HORMIGONES SIMPLES
HORMIGON 1:3:5 A MANO 1.00 M3
ANALISIS DE MORTEROS 5
1:2 PARA IMPERMEABLE P/ PULIDO
1.00 M3
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNIT. ($)
1 ARENA FINA + 2% DESPERD. 1.02 m3 1,200.00 1,224.00
2 AGUA 100.00 gl 1.50 150.00
3 CAL HIDRATADA (50 LBS) 3.06 fda 65.00 198.90
4 CEMENTO GRIS 17.66 fda 220.00 3,885.20
5 MANO OBRA MEZCLADO 0.50 da 500.00 250.00
COSTO POR M3 5,708.10
1:3 PARA COLOCACION BLOQUES Y PISOS
1.00 M3
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNIT. ($)
1 ARENA GRUESA LAVADA + 2% Desp. 1.02 M3 1,100.00 1,122.00
2 AGUA 69.04 GLS. 1.50 103.56
3 CEMENTO GRIS PORTLAND 11.51 FDA. 220.00 2,532.20
4 MANO OBRA MEZCLADO ( UN PEON) 0.50 DIA 500.00 250.00
COSTO POR M3 4,007.76
1,010.94
8
BLOQUES 6" SNP / 3/8" @ 0.60 M. 1.00
10
BLOQUES 8" SNP / 3/8" @ 0.60 M. CON SERPENTINAS 2 3/8" CADA 3 HILERAS 1.00
BLOQUES 6" SNP / 3/8" @ 0.60 M. CON SERPENTINAS 2 3/8" CADA 3 HILERAS 1.00
11
EXCAVACIONES
1.00 M3
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 TIERRA A MANO 1.00 M3 450.00 450.00
500.00
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 CALICHE A MANO 1.00 M3 550.00 550.00
700.00
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 ROCA A MANO 1.00 M3 850.00 900.00
900.00
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 ROCA A COMPRESOR 1.00 M3 1,800.00 1,800.00
1,800.00
CUBICACION DE MADERA
CUADRO ESTACAS
Espesor Ancho Largo Cantidad Cubicacion Espesor Ancho Largo Cantidad Longitud Cubicacion
(plg) (plg) (p) (uds) (p2) (plg) (plg) (p) (uds) (p) (p2)
1 4 10 33.45888 111.5296 1 4 3.33 33.45888 111.4180704 37.1393568
CUBICACION TOTAL DE MADERA A USAR 148.6689568 P2
ANALISIS DE COSTO PRECIO UNITARIO (P.U)
NO. DESCRIPCION CANTIDAD UNIDAD P.U. ($) SUBTOTAL
1 Clavos corrientes 2 1/2" (1 m. = 0.13 lb) 12.86 Lb 24.00 308.76
2 Cal 50 lbs (1 m. = .05 fda.) 4.95 Fda 65.00 321.62
3 Madera bruta americana (4 usos + 25 % desp.) 148.67 P2 31.00 4,608.74
4 Hilo de nylon + Herramientas 1.00 Ud 1,050.00 1,050.00
5 Tcnico No Calificado (Peon) 2.00 Hombre 500.00 1,000.00
6 Carpintero de segunda (OP2) (1 m. = .015 da) 2.00 Hombre 700.00 1,400.00
7 Maestro de rea (MA) (1 m. = .015 da) 1.00 Ud 1,000.00 1,000.00
Unid. $9,689.12
M $97.91
M2 $22.42
13
4. HORMIGON ARMADO 16
4.1 HORMIGON ARMADO EN ZAPATA DE COLUMNAS / 12 1/2" G40/ HORM. INDUSTRIAL 210 KG
ZAPATA DE COLUMNA
DIMENSIONES DESPERDIC. VOLUMEN CANTIDAD VOLUMEN
LX (M) LY (M) ALTURA (M) POR UD (M3) COLUMNAS TOTAL (M3
1.40 1.80 0.50 1.05 1.32 8.00 10.58
LONGITUD DE GANCHOS 0.15 M
M ACERO
TIPO TAMAO RECUBRIM. LONGITUD GANCHOS LONGITUD # PIEZAS LONG. POR CANTIDAD LONGITUD PESO DESPERDIC.
