Anda di halaman 1dari 7

See

discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/237189851

Initial operating experiences of a nutrient


removal process (Modified Bardenpho) at
Kelowna, British Columbia

Article in Canadian Journal of Civil Engineering February 2011


DOI: 10.1139/l84-067

CITATIONS READS

6 134

2 authors, including:

Gerry Michael Stevens


AECOM - Kelowna B.C.
16 PUBLICATIONS 20 CITATIONS

SEE PROFILE

All content following this page was uploaded by Gerry Michael Stevens on 21 November 2014.

The user has requested enhancement of the downloaded file.


Initial operating experiences of a nutrient removal process (Modified Bardenpho) at
Kelowna, British Columbia'
W. K. OLDHAM
Department of Civil Engineering, University of British Columbia, Vancouver, B . C . , Canada V6T I W5
AND
G . M . STEVENS
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Renmin University of China on 06/04/13

Water and Wastewater Division, City of Kelowna, I435 Water Street, Kelowna, B . C . , Canada VIY 154
Received August 12, 1983
Revised manuscript accepted May 7, 1984

A new wastewater treatment plant that utilizes the "Modified Bardenpho" process for nutrient removal has recently been
commissioned in Kelowna, B.C. The 260 L/s facility (130 L/s in each of two parallel modules) has been operating at full
design flow through one module for over 6 months.
Two months of operating time was required to establish the nitrification-denitrification capabilities and to build up the
phosphorus release-uptake mechanism in the biomass. Subsequent to that start-up period, the process has been capable of
producing an effluent containing less than 5 mg/L total nitrogen and less than 0.3 mg/L orthophosphate when the influent
sewage has contained some 30 mg/L of nitrogen and 6 mg/L of phosphorus.
Key words: phosphorus removal, nitrogen removal, biological waste treatment, advanced waste treatment.

L'usine d'kpuration des eaux usCes construite rkcemment a Kelowna (Colombie Britannique) utilise le procCdC Bardenpho
modifik pour I'enlkvement des substances nutritives. Le traitement est form6 de nitrification, de dknitrification et d'enlkvement
microbiologique du phosphore (relargage et absorption).
For personal use only.

I1 a fallu 2 mois avant que le systkme n'atteigne son Cquilibre. Aprks cette @node de rnise en route l'usine a produit un
effluent contenant moins de 5 mg/L d'azote total et moins de 0,3 mg/L d'orthophosphates alors que I'affluent de l'usine
contenait 30 mg/L d'azote et 6 mg/L de phosphore.
Mots clks: dtphosphatage, dknitrification, traitement biologique des eaux usCes, traitements tertiaires.
[Traduit par la revue]
Can. J. Civ. Eng. 11. 474-479 (1984)

Introduction fy the provincial authorities, a process train as outlined


The new Kelowna Pollution Control Centre (KPCC) in Fig. 2 was utilized. In terms of the broad objectives
was designed to operate in the "Modified Bardenpho" of the waste management scheme, the following pro-
or "Phoredox" mode (see Fig. 1) to achieve biological cess components are of interest.
removal of nitrogen (N) and phosphorus (P). Effluent
quality requirements for N and P , as well as for the (a) Bioreactor (see Fig. 3 )
more general parameters, BOD, (biochemical oxygen T h e bioreactor is designed to reduce the soluble frac-
demand) and S S (suspended solids), are shown in tions of BOD,, total N, and total P t o values below
Table 1. those required for effluent quality. T h e phosphorus re-
Some of the more important process design values quirement is met by creating an environment in which
used for the Kelowna facility are summarized as fol- the biomass is capable of extracting P from solution in
lows: Q,, = 260 L/s ( 6 X lo6 US gpd); Q,, = 660 L/s much greater quantity than actually required for
(15 x lo6 US gpd) (hydraulic design criterion); Tmi,= growth. The phosphorus can thereby be extracted from
10C in mixed liquor; influent C O D (chemical oxygen the process as part of the sludge wasting stream.
demand) = 375 mg/L; influent BOD, = 200 mg/L; Nitrogen removal is accomplished by sequential
influent total N = 35 mg/L; and influent total P = nitrification-denitrification in a single sludge system,
6.5 mg/L. with most of the total N lost from the system as nitrogen
gas.
Plant configuration
T o achieve the degree of treatment necessary to satis- (b) Final clar$et-s
Since the effluent requirements' are stringent with
'This paper was presented at the 1983 Annual Conference respect to suspended solids, it is imperative that good
of the Canadian Society for Civil Engineering, Ottawa, solids separation be continuously achieved on the out-
Ontario, June 1-3. flow from the bioreactor. The final clarifiers were de-
OLDHAM AND STEVENS 475

I 1 I I
0
I I I
b ANAEROBIC 1- + ANAEROBIC AEROBIC

FERMENTATION
b
RESPIRATION RESPIRATION
-
I-*
I
Candltlonlng (ANOXIC) BOO r*ductlon
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Renmin University of China on 06/04/13

tor P uptaka O*nllrlflcotlon plus nllrlflcallm


I
I I

AEROBIC ANAEROBIC

RESPIRATION RESPIRATION

CLARIFIER C02 strlpplng plus (ANOXlC)

ory9*nallon to prav*nt D~nltr1t1catIon

furlher d.nltrltlcallon tor nom - r*cyc(.d P

FIG. 1. Modified Bardenpho process.


