17 Dec 2017 Jan 2018 Feb 2018 Mar 2018 Apr 2018 May 2018 Jun 2018 Jul 2018
Name Duration Start Finish
23 30 06 13 20 27 03 10 17 24 01 08 15 22 29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17 24 01 08 15
1 TS AL BAKER VILLA 275 days 7 / 3 1 / 1 7 8 : 0 0 A M 6/16/18 5:00 PM
2 ELECTRICAL WORKS 75 days 7 / 3 1 / 1 7 8 : 0 0 A M 10/25/17 5:00 PM
3 ELEC POINTS & ROUGH... 20 days 7/31/17 8:00 AM 8/22/17 5:00 PM
4 ELEC WIRING-INS 20 days 8/23/17 8:00 AM 9/14/17 5:00 PM
5 ELEC SOCKET & SWITCH... 20 days 9/16/17 8:00 AM 10/8/17 5:00 PM
6 ELEC LIGHTING INS 15 days 10/9/17 8:00 AM 10/25/17 5:00 PM
7 SANITARY & PLUMBING ... 40 days 7 / 3 1 / 1 7 8 : 0 0 A M 9/14/17 5:00 PM
8 BATHROOM ROUGH-INS 20 days 7/31/17 8:00 AM 8/22/17 5:00 PM
9 BATHROOM FIXTURE-INS 20 days 8/23/17 8:00 AM 9/14/17 5:00 PM
10 KITCHENS ROUGH-INS 10 days 7/31/17 8:00 AM 8/10/17 5:00 PM
11 KITCHENS FIXTURE INS 10 days 8/12/17 8:00 AM 8/22/17 5:00 PM
12 WATERPROOFING WORKS 45 days 8 / 2 3 / 1 7 8 : 0 0 A M 10/14/17 5:00 PM
13 BATHROOMS 15 days 8/23/17 8:00 AM 9/9/17 5:00 PM
14 ROOF 30 days 9/10/17 8:00 AM 10/14/17 5:00 PM
15 CONCRETE & MASONRY ... 50 days 7 / 3 1 / 1 7 8 : 0 0 A M 9/26/17 5:00 PM
16 INTERIOR BLOCKWORK 15 days 7/31/17 8:00 AM 8/16/17 5:00 PM
17 INTERIOR PLASTERWORK 30 days 8/23/17 8:00 AM 9/26/17 5:00 PM
18 CARPENTRY 125 days 9 / 2 7 / 1 7 8 : 0 0 A M 2/19/18 5:00 PM
19 CEILING 60 days 11/1/17 8:00 AM 1/9/18 5:00 PM
20 DRYWALL 20 days 1/10/18 8:00 AM 2/1/18 5:00 PM
21 WINDOWS 30 days 9/27/17 8:00 AM 10/31/17 5:00 PM
22 DOORS 15 days 2/3/18 8:00 AM 2/19/18 5:00 PM
23 CABINETRY 30 days 1/10/18 8:00 AM 2/13/18 5:00 PM
24 HVAC 170 days 7 / 3 1 / 1 7 8 : 0 0 A M 2/13/18 5:00 PM
25 DUCTING & PLENUM-INS 35 days 7/31/17 8:00 AM 9/9/17 5:00 PM
26 INDOOR UNITS 15 days 1/10/18 8:00 AM 1/27/18 5:00 PM
27 OUTDOOR UNITS 15 days 1/28/18 8:00 AM 2/13/18 5:00 PM
28 GRILLS INSTALLATION 6 days 1/28/18 8:00 AM 2/3/18 5:00 PM
29 COMMISSIONING & TEST... 6 days 2/4/18 8:00 AM 2/10/18 5:00 PM
30 INTERIOR WALL & FLOO... 135 days 1 / 1 0 / 1 8 8 : 0 0 A M 6/16/18 5:00 PM
31 FLOOR SCREED 15 days 1/10/18 8:00 AM 1/27/18 5:00 PM
32 TERRAZZO INS 15 days 1/28/18 8:00 AM 2/13/18 5:00 PM
33 FLOOR FINISHES-HALLS 30 days 2/14/18 8:00 AM 3/20/18 5:00 PM
34 WALL FINISHES-HALLS 30 days 3/21/18 8:00 AM 4/24/18 5:00 PM
35 WALL FINISHES-BATHRO... 30 days 1/28/18 8:00 AM 3/3/18 5:00 PM
36 FLOOR FINISHES-BATHR... 30 days 3/4/18 8:00 AM 4/7/18 5:00 PM
37 PAINTING WORKS 45 days 4/25/18 8:00 AM 6/16/18 5:00 PM