TIME SCHEDULE

BULAN : 1 ( SATU )
PROYEK : PEMBANGUNAN KOMPLEK PERUMAHAN "CITI 9 AIRPORT VILLAGE" TANGGAL : 11 DESEMBER 2014
PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL TYPE - 60 STANDART S/D : 31 JANUARI 2015
LOKASI : JL. H. SYUKUR RT. 01 RW. 14 Ds. SEDATIGEDE, SEDATI - SIDOARJO NOMOR : 001/OP/SDJ/DP/I/2015

PROSENTASE PROSENTASE PROGRESS PROGRESS SELISIH


NO URAIAN PEKERJAAN BOBOT %
BULAN LALU % BULAN INI % BULAN LALU BULAN INI PROGRESS

A PEK. PERSIAPAN
1 Manajemen Proyek
2 Air Kerja
3 Listrik Kerja
4 Pembersihan Lapangan & Buang Gragal / Tanah
5 Pengukuran & Pasang Bouwplank
6 Pagar Sementara
7 Alat Bantu Kerja (Scafolding, Lampu, Kabel, dll)

B PEK. TANAH
1 Galian Tanah Pondasi 0.0138 100% 0.0138
2 Urugan Pasir Bawah Pondasi t = 10 cm 0.0062 100% 0.0062
3 Rabatan Lantai Kerja t = 5 cm 0.0132 100% 0.0132
4 Rabatan Lantai Tanpa tulangan Area Carport 0.0018
5 Urugan Kembali bekas galian 0.0031

C PEK. STRUKTUR
I PEK. PONDASI
1 Beton Strauss pile 30 cm / 4m ( 5 10, 6 - 150 ) 0.0867 100% 0.0867
2 Beton Plat Setempat/Poer, uk 60x60 30 cm ( 8 - 150 )
- Beton mutu K - 225 0.0085 100% 0.0085
- Pembesian mutu BJTP U 39
- Pembesian mutu BJTP U 24 0.0058 100% 0.0058
- Bekisting Batako 0.0050 100% 0.0050
3 Pasang Pondasi bt. Kali & Aanstampeng, uk 30x80x70 cm 0.0578 100% 0.0578
4 Pasang Roolag bata merah trap area teras 0.0050
5 Beton Sloof, uk 15x30 cm ( 6 10, 8 - 150/200 )
- Beton mutu K - 225 0.0116 100% 0.0116
- Pembesian mutu BJTP U 39 0.0000 100% 0.0000
- Pembesian mutu BJTP U 24 0.0205 100% 0.0205
- Bekisting Batako 0.0137 100% 0.0137

II PEK. BETON KOLOM


1 Beton Kolom K1, uk 13x15 cm ( 4 10, 8 - 150 )
- Beton mutu K - 225 0.0007 35% 0.0002
- Pembesian mutu BJTP U 39 0.0000 100% 0.0000
- Pembesian mutu BJTP U 24 0.0017 100% 0.0017
- Bekisting Triplek 0.0013 40% 0.0005
2 Beton Kolom K2, uk 15x20 cm ( 4 10, 8 - 150 )
- Beton mutu K - 225 0.0100 35% 0.0035
- Pembesian mutu BJTP U 39 0.0000 100% 0.0000
- Pembesian mutu BJTP U 24 0.0168 100% 0.0168
- Bekisting Triplek 0.0114 40% 0.0046

III PEK. BETON BALOK


1 Beton Ring Balk Rb, uk 15x15 cm ( 4 10, 8 - 200 )
- Beton mutu K - 225 0.0051
- Pembesian mutu BJTP U 39 0.0000
- Pembesian mutu BJTP U 24 0.0120
- Bekisting Triplek 0.0047
PROSENTASE PROSENTASE PROGRESS PROGRESS SELISIH
NO URAIAN PEKERJAAN BOBOT %
BULAN LALU % BULAN INI % BULAN LALU BULAN INI PROGRESS
2 Beton Balok B1, uk 15x20 cm ( 4 10, 8 - 150/200 )
- Beton mutu K - 225
- Pembesian mutu BJTP U 39
- Pembesian mutu BJTP U 24
- Bekisting Triplek
3 Beton Balok Talang B2, uk 15x30 cm ( 6 10, 8 - 150/200 )
- Beton mutu K - 225 0.0028
- Pembesian mutu BJTP U 39 0.0000
- Pembesian mutu BJTP U 24 0.0050
- Bekisting Triplek 0.0039
4 Beton Plat dak ( topi-topian ) t= 12 cm ( 8 - 150 )
- Beton mutu K - 225
- Pembesian mutu BJTP U 39
- Pembesian mutu BJTP U 24
- Bekisting Triplek