For personal use only.

TABLE1. Provincial permit require- disinfection in a contact basin designed for 2 h of de-
ments for KPCC effluent tention at design average flows. The maintenance of a
free chlorine residual is possible because of the high
Value not to be exceeded efficiency of nitrification designed into the system.
Parameter (mg/L)
(e) Waste activated sludge handling
BODS 8 To make it easy to use solids retention time (SRT) to
SS 7
Total N 6
control the bioreactor operation, the wasting of acti-
Total P 2 vated sludge is being done from the final cell of the
bioreactor, rather than from the clarifier underflow. An
additional benefit of using this wasting point arises
signed to function at solids loading rates recommended from the aerobic nature of the resulting waste stream,
for extended aeration plants, because the operating which in turn more or less ensures that the P content of
sludge age (or solids retention time) may be as high as the waste sludge is contained in the solids fraction. The
40 days. That design loading rate is about 8 kg/(m2-h) clarifier underflow, on the other hand, could have
at peak flow. undergone some P release to the water phase of the
mixture, which could adversely affect total P removal
( c ) Dual media filters in the treatment plant.
To help ensure excellent disinfection of the final ef- Disposal of the waste activated sludge (WAS) is via
fluent, and to provide a factor of safety regarding the composting with sawmill wastes-hence trucking to a
accomplishment of the effluent SS requirement, dual remote site is involved. To minimize trucking costs,
media automatic backwash filters were installed. The thickening of the WAS is desirable, but is restricted to
anticipated (and achieved) effluent SS was thereby less an aerobic thickening environment to ensure that P re-
than 3 mg/L. lease to the separated liquid stream does not occur.
Dissolved air flotation (DAF) was the process of
( d ) Chlorination choice. It was designed to be capable of handling the
Because it is anticipated that the effluent from the anticipated WAS flows without the addition of poly-
KPCC will be used for irrigation of a variety of crops mers, and to give a 4% solids content in the float.
in rural areas with small land holdings, public health
considerations are paramount. To achieve good disin- Ifl Primary sludge handling
fection, the filtered effluent is subjected to free chlorine Primary sludge is pumped to a gravity thickening
CAN. J. CIV. ENG. VOL. 11. 1984
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Renmin University of China on 06/04/13

- * Mapnsllc Flow Meter


For personal use only.

S e w a p e plpe
-- - Sludge p l p e

FIG.2. Schematic of Kelowna Pollution Control Centre.

G F E D C A
Legend: + Main flow ---b Mixed l~quorflow ---b Return sludge

FIG.3. Biological reactor module.

tank (an old anaerobic digester), from which the super- (g) Equalization basin
natant is returned to the process stream. Both the thick- To provide some measure of load equalization to the
ened primary sludge and the DAF float is transferred to bioreactor, the old activated sludge tank has been con-
a short-term storage vault, with trucking to the com- verted into an equalization basin, which automatically
posting site occurring therefrom. stores primary effluent during the peak hours of the day
OLDHAM AND STEVENS 477

30 30

-
J
-
p
J

P
: 20 : 20
T
Z 0'
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Renmin University of China on 06/04/13

I0 10

0
I 11 PI 31 10 20 30 10 20 30 9 I9 29 8 18 28 8 I8 28 1 I5 '1 11 21 31 D 2 0 3 0 10 20 30 9 19 29 8 18 28 8 18 28 1 I5
MDI June July lw. 5.~1. Ocl. Nor. MOI June July lug. Ssp1 Ocl. Nor.

