp18,000.00
9 batu bata merah buah 30 Rp450.00 Rp13,500.00
10 seng plat Lbr 0.25 Rp18,000.00 Rp4,500.00
11 jendela nako buah 2 Rp7,000.00 Rp14,000.00
12 kaca polos ^20.08 Rp50,000.00 Rp4,000.00
13 kunci tanam buah 0.15 Rp45,000.00 Rp6,750.00
14 engsel buah 0.3 Rp2,250.00 Rp675.00
15 Plywood 4 mm Lbr 0.06 Rp51,000.00 Rp3,060.00
JUMLAH (I+II) Rp 1,030,294.60
BIAYA UMUM DAN KEUNTUNGAN 10% Rp 103,029.46
JUMLAH Rp 1,133,324.06
DIBULATKAN Rp 1,133,324.00
Analisa Harga Satuan Pekerjaan
Tabel 6.19 Galian Tanah sedalam 2 m dan 3 m
PEKERJAAN : Perencanaan Polder Sawah Besar
TAHUN
ANGGARAN : 2009
LOKASI : Kec. Gayamsari , kota semarang
ITEM
PEKERJAAN : Galian Tanah sedalam 2 m dan 3 m
SATUAN : m3
No Uraian pekerjaan Satuan Koefesien Harga Satuan JumlahHarga
1 2 3 4 5 6
I TENAGA
1 mandor org/hr 0.008 Rp110,000.00 Rp880.00
2 operator org/hr 0.003 Rp80,000.00 Rp240.00
II ALAT
1 Backhoe jam 0.024 Rp218,826.00 Rp5,251.82
JUMLAH (I+II) Rp6,371.82
BIAYA UMUM DAN KEUNTUNGAN 10% Rp637.18
JUMLAH Rp7,009.01
DIBULATKAN Rp7,009.00
I TENAGA
1 mandor org/hr 0.008 Rp 110,000.00 Rp 880.00
2 sopir org/hr 0.005 Rp 100,000.00 Rp 500.00
II ALAT
1 Dumptruck jam 0.09 Rp 130,324.00 Rp 11,729.16
JUMLAH (I+II) Rp 13,109.16
BIAYA UMUM DAN KEUNTUNGAN 10% Rp 1,310.92
JUMLAH Rp 14,420.08
DIBULATKAN Rp 14,420.00
Tabel 6.21 Urugan Tanah
PEKERJAAN : Perencanaan Polder Sawah Besar
TAHUN
ANGGARAN : 2009
LOKASI : Kec. Gayamsari , kota semarang
ITEM
PEKERJAAN : Urugan Tanah
SATUAN : m3
No Uraian pekerjaan Satuan Koefesien Harga Satuan JumlahHarga
1 2 3 4 5 6
I TENAGA
1Pekerja org/hr 0.0375 Rp 80,000.00 Rp 3,000.00
2 Mandor org/hr 0.013 Rp 110,000.00 Rp 1,430.00
II ALAT
1 Stamper jam 0.13 Rp 11,737.00 Rp 1,525.81
JUMLAH (I+II) Rp 5,955.81
BIAYA UMUM DAN KEUNTUNGAN 10% Rp 595.58
JUMLAH Rp 6,551.39
DIBULATKAN Rp 6,551.00
Tabel 6.22 Urugan Pasir
PEKERJAAN : Perencanaan Polder Sawah Besar
TAHUN
ANGGARAN : 2009
LOKASI : Kec. Gayamsari , kota semarang
ITEM
PEKERJAAN : Urugan Pasir
SATUAN : m3
No Uraian pekerjaan Satuan Koefesien Harga Satuan JumlahHarga
1 2 3 4 5 6
I BAHAN
1 Pasir Urug ^3 1.2 Rp110,000.00 Rp132,000.00
II tenaga
1 pekerja org/hr 0.3 Rp80,000.00 Rp24,000.00
2 mandor org/hr 0.01 Rp110,000.00 Rp1,100.00
JUMLAH (I+II) Rp157,100.00
BIAYA UMUM DAN KEUNTUNGAN 10% Rp15,710.00
JUMLAH Rp172,810.00
DIBULATKAN Rp172,810.00
I BAHAN
1 Batu Belah 20/30 ^3 1.2 Rp350,000.00 Rp420,000.00
2 portland semen kg 202 Rp1,400.00 Rp282,800.00
3 Pasir pasang ^3 0.485 Rp80,000.00 Rp38,800.00