(M) (M) (M) (M) EFECTIVA. (M) COLUMNA ZAP. (M) COLUMNAS TOTAL (M) (LB / MT) 13% (20')
LX / 1/2" 1.80 0.07 1.66 0.30 1.96 15 29 8.00 232.59 2.20 1.04
LY/ 1/2" 1.40 0.07 1.26 0.30 1.56 12 18 8.00 143.52 2.20 1.18
RECOMENDACIN: Usar Varilla 1/2" de 25 Pies por ser mas facil de obtener ly
RECOMENDACIN: Usar Varilla 1/2" de 30 Pies por ser mas facil de obtener lx
ACERO
TIPO Diametro LONGITUD CANTIDAD RECUBRIM. LONGITUD LONGITUD PESO DESPERDIC. PESO PESO
() (M) (UD) (M) UTIL (M) TOTAL (M) (LB / MT) (20') (LBS) (QQ)
Longit. 3/8" 45.09 3.00 0.04 45.01 135.03 1.25 1.30 219.42 2.19
Cangrejo 3/8" 0.60 226.45 0.04 0.72 163.04 1.25 1.06 215.16 2.15
DESPERDICIO EN CANGREJOS
USANDO VARILLAS DE 20P
Long. Piezas Long 20' Long. 8 Diferencia % de
(M) (M) Piezas (M) por varilla Desperdicio
0.72 6.10 5.76 0.34 1.06
DESPERDICIO EN ACERO LONG. USANDO VARILLAS DE 35P DESPERDICIO EN ESTRIBOS USANDO VARILLAS DE 20P
Long. Piezas Long 30' Long. 2 Diferencia % de Long. Piezas Long 20' Long. 8 Diferencia % de
(M) (M) Piezas (M) por varilla Desperd. (M) (M) Piezas (M) por varilla Desperd.
5.28 10.67 10.56 0.11 1.01 0.98 6.10 5.88 0.22 1.04
Usar En Acero Long. Varilla 1/2" de 25 Pies Usar En Estribos Varilla 3/8" de 20 Pies
ANALISIS DE COSTO PRECIO UNITARIO (P.U)
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
TOTAL DE QQS. 15.18 ALAMBRE (2LBS. X QQ) 30.36715 LBS CUANTIA DE ACERO 1.449737094 X M3
TOTAL DE QQS. 3.31 ALAMBRE (2LBS. X QQ) 6.612508 LBS CUANTIA DE ACERO 3.683438057 X M3
DESPERDICIO EN ESTRIBOS USANDO VARILLAS DE 20P
Long. Piezas Long 20' Long. 8 Diferencia % de
(M) (M) Piezas (M) por varilla Desperd.
0.74 6.10 5.92 0.18 1.03
Usar En Estribos Varilla 3/8" de 20 Pies
ANALISIS DE COSTO PRECIO UNITARIO (P.U)
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 Hormigon 1:2:4 A Mano 0.90 M3 3,925.60 3,523.62
2 Acero estructural de 1/2" 3.31 QQ 2,000.00 6,612.51
3 Alambre dulce #18 (2lbs. * QQ) 6.61 LB 25.00 165.31
4 M. de Obra Carpinteria (Todo Costo) 20.40 M 250.00 5,100.00
5 Mano de Obra Acero 20.40 M 250.00 5,100.00
SUBTOTAL 20,501.44
COSTO POR M3 RD$ 22,840.28
25
TOTAL DE QQS. 4.08 ALAMBRE (2LBS. X QQ) 8.15637467 LBS CUANTIA DE ACERO 3.131286343 X M3
DESPERDICIO EN ESTRIBOS USANDO VARILLAS DE 20P
Long. Piezas Long 20' Long. 8 Diferencia % de
(M) (M) Piezas (M) por varilla Desperd.