D PEK. ARSITEKTURAL
I PEK. PASANGAN DINDING
1 Pas. Dinding Batu Alam 0.0078
2 Pas. Dinding Bata Merah 1 : 5 0.1039 35% 0.0364
3 Plesteran dinding 0.1390
4 Acian dinding 0.0353
5 Benangan/tali air 0.0050

II PEK. RANGKA DAN PLAFON


1 Pas. Plafon Gypsum 9 mm ex Jayaboard (area interior) 0.0169
include Rangka Hollow Galvalum
2 Pas. Plafon Kalsiboard 4 mm (area exterior) 0.0018
include Rangka Hollow Galvalum
3 Pasang List Plafon Gypsum 0.0000

III PEK. PENGECATAN


1 Cat Plafon Gypsum 0.0050
2 Cat List Gypsum 0.0000
3 Cat Dinding Interior ex Catylac / setara 0.0294
4 Cat Dinding exterior ex Dulux Weathershield 0.0211

IV PEK. PENUTUP LANTAI & DINDING


1 Pas. Keramik Lantai 40 x 40 cm ex lokal / setara ( L1 ) 0.0434
2 Pas. Keramik Lantai 30 x 30 cm ex lokal / setara ( L2 ) 0.0023
3 Pas. Keramik Lantai km/wc 20 x 20 cm ex lokal / setara (L3) 0.0010
4 Pas. Keramik Dinding km/wc 20 x 25 cm ex lokal/setara (L3) 0.0040

V PEK. RAILING, KUSEN, PINTU & JENDELA


1 (PJ.1) Pintu Panel Jendela Double 0.0187
- Profil Kosen Allumunium, Silver 1 3/4 x 3" Powder Coating
- Pintu double teakwood 6 mm lapis melamic
rangka kamper samarinda oven
- Frame Jendela Finish Powder Coating
- Kaca Jendela, Clear Glass 5 mm
- Sealant Non Struktural DC 688
- Hardware
Lever Handle LHTR 0821 + Escutcheon, Ex. Dekkson
Lockcase MTS IL 8485 SSS, Ex. Dekkson
Cylinder CYL DC DL 60 mm SN, Ex. Dekkson
Hinges ES IR 4x3x3 mm 4BB CP, Ex. Dekkson
2 (PJ.2) Pintu Jendela Double 0.0187
- Profil Kosen Allumunium, Silver 1 3/4 x 3" Powder Coating
- Pintu double teakwood 6 mm lapis melamic
rangka kamper samarinda oven
- Frame Jendela Finish Powder Coating
- Kaca Jendela, Clear Glass 5 mm
- Sealant Non Struktural DC 688
- Hardware
Lever Handle LHTR 0821 + Escutcheon, Ex. Dekkson
Lockcase MTS IL 8485 SSS, Ex. Dekkson
Cylinder CYL DC DL 60 mm SN, Ex. Dekkson
Hinges ES IR 4x3x3 mm 4BB CP, Ex. Dekkson
PROSENTASE PROSENTASE PROGRESS PROGRESS SELISIH
NO URAIAN PEKERJAAN BOBOT %
BULAN LALU % BULAN INI % BULAN LALU BULAN INI PROGRESS
3 (PJ.3) Pintu Jendela Single 0.0088
- Profil Kosen Allumunium, Silver 1 3/4 x 3" Powder Coating
- Pintu double teakwood 6 mm lapis melamic
rangka kamper samarinda oven
- Frame Jendela Finish Powder Coating
- Kaca Jendela, Clear Glass 5 mm
- Sealant Non Struktural DC 688
- Hardware
Lever Handle LHTR 0821 + Escutcheon, Ex. Dekkson
Lockcase MTS IL 8485 SSS, Ex. Dekkson
Cylinder CYL DC DL 60 mm SN, Ex. Dekkson
Hinges ES IR 4x3x3 mm 4BB CP, Ex. Dekkson
4 (P.1) Pintu double teakwood 0.0117
- Profil Kosen Allumunium, Silver 1 3/4 x 3" Powder Coating
- Pintu double teakwood 6 mm lapis melamic
rangka kamper samarinda oven
- Hardware
Lever Handle LHTR 0821 + Escutcheon, Ex. Dekkson
Lockcase MTS IL 8485 SSS, Ex. Dekkson
Cylinder CYL DC DL 60 mm SN, Ex. Dekkson
5 (P.2) Pintu PVC ( area k. Mandi ) 0.0013
6 (J.1) Jendela Single 0.0033
- Profil Kosen Allumunium, Silver 1 3/4 x 3" Powder Coating
- Frame Jendela Finish Powder Coating
- Kaca Jendela, Clear Glass 5 mm
- Sealant Non Struktural DC 688
- Hardware
Hinges ES IR 4x3x3 mm 4BB CP, Ex. Dekkson
7 (J.2) Jendela Double ukuran Besar 0.0250
- Profil Kosen Allumunium, Silver 1 3/4 x 3" Powder Coating
- Frame Jendela Finish Powder Coating
- Kaca Jendela, Clear Glass 5 mm
- Sealant Non Struktural DC 688
- Hardware
Hinges ES IR 4x3x3 mm 4BB CP, Ex. Dekkson
8 (J.3) Jendela Kaca Siku 0.0177
- Profil Kosen Allumunium, Silver 1 3/4 x 3" Powder Coating
- Kaca Jendela, Clear Glass 5 mm
- Sealant Non Struktural DC 688
9 (BV) Bouvenlist 0.0012
- Profil Kosen Allumunium, Silver 1 3/4 x 3" Powder Coating
- Kaca Jendela, Clear Glass 5 mm
- Sealant Non Struktural DC 688

