1. Introduction
This document consists of the following sections:
Site installation commission form.
This section includes site details, information and tests.
Those tests need to be done on every XDM NE and in all site, in order to verify normal
operation of each NE.
Once the customer has signed this form, it constitutes the customers approval of the sites
installation and tests: mechanical, electrical and functional.

2. Site Installation Tests


All the tests mention in the following section need to be done for all NEs and for all sites.
The use of those tests is to verify normal operation of all XDM Network Elements.
For all optical level parameters, please refer to document 417006-2007-013-A0 XDM
System Specification.

2.1 General Information


Customer Name:
Country:
Project Name:
Site Name:
Installation Date:
XDM Type:
Embedded Version:
IP Address
NE ID
NE Name
Chassis Sl No.

DWG NO. 417006-0701-010-77 REV. B0 PAGE 2 OF 11


XDM Site Commission Tests

2.2 NE Cards Inventory


Card / Module Type Slot # Boot Version Serial #

Remark:
Make sure the Boot Version of each card is as required according to the embedded version.

DWG NO. 417006-0701-010-77 REV. B0 PAGE 3 OF 11


XDM Site Commission Tests

Card / Module Type Slot # Boot Version Serial #

Remark:
Make sure the Boot Version of each card is as required according to the embedded version.

DWG NO. 417006-0701-010-77 REV. B0 PAGE 4 OF 11


XDM Site Commission Tests

2.3 NE Mechanical Tests

No. Description Results


1 Rack mechanical mounting

2 DC Power cable installation (main fuse xRAP; xRAP FuseNE)

3 Ground cable connection

4 2, 34, 140, 155 Mbps tributary cables installation and connectors mounting
(CCPDDF)

5 622 Mbps, 2.5, 10 Gbps Optical interface fibber installation

6 DDF Installation

7 ODF Installation

8 Cards / Modules unpacking and insertion to NE

9 Check DC power at the X-RAP for first source need to be (-48V) ~ (-56V) V(DC)

10 Check DC power at the X-RAP for second source need to be (-48V) ~ (-56V) V(DC)

11 NE Power Up.

12 Check both Power sources working o.k. by disconnect each source at a time.

13 Communication to eCraft via Slip

15 Perform slot assignment for all relevant card (according to the Installation book)

16 Check that there are no abnormal alarms

17 LED Test

DWG NO. 417006-0701-010-77 REV. B0 PAGE 5 OF 11


XDM Site Commission Tests

2.4 NE Optical Power Measurements (OPM)

Expected Results
Slot # Card type / Port (1..16 or Wavelength Transmit Receive
Perform slotmodule
assignment for lower / upper)
all relevant cards in Make sure no Optical Level
abnormal * on
alarms Optical Level
any card (Fail *
the Test Procedure shelf (according to the card, bit fail,(dBm)
type mismatch). (dBm)
installation book).

Turn off the circuit breaker. The equipment returns to normal operation
automatically, without the operators intervention.
Wait 30 sec.
Turn on the circuit breaker.

Please mark the measured value by OPM and compare to document 417006-2007-013-A0
XDM System Specification.

DWG NO. 417006-0701-010-77 REV. B0 PAGE 6 OF 11


XDM Site Commission Tests

Slot # Card type / Port (1..16 or Wavelength Transmit Receive


module lower / upper) Optical Level * Optical Level *
(dBm) (dBm)

Please mark the measured value by OPM and compare to document 417006-2007-013-A0
XDM System Specification.

DWG NO. 417006-0701-010-77 REV. B0 PAGE 7 OF 11


XDM Site Commission Tests

2.5 Cross Connection and Tributary Test

2.5.1 Make few cross connection at VC12/VC3 and VC4 level from any where to
any where.

2.5.2 Create cross-connect for all the available E1 tributaries to an optical port.
Loop back all the tributary ports and connect SDH analyzer on the optical port to
which the entire cross-connects are created and run tributary scan.

Result: All the tributary ports are working fine.

2.6 Card Assignment and Un-assignment Test.

2.6.1 Card Assignment

Insert the cards in the shelf and start assigning them.

Result: No alarms for the cards.

2.6.2 Insertion of Different configuration card

Pull out one card and insert a card of different configuration.

EX. Pull out STM-1 card from the shelf and insert STM-4 in that slot.

Result: The alarm is Type Mismatch

2.6.3 Revert back.

Ex. Remove the STM-4 card and insert STM-1 card.

Result: The alarm Type Mismatch gets cleared.

2.7 Protection Test


2.7.1 Configure 1:1 MSP protection for STM-1, STM-4 and STM-16s ( any port
to any port). Following things to be observed

Linear MSP 1+1


Protection STM16/4/1
Normal

SDH equipments
DWG NO. 417006-0701-010-77 REV. B0 PAGE 8 OF 11

ANT-20 STM-16/4/1 optical card


TX RX
XDM Site Commission Tests

Working MSP (1+1)

Linear MSP 1+1


Protection STM16/4/1
Switch Over

TX RX

ANT-20
Loop Break Switch Over

SDH equipments

STM-16/4/1 optical card

2.7.1.1 STM-1 MSP Protection:

Switching Time WTR (Wait To Restore)


NA NA

2.7.1.2 STM-4 MSP Protection:

DWG NO. 417006-0701-010-77 REV. B0 PAGE 9 OF 11


XDM Site Commission Tests

Switching Time WTR (Wait To Restore)


NA NA

2.7.1.3 STM-16 MSP Protection:

Switching Time WTR (Wait To Restore)


13 ms 17 ms

2.8 NE Power UP Test


Power off the NE for few minutes and POWER ON the NE, note down the rebooting time.
I.e. the time taken by the NE to bring traffic back to normal after POWER ON.

Result: ..

2.9 Maintenance Functions


Alarm Indications: For all AGGREGATE & TRIBUTARY cards.

Sr. No. Description


Card Type Slot Pass Fail
Number
1 LOS
2 LOF
3 AU / TU AIS
4 Loopback ON

5 Card Missing

6 Power Fail

7 LOP

Alarms severity needs to be verified as per the default settings.


B1 Alarms (Degrade Signal, Excessive Error)

DWG NO. 417006-0701-010-77 REV. B0 PAGE 10 OF 11


XDM Site Commission Tests

3. Hot-swapping of Cards
1. Remove the standby MATRIX card
2. wait for few minutes
3. Insert the card
4. observe the result
Result: (traffic should not be affected)

5. Remove the working MATRIX card


6. wait for few minutes
7. observe the result
Result: (traffic should switch to protection matrix note down the error count /switching time)
.

Repeat the same test for XMCP and traffic cards and note down the results.

GSPI TEAM O&M TEAM REPRESENTATIVE


REPRESENTATIVE
Name: ____________________ Name: ____________________
Title: ____________________ Title: ____________________
Signature ____________________ Signature ____________________
Date: ____________________ Date: ____________________

DWG NO. 417006-0701-010-77 REV. B0 PAGE 11 OF 11

Anda mungkin juga menyukai