0.74 6.10 5.92 0.18 1.03
Usar En Estribos Varilla 3/8" de 20 Pies
ANALISIS DE COSTO PRECIO UNITARIO (P.U)
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 Hormigon 1:2:4 A Mano 1.30 M3 3,925.60 5,112.70
2 Acero estructural de 1/2" 4.08 QQ 2,000.00 8,156.37
3 Alambre dulce #18 (2lbs. * QQ) 8.16 LB 25.00 203.91
4 M. de Obra Carpinteria (Todo Costo) 29.60 M 250.00 7,400.00
5 Mano de Obra Acero 29.60 M 250.00 7,400.00
SUBTOTAL 28,272.99
COSTO POR M3 RD$ 21,708.37
27
TOTAL DE QQS. 10.38 ALAMBRE (2LBS. X QQ) 20.7608384 LBS CUANTIA DE ACERO 3.168626129 X M3
DESPERDICIO EN ESTRIBOS USANDO VARILLAS DE 20P
Long. Piezas Long 20' Long. 6 Diferencia % de 36.57
(M) (M) Piezas (M) por varilla Desperd. 0.7656549084
1.28 6.10 5.12 0.98 1.16 0.2343450916
Usar En Estribos Varilla 3/8" de 20 Pies
ANALISIS DE COSTO PRECIO UNITARIO (P.U)
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 Hormigon Industrial 210 kg/cm2 3.28 M3 4,800.00 15,724.80
2 Acero estructural de 1/2" 10.38 QQ 2,000.00 20,760.84
3 Alambre dulce #18 (2lbs. * QQ) 20.76 LB 25.00 519.02
4 M. de Obra Carpinteria (Todo Costo) 28.00 M 350.00 9,800.00
5 Mano de Obra Acero 28.00 M 250.00 7,000.00
SUBTOTAL 53,804.66
COSTO POR M3 RD$ 16,423.89
29
LOSA PLANA
4.9 H. A. EN LOSA PLANA 3/8" @0.12 Y @ 0.25M G40/ HORM. 210 KG
DESPERDICIO AX1 USANDO VARILLAS DE 35P DESPERDICIO AX2 USANDO VARILLAS DE 35P
Long. Piezas Long 35' X 2 Long. Diferencia % de Long. Piezas Long 20' Long. 1 Diferencia % de
(M) (M) Piezas (M) por varilla Desperd. (M) (M) Piezas (M) por varilla Desperd.
9.79 10.67 9.79 0.88 1.08 10.29 10.67 10.29 0.38 1.04
DESPERDICIO AY1 USANDO VARILLAS DE 25P DESPERDICIO AY2 USANDO VARILLAS DE 25P
Long. Piezas Long 30' X 4 Long. 1 Diferencia % de Long. Piezas Long 30' X 4 Long. 1 Diferencia % de
(M) (M) Piezas (M) por varilla Desperd. (M) (M) Piezas (M) por varilla Desperd.
36.79 42.68 36.79 5.89 1.14 37.29 42.68 37.29 5.39 1.13
TOTAL DE QQS. 74.81 ALAMBRE (2LBS. X QQ) 149.61743 LBS CUANTIA DE ACERO 1.4094602961 X M3 31
32
ANALISIS DE COSTO PRECIO UNITARIO (P.U)
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 Hormigon Industrial 210 KG 53.08 M3 4,800.00 254,765.48
2 Acero estructural de 3/8" 74.81 QQ 1,600.00 119,693.94
3 Alambre dulce #18 (2lbs. * QQ) 149.62 LB 25.00 3,740.44
4 M. de Obra Carpinteria (Todo Costo) 343.53 M 235.00 80,730.70
5 Mano de Obra Acero 74.81 QQ 300.00 22,442.61
SUBTOTAL 481,373.18
COSTO POR M3 RD$ 9,069.48
DIMENSIONES EXTERNAS LOSA DESPERD. VOL. BRUTO VOL. UTIL AREA LOSA DIMENSIONES INTERNAS LOSA DIMENSIONES COLOC. BOV.