FIG. 4. Effluent ammonia nitrogen. FIG.5. Effluent nitrate nitrogen.

and releases it to the process during the low-flow night mg/L, with the average being 29 mg/L. The total COD
hours. in the primary clarifier effluent over this same period
averaged 200 mg/L (s.d. = 58 mg/L).
Commissioning
During the last week of April 1982, the contents of Nitrogen removal
the old activated sludge tank (short SRT sludge) was Nitrogen content in the primary effluent has been
For personal use only.

transferred to one module of the bioreactor (see Fig. 2), monitored by way of ammonia nitrogen only, so it can
as was the primary effluent flow. Additionally, a small be expected that total nitrogen will be perhaps 30%
amount of sludge from an existing long SRT treatment higher. The ammonia N concentration in the primary
plant was added to the new bioreactor. effluent has averaged 22 mg/L, with a standard devi-
Between May 1 and mid-November, the system was ation of 4.8 mg/L.
operated continuously with all components generally on Dissolved nitrogen forms in the secondary clarifier
stream as required, with the exception of the equal- effluent are quantified in Figs. 4 and 5 . Two primary
ization basin, which only went into service in October. points to note are that essentially complete nitrification
With one module of the bioreactor operating, and with was established within 1 month of initial start-up, and
measured daily flows ranging from 88 to 295 L/s, com- that denitrification capabilities were present from the
parison with the design data presented earlier shows beginning, with only a slight peak in average weekly
that the first 6i months of operation is a true indicator nitrates after 3-4 weeks of operation.
of anticipated operation at full design flows. After nitrification and denitrification were estab-
Wasting of activated sludge on a consistent basis was lished, there was only 1 week when the average total
commenced in early July. Up to that time, only short nitrogen exceeded the permit requirement (Sept 11 data
periods of wasting occurred in order to test the oper- point). The high average ammonia-N concentration
ation of the DAF units. during that week was caused by a single high day. That
reading, plus other single high-day values indicated by
Treatment results-single module operation the limits on Fig. 4 were explainable by two reasons:
Effluent quality from the new KPCC has been excep- (a) A partial loss of nitrification occurred on Sept. 2
tional, especially when it is recognized that for the first owing to a gate between cell 2G (Fig. 3) and the main
41 months of operation there were many interruptions to flow channel being removed for repairs. Most of the
"normal" operating procedures while various con- first aerobic zone was therefore bypassed.
tractors tested equipment and rectified deficiencies. All (b) The other high ammonia-N values in mid-August
samples taken to determine process efficiency have and mid-September were apparently caused by low
been grab samples obtained during the day shift. influent COD and high aeration tank oxygen levels,
Conventional testing for BODS and SS in the filtered combined with high mixed liquor temperatures. This
effluent has shown values of < 10 mg/L and <4 mg/L, combination of operating conditions gave rise to rapid
respectively, at all times. More-detailed testing of sec- loss of substrate in the recycle leg of the process (row
ondary clarifier effluent has provided dissolved COD 3 in Fig. 3). Dissolved ammonia values found in cell 3B
results ranging from a low of 5 mg/L to a high of 70 on these days (up to 23 mg/L) indicate that endogenous
478 CAN. J. CIV. ENG;. VOL. 1 1 , 1984

TABLE2. Orthophosphate scans

Dissolved ortho-P (mg/L)


Date Effluent Cell 1G Cell 2G Cell 2B
October 25 0.17 0.39 0.35 10.4
November 1 4.0 0.72 0.35 8.2
November 3 0.16 0.24 0.60 12.4
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Renmin University of China on 06/04/13

Examination of Fig. 6 shows that good phosphorus


removal was achieved within 2 months of initial plant
start-up. As anticipated from others' experience with
the process, good P removal was not obtained until
good P release into solution was occurring in the anaer-
obic zone (cells 3A, 2A, and 2B in Fig. 3). After the
FIG. 6. Effluent orthophosphorus. first 2 months of operation, the dissolved ortho-P con-
centration had risen to about 10 mg/L from an initial
respiration was causing a high release of reduced nitro- value of about 4.5 mg/L. By mid-July, dissolvedortho-
gen from the biomass. If some of this endogenous re- P in the anaerobic zone had risen to between 15 and
lease had been present in cell 3D, it would not have 25 mg/L.
been nitrified by the time it reached the effluent. In mid-August, phosphorus in the effluent began to
Nitrate nitrogen in the secondary clarifier effluent has increase (see Fig. 6). A review of plant records at that
been continuously below 4 mg/L since midJune, ex- time showed that the P content of the mixed liquor
For personal use only.