VI PEK. RANGKA & PENUTUP ATAP


1 Pasang rangka atap Galvalum 0.0337
2 Pasang atap genteng beton 0.0230
3 Pasang bubungan / Nok atap genteng 0.0033
4 Pasang lisplank calsiboard L=20 cm 0.0100
5 Talang cor (L=40 cm) 0.0065

E PEK. INSTALASI MEP (MEKANIKAL, ELEKTRIKAL & PLUMBING)

I PEK. SANITARY
1 Pas. Kran Air dinding ex Onda 0.0008
2 Pas. Wastafel / Meja Beton + kitchen seet 0.0012
3 Pas. Avour Lantai 0.0003
4 Pas. Jet shower ex lokal 0.0008
5 Pas. Kloset Duduk ex. American Standart 0.0036

II PEK. INSTALASI MEKANIKAL & PLUMBING


1 Pas. Instalasi Air Bersih Pipa PVC 3/4" AW 0.0025
2 Pas. Instalasi Air Kotor Pipa PVC 4" D 0.0072 30% 0.0022
3 Pas. Instalasi Air Hujan Pipa PVC 3" D 0.0000
4 Pas. Instalasi Air Hujan Pipa PVC 3" D 0.0018 50% 0.0009
5 Pas. Instalasi Air Kotor Hujan PVC 4" D 0.0000
6 Buat Bak Kontrol include tutup Beton 0.0048
7 Tandon Air bawah Beton 1,5 m3 0.0120
8 Septictank 0.0124
9 Sumur peresap 0.0125
PROSENTASE PROSENTASE PROGRESS PROGRESS SELISIH
NO URAIAN PEKERJAAN BOBOT %
BULAN LALU % BULAN INI % BULAN LALU BULAN INI PROGRESS

III PEK. INSTALASI ELEKTRIKAL


1 Instalasi titik lampu ex. Eterna 0.0061
2 Instalasi titik stop kontak ex. Eterna 0.0030
3 Instalasi power meter PLN ke box Panel 0.0007
4 Instalasi Arde BC ( grounding)
5 Instalasi penangkal petir
6 Instalasi box Panel 0.0007
7 Pasang armatur lampu 0.0013
8 Pasang armatur saklar tunggal ex. broco / setra 0.0004
9 Pasang armatur saklar ganda ex. Broco / setara 0.0004
10 Pasang armatur stop kontak ex. Broco / setara 0.0006

T OTAL 1.0000 0.0000 0.3096 0.6905

1 TOTAL PROGRESS BULAN LALU 0.000%

2 TOTAL PROGRESS BULAN INI 30.955% Rp 41,200,000 Rp 12,753,460

3 SELISIH PROGRESS SAAT INI 69.045%

Menyetujui Surabaya, 31 Januari 2015


Pengawas Lapangan Dibuat oleh,

MOEDJIO SANTOSO SARHAM