LX (M) LY (M) H BRUTA (M) 10% (M3) (M3) (M2) LX (M) LY (M) AREA (M2) LX (M) LY (M)
7.48 7.19 0.20 1.10 11.831864 9.13 53.7812 6.88 6.59 45.3392 5.68 5.39
DIMENSIONES DE BOVEDILLAS AREA DE AREA DE BOVEDILLA AREA COLOC. ANCHO DE NERVIOS 0.15 M
BASE (M) ALTURA (M) H BRUTA (M) BOVED. (M2) CON NERVIOS (M2) BOVED. (M2) ALTURA NERVIOS 0.15 M
0.50 0.50 0.15 0.25 0.43 30.6152 ANCHO DE ABACO 0.60 M
LONGITUD ABACO 24.54 M
CALCULO PARA BOVEDILLAS CANTIDAD DE NERVIOS ASX1 8.00 UD
LX INTERNA LY INTERNA AREA BRUTA AREA UTIL CANTIDAD VOLUMEN DE CANTIDAD DE NERVIOS ASY1 8.00 UD
(M) (M) (M2) (M2) BOVEDILLAS BOVED. (M3) LONGITUD NERVIOS ASX 7.48 M
6.88 6.59 45.34 18.01 72.04 2.70 LONITUD NERVIOS ASY 7.19 M
ANCHO DE VIGAS 0.30 M
1/4 LX INTERNA 1.72 M
1/4 LY INTERNA 1.65 M
5. BLOQUES
5.1 Colocacion de Bloques 8" en Muros BNP / 3/8" @ 0.40 33
DIMENSIONES HUECOS
Longitud Longitud Longitud Altura Area Exteriores Interiores Area Area Neta Bloques Cantidad
Muros Ext. Muros Int. Total Muros Bruta Huecos Muros por M2 Bloques
mt. mt. mt. mt. m2 m2 m2 m2 m2 Ud Ud
0.00 47.81 47.81 0.84 40.16 0.00 0.00 0.00 40.16 13.00 574.29
DESPERDICIO 1.10
OTRAS AREAS 0 M2 AREA TOTAL 40.16 M2
ANALISIS DE COSTO PRECIO UNITARIO (P.U) 1.00 M2
34
5.2 Colocacion de Bloques 8" en Muros SNP / 3/8" @ 0.40 Y Serpentina 3/8" cada 3 hileras (0.60 mts.) 35
DIMENSIONES HUECOS
Longitud Longitud Longitud Altura Area Exteriores Interiores Area Area Neta Bloques Cantidad
Muros Ext. Muros Int. Total Muros Bruta Huecos Muros por M2 Bloques
mt. mt. mt. mt. m2 m2 m2 m2 m2 Ud Ud
0.00 47.81 47.81 2.85 136.26 0.00 0.00 0.00 136.26 13.00 1,948.50
DESPERDICIO 1.10
OTRAS AREAS 0 M2 AREA NETA TOTAL 149.88 M2
ANALISIS DE COSTO PRECIO UNITARIO (P.U) 1.00 M2
BLOQUES 8" SNP / 3/8" @ 0.40 M. CON SERPENTINAS 2 3/8" CADA 3 HILERAS 1.00 M2
36
5.3 Colocacion de Bloques 6" en Muros SNP / 3/8" @ 0.40 Y Serpentina 3/8" cada 3 hileras (0.60 mts.) 37
DIMENSIONES HUECOS
Longitud Longitud Longitud Altura Area Exteriores Interiores Area Area Neta Bloques Cantidad
Muros Ext. Muros Int. Total Muros Bruta Huecos Muros por M2 Bloques
mt. mt. mt. mt. m2 m2 m2 m2 m2 Ud Ud
60.45 24.00 84.45 2.85 240.68 46.08 34.56 80.64 160.04 13.00 2,288.61
DESPERDICIO 1.10
OTRAS AREAS 0 M2 AREA NETA TOTAL 176.05 M2
ANALISIS DE COSTO PRECIO UNITARIO (P.U) 1.00 M2
BLOQUES 6" SNP / 3/8" @ 0.40 M. CON SERPENTINAS 2 3/8" CADA 3 HILERAS 1.00 M2
38
6. TERMINACION DE SUPERFICIES 39
6.1 FRAGUACHE DE TECHOS (CARETEO) / 1.55 mm ESPESOR / MORTERO 1:4
41
SUBTOTAL DE EMPAETE / TECHOS RD$ 82,887.29
43
SUBTOTAL DE EMPAETE INTERIOR RD$ 78,158.29
6.6 CANTOS 47
LONGITUD DE CANTOS 596.00 MT.