pipa pembuangan pvc
4 diam 3/4 m 1 Rp7,000.00 Rp7,000.00
5 ijuk kg 0.25 Rp10,000.00 Rp2,500.00
II TENAGA
1 pekerja org/hr 1.5 Rp80,000.00 Rp120,000.00
2 tukang batu org/hr 0.6 Rp100,000.00 Rp60,000.00
3 kepala tukang org/hr 0.06 Rp120,000.00 Rp7,200.00
4 mandor org/hr 0.075 Rp110,000.00 Rp8,250.00
III ALAT 0
1 concrete Mixer 0.774 Rp88,000.00 Rp68,112.00
JUMLAH (I+II) Rp1,014,662.00
BIAYA UMUM DAN KEUNTUNGAN 10% Rp101,466.20
JUMLAH Rp1,116,128.20
DIBULATKAN Rp1,116,128.00
Tabel 6.24 Pasangan Batu Bata
PEKERJAAN : Perencanaan Polder Sawah Besar
TAHUN
ANGGARAN : 2009
LOKASI : Kec. Gayamsari , kota semarang
ITEM
PEKERJAAN : Pasangan Batu Bata
SATUAN : m3
No Uraian pekerjaan Satuan Koefesien Harga Satuan JumlahHarga
1 2 3 4 5 6
I BAHAN
1 Bata Merah buah 140 Rp450.00 Rp63,000.00
2 portland semen kg 43.5 Rp1,400.00 Rp60,900.00
3 Pasir pasang ^3 0.08 Rp80,000.00 Rp6,400.00
II TENAGA Rp0.00
1 pekerja org/hr 0.6 Rp80,000.00 Rp48,000.00
2 tukang batu org/hr 0.2 Rp100,000.00 Rp20,000.00
3 kepala tukang batu org/hr 0.02 Rp120,000.00 Rp2,400.00
4 mandor org/hr 0.03 Rp110,000.00 Rp3,300.00
JUMLAH (I+II) Rp204,000.00
BIAYA UMUM DAN KEUNTUNGAN 10% Rp20,400.00
JUMLAH Rp224,400.00
DIBULATKAN Rp224,400.00
I BAHAN
1 Besi Beton (polos/ulir) Kg 1.05 Rp12,000.00 Rp12,600.00
2 Kawat Beton kg 0.015 Rp16,000.00 Rp240.00
II TENAGA Rp0.00
1 pekerja org/hr 0.007 Rp80,000.00 Rp560.00
2 tukang besi org/hr 0.007 Rp100,000.00 Rp700.00
3 kepala tukang besi org/hr 0.001 Rp120,000.00 Rp120.00
4 mandor org/hr 0.0004 Rp110,000.00 Rp44.00
JUMLAH (I+II) Rp14,264.00
BIAYA UMUM DAN KEUNTUNGAN 10% Rp1,426.40
JUMLAH Rp15,690.40
DIBULATKAN Rp15,690.00
I BAHAN
1 Besi profil Kg 1.1 Rp13,000.00 Rp14,300.00
2 Alat bantu set 0.022 Rp34,650.00 Rp762.30
II TENAGA
1 pekerja org/hr 0.064 Rp80,000.00 Rp5,120.00
2 tukang org/hr 0.064 Rp100,000.00 Rp6,400.00
3 kepala tukang org/hr 0.032 Rp120,000.00 Rp3,840.00
JUMLAH (I+II) Rp30,422.30
BIAYA UMUM DAN KEUNTUNGAN 10% Rp3,042.23
JUMLAH Rp33,464.53
DIBULATKAN Rp33,464.00
I BAHAN
1 Portland Cement Kg 6.52 Rp1,400.00 Rp9,128.00
2 Pasir Muntilan ^3 0.0209 Rp150,000.00 Rp3,135.00
3 Alat Bantu set 0.0134 Rp34,650.00 Rp464.31
II TENAGA
1 pekerja org/hr 0.35 Rp80,000.00 Rp28,000.00
2 tukang org/hr 0.17 Rp100,000.00 Rp17,000.00
3 mandor org/hr 0.02 Rp110,000.00 Rp2,200.00
JUMLAH (I+II) Rp59,927.31
BIAYA UMUM DAN KEUNTUNGAN 10% Rp5,992.73
JUMLAH Rp65,920.04
DIBULATKAN Rp65,920.00
6.26 Rencana anggaran biaya san Rekapitulasi Rencana Anggaran Biaya