cept on 1 day when a value of 5.6 mg/L was deter- solids leaving the bioreactor had reached a plateau at
mined (see Fig. 5). Although no specific reason for this about 6.25%. Assuming this P content to be a max-
somewhat high reading can be ascertained from the imum attainable value, a phosphorus mass balance cal-
data, it would appear to be related to a partial loss in culation showed that an effluent P concentration of
denitrification capability in the first anoxic zone (cells about 1.7 mg/L was all that could be expected for the
2C-2E on Fig. 3). On that day, the nitrate-N content summer sewage characteristics and the then current
in 2E rose to 3 mg/L, whereas it is normally below plant operating conditions (Q = 170 L/s, MLSS
2 mg/L. (mixed liquor suspended solids) = 3500 mg/L, influent
It is interesting to note that good nitrogen removal tot. P = 6 mg/L, SRT = 35 d). Wasting from the
has been attainable in the Kelowna facility with an bioreactor was subsequently increased from 3.3 to
average ratio of COD/NH3-N in the bioreactor influent 4.5 L/s, and by the end of August the effluent phos-
of 200122, or 9/ 1. This result is somewhat at odds with phorus was again below 0.5 mg/L.
conclusions of researchers in South Africa. For in- The subsequent phosphorus peak during the first
stance, Marais et al. (1982), in their review of South week in September was due to the pulling of the gate in
African experience, indicate that the Modified Bar- cell 2G, as mentioned previously, thus not allowing
denpho or Phoredox system can only achieve good total sufficient aerobic time for the phosphorus released in
nitrogen removal if the COD/TKN ratio is at least the anaerobic zone to be taken back into the biomass.
1211. If it is assumed that NH3-N is about 80% of TKN Two individual high readings for effluent ortho-P
(total Kjeldahl nitrogen), then a required COD/NH3-N occurred during the single-module phase of operations.
ratio of about 1511 is indicated. On June 16, an ortho-P value of 6.1 mg/L was recorded
at a time when the air supply had been out of service for
Phosphorus removal some 12 h. This failure apparently resulted in the occur-
The concentration of phosphorus in the influent flow rence of generally anaerobic conditions throughout the
to the bioreactor has typically been between 5 and bioreactor, with subsequent release of phosphorus.
6 mg/L. Until the composite sampler is operating, it is On November 1, an effluent ortho-P concentration of
not possible to describe the influent P concentration in 4 mg/L was measured. It is believed that this anoma-
any more exact terms. Dissolved ortho-P in the second- lous result is due to a sampling error or a malfunction
ary clarifier effluent is summarized in Fig. 6. Spot in the Technicon Autoanalyzer. This explanation is up-
checks with total ortho-P in the final plant effluent have held by an analysis of ortho-P data in various cells (see
shown good correlation, with differences being no more Fig. 3) of the bioreactor on November 1 and a "normal"
than 0.2 mg/L. day such as October 25 or November 3. As the mixed
OLDHAM AND STEVENS 479

liquor progresses from cell 2B (anaerobic), through 2G values of about 1 mg/L being obtained thereafter.
and 1G to the effluent, there should be a general (2) Phosphorus removal capabilities took 2 months to
progression to less dissolved ortho-P. As indicated in become established. Subsequently, the system was
Table 2, the effluent value for November 1 is not at all found to produce an effluent with an average ortho-
defensible in terms of the other measured values in the phosphate concentration of <0.5 mg/L as P, when the
process on the same day. If that effluent value is re- influent to the bioreactor (primary clarifier effluent) had
moved from Fig. 6, the average phosphorus concen- an ortho-P concentration between 5 and 6 mg/L.
tration for the week of November 7 is reduced to (3) Some individual analytical values for N and P in
Can. J. Civ. Eng. Downloaded from www.nrcresearchpress.com by Renmin University of China on 06/04/13

0. I2 mg/L, which is in line with the other weekly the effluent were considerably higher than the averages,
averages. but in every case except one the high values were ex-
plainable in terms of physical problems associated with
Continuing plant operation the start-up of such a complex facility. The one data
In mid-November, the process flow pattern was point that could not be easily explained was shown to be
changed from single-module operation to dual-module suspect in its measured value.
operation so that process optimization studies could be (4) The first 6f months of operation give a strong
commenced. These ongoing studies are intended to de- indication that the Modified Bardenpho system is
termine the importance of various design and oper- capable of providing an effluent with an average total N
ational parameters on the efficiencies of both nitrogen content of 4-5 mg/L and a total ortho-P content of less
and phosphorus removal. The research project, which is than 0.5 mg/L. Such results are shown to be obtainable
funded by Environment Canada through the De- with a sewage having a COD/NH,N ratio of 911.
partment of Supply and Services, is expected to take 2
years to complete. Acknowledgement
Portions of the data used herein were gathered with
Conclusions funding received from Environment Canada through an
For personal use only.

Based upon more than 6 months of plant operation at unsolicited proposal to the Department of Supply and
design flows and loading (achieved by operating only Services.
one of two modules), the nutrient analysis program
on plant influent and effluent justifies the following MARAIS, G. V. R., LOEWENTHAL, R. E., and SIEBRITZ, F.
conclusions. 1982. Review: Observations supporting phosphate removal
(1) Nitrification and denitrification were well estab- by biological excess uptake. IAWPR Post Conference
lished within I month of plant start-up, with effluent Seminar on Phosphate Removal in Biological Treatment
Processes, Pretoria, S.A.
nitrate-N values of about 3 mg/L and ammonia-N

View publication stats

Anda mungkin juga menyukai