7 . PISOS 48
7.1 TORTA DE PISO PARA BASE DE MOSAICO/ HORMIGON 1:3:5 A MANO
51
53
ANALISIS DE COSTO PRECIO UNITARIO (P.U) 1.00 M
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 Mortero 1:10. + 20% desp. 0.00 m3 3,392.88 4.99
2 Baldosas + transporte + 10% desp. 1.10 m2 550.00 605.00
3 Lechada cemento bco. + 10% desp. 0.03 Fda. 700.00 23.10
4 Estopa (1 lb. / 20 m2) 0.05 lb 60.00 3.00
5 Colocacin 1.00 m 65.00 65.00
701.09
8 . REVESTIMIENTOS / PAREDES 54
8.1 Colocacion de Ceramica de Paredes en Baos
Espesor Aproximado / Mortero Coloc. 0.02 MT Cantidad de Mortero 1:3 + 5 % Desperdicio 0.021 M3 X M2
55
D ANALISIS DE PRESUPUESTOS
DAMIAN ROMERO PAG. NO. 1
ARQUITECTO PROYECTO: EDIFICIO APARTAMENTOS / 4 NIVELES / 8 UDS.
PROPIETARIO:
1 ER. NIVEL AREA BRUTA ESTIMADA 918.84 M2 Mayo / 2013
UBICACION:
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR SUBTOTAL
UNITARIO ($) ($) ($)
1 PRELIMINARES
1.1 Limpieza y Acondicionamiento del terreno 512.34 M2 4.88 2,500.22
1.2 Caseta de materiales 1.00 UD $18,245.68 18,245.68
20,745.90
2 REPLANTEO
2.1 Confeccion de Charrancha 98.96 M 97.91 9,689.12
9,689.12
3 MOVIMIENTO DE TIERRA
3.1 Excavacion Caliche a mano hasta 3.0 mt. Profundidad 37.73 M3 700.00 26,412.75
3.2 Relleno Compactado Interior 73.79 M3 615.00 45,379.39
71,792.14
4 HORMIGON ARMADO EN
4.1 Zapata de Columna 1.2 x .1.20 x 0.35 mt./ 12 . 1/2"/ Horm. 210 Kg 10.58 M3 14,009.33 148,274.78
4.2 Zapata de Muro 8" /3 3/8" + 3/8" @ 0.20 mt./ Horm. 210 Kg 8.36 M3 7,006.21 58,569.70
4.3 Columna C1 .20 x .20m./ 4 . 1/2" y 3/8" @ .20m / 1:2:4 A Mano 0.90 M3 16,464.84 14,736.85
4.4 Viga de Amarre .20 x .20m./ 4 . 1/2" y 3/8" @ .15m / 1:2:4 A Mano 10.47 M3 14,510.51 151,973.31
4.5 Dinteles .20 x .50m / 3 . 1/2" + 2 . 3/8" y 3/8" @ .15 / Horm.. 210 kg 0.90 M3 22,840.28 20,501.44
4.6 Dinteles .20 x .20m / 2 . 1/2" + 2 . 3/8" y 3/8" @ .15 / 1:2:4 A Mano 1.30 M3 21,708.37 28,272.99
4.7 Vigas .20 x .32 m./ 2 3/4" y 3/8" @ .13 / Horm. 210 Kg 3.28 M3 16,423.89 53,804.66
4.8 Rampa de Escalera 1.51 M3 24,538.00 37,052.38
4.9 Losas Planas / h=0.12m. / 3/8"@ .12m y 3/8" @ .25m./ Horm. 210 Kg 51.53 M3 9,069.48 467,352.60
980,538.71
ANALISIS DE COSTOS DE EDIFICACION
DAMIAN ROMERO PAG. NO. 2
ARQUITECTO PROYECTO: EDIFICIO APARTAMENTOS / 4 NIVELES / 8 UDS.
