Q.1 (a) the shortest time you can finish this project (20 marks), and critical activities.
A.1 The shortest time of Project to finish 22 days. There are two critical path in diagram. Critical
activity path 1 are A-B-D-F-L-M-R-S-T-U And Path-2 are A-B-G-I-N-O-R-S-T-U