PROPIETARIO:
1 ER. NIVEL AREA BRUTA ESTIMADA M2 Mayo / 2013
UBICACION:
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR SUBTOTAL
UNITARIO ($) ($) ($)
5 BLOQUES
5.1 Colocacion de Bloques 8" BNP / 3/8" @ .20M. 40.16 M2 1,152.46 46,283.16
5.2 Colocacion de Bloques 8" SNP / 3/8" @ .40M. 149.88 M2 1,061.22 159,060.29
5.2 Colocacion de Bloques 6" SNP / 3/8" @ .40M. 176.05 M2 931.66 164,015.37
369,358.82
6 TERMINACION DE SUPERFICIES
6.1 Fraguache de Vigas, Columnas y Techos 266.01 M2 37.25 9,909.92
6.2 Empaete de Techos con Andamios 260.73 M2 317.90 82,887.29
6.3 Empaete Liso Interior 311.81 M2 250.66 78,158.29
6.4 Empaete Liso Exterior 158.14 M2 319.08 50,458.98
6.5 Mochetas / A= .20 m. 204.60 M 62.75 12,839.43
6.6 Cantos 596.00 M 45.00 26,820.00
6.7 Goteros Colgantes en vuelos 42.75 M 101.55 4,341.11
265,415.02
7 PISOS Y ZOCALOS
7.1 Torta de Piso en Hormigon Simple 235.20 M2 445.67 104,818.89
7.2 Colocacion Piso Ceramica Importada 45 x 45 235.20 M2 1,016.37 239,045.60
7.3 Zocalo de Ceramica Importada 87.00 M 701.09 60,994.62
7.4 Piso de Hormigon Armado M2 0.00
404,859.10
8 REVESTIMIENTO DE PAREDES
8.2 Ceramica Importada en Baos 95.94 M2 866.28 83,111.05
83,111.05
COSTOS INDIRECTOS
ZAPATA DE COLUMNA
DIMENSIONES DESPERDIC. VOLUMEN CANTIDAD VOLUMEN
LX (M) LY (M) ALTURA (M) POR UD (M3) COLUMNAS TOTAL (M3
1.40 1.80 0.50 1.05 1.32 8.00 10.58
LONGITUD DE GANCHOS 0.25 M
ACERO
TIPO TAMAO RECUBRIM. LONGITUD GANCHOS LONGITUD # PIEZAS LONG. POR CANTIDAD LONGITUD PESO DESPERDIC.
(M) (M) (M) (M) GANCH. (M) COLUMNA ZAP. (M) COLUMNAS TOTAL (M) (LB / MT) 5% (25')
LX / 3/4" 1.40 0.04 1.32 0.50 1.82 8.00 14.56 8.00 177.60 4.92 1.04
LY/ 3/4" 1.80 0.04 1.72 0.50 2.22 10.00 22.20 8.00 177.60 4.92 1.04
DESPERDICIO EN CANGREJOS
USANDO VARILLAS DE 20P
Long. Piezas Long 20' Long. 8 Diferencia % de
(M) (M) Piezas (M) por varilla Desperdicio
0.61 6.10 4.88 1.22 1.20
TOTAL DE QQS. 46.97 ALAMBRE (2LBS. X QQ) 93.942 LBS CUANTIA DE ACERO 4.873016
DESPERDICIO EN ACERO LONG. USANDO VARILLAS DE 25P DESPERDICIO EN ESTRIBOS USANDO VARILLAS DE 20P
Long. Piezas Long 25' Long. 2 Diferencia % de Long. Piezas Long 20' Long. 8 Diferencia % de
(M) (M) Piezas (M) por varilla Desperd. (M) (M) Piezas (M) por varilla Desperd.
4.43 7.62 8.86 1.24 1.16 2.36 6.10 18.88 -12.78 -1.10
Usar En Acero Long. Varilla 1/2" de 25 Pies Usar En Estribos Varilla 3/8" de 20 Pies
ANALISIS DE COSTO PRECIO UNITARIO (P.U)
NO. DESCRIPCION CANTIDAD UD PRECIO VALOR ($)
UNITARIO ($)
1 Hormigon 210 KG/CM2 9.64 M3 4,500.00 43,375.50
2 Acero estructural de 1/2" 46.97 QQ 2,000.00 93,942.00
3 Alambre dulce #18 (2lbs. * QQ) 93.94 LB 25.00 2,348.55
4 M. de Obra Carpinteria (Todo Costo) 146.88 M 375.00 55,080.00
5 Mano de Obra Acero 61.20 M 225.00 13,770.00
6 Cepos para Columnas 17.00 UD 900.00 15,300.00
SUBTOTAL 223,816.04
COSTO POR M3 RD$ 23,219.84
0.49004054
1.22134733
0.49004054
40p