Contents
1 General ......................................................................................................................................... 5
1.1 Safety instructions ............................................................................................................... 5
1.2 Specified application ........................................................................................................... 5
2 Design ....................................................................................................................................... 6
3 Shipment ................................................................................................................................... 6
NOTE
Data contained herein may differ in details from the tap-changing equipment delivered.
We reserve the right to make alterations without notice.
119/06 EN 3
Contents
10 Mounting the motor drive unit, the bevel gear and the drive shaft ...................................... 21
10.1 Mounting the motor drive unit ........................................................................................... 21
10.2 Mounting the bevel gear ................................................................................................... 21
10.3 Mounting the drive shaft (square tube) ............................................................................. 21
11 Putting the on-load tap-changer into operation at the transformer factory ........................ 22
11.1 Operational tests .............................................................................................................. 22
11.2 Final oil filling .................................................................................................................. 22
11.3 Ground connections ......................................................................................................... 23
11.4 Electrical transformer tests ............................................................................................... 23
15 Inspections ............................................................................................................................... 26
16 Appendix ................................................................................................................................... 28
4 119/06 EN
1
General
1 General
1.1 Safety instructions 1.2 Specified application
NOTE
119/06 EN 5
2 Design
3 Shipment
2 Design 3 SHIPMENT
The on-load tap-changer (OLTC) consists of the diver- On-load tap-changer and motor drive are shipped in the
ter switch with the tap selector mounted below (fig. 1). adjustment position. The on-load tap-changer is packed
in two parts, diverter switch and tap selector, and is well
The diverter switch is installed in its own oil compart-
protected against moisture. Both the diverter switch and
ment.
the tap selector are blocked in the adjustment position.
The on-load tap-changer is attached to the transformer
The tap-changing equipment is shipped as follows:
cover by means of the tap-changer head.
Diverter switch oil compartment with tap-changer head
If required, the tap selector may be equipped with a
and diverter switch unit (max. weight approx. 210 kg),
change-over selector.
fig. 2.
The change-over selector of all type R OLTCs is
Tap selector (max. weight approx. 270 kg), fig. 3.
laterally attached to the fine tap selector.
Motor drive unit ED-S (approx. 80 kg) fig. 4.
OLTC models without change-over selector are avail-
able for max. 18, and with change-over selector for Drive shaft with coupling parts and bevel gear (max.
max. 35 operating positions. weight approx. 20 kg), fig. 5.
The design of the on-load tap-changer and the designa- Protective relay RS 2001(weight 3.5 kg), fig. 6.
tion of its main parts are shown in the installation draw- Check shipment against documents.
ing 896 705 in the appendix. Store all parts in a dry place until installation.
These Operating Instructions contain all information The tap-changer parts must be left wrapped in their
regarding installation and operation of the following airtight cover, unwrap just before installation.
OLTC standard models, which are available with and
without change-over selector.
Three-phase OLTC:
R III 1200 (see fig. 1)
Single-phase OLTC:
R I 2000/2002/2402, R I 3000/3600.
All single-phase OLTCs are also available as a group
3 x R I 2002/2402 or
3 x R I 3000/3600
with a common motor drive. A
V2 W1
3 1
U1
4 2
U21
3 1
V1
4 2
V2
3 1
W1
4 2
W2
1 KHW 1086-4
6 119/06 EN
3
Shipment
NOTE
4 KHW 915-4
MR
V2 W1
2 KHW 1087-4
5 KHW 766-4
MR
3 1
4 2
3 1
4 2
3 1
4 2
119/06 EN 7
4
Installation of the on-load tap-changer for cover attachment
25
should meet the requirements of the tap-changer head
45
gasket surface (see fig. 7, and section 16, drawing
15
896 705).
To position the thread studs (M12, max. length = 45 mm)
we recommend the use of a drilling template (see
fig. 8 and section 16, dwg. 890 183). If requested, the
drilling template will be supplied without charge with the
15
0
first on-load tap-changer type R. 74
710
7,5
15
4.2 Attachment of the tap-changer
65
0
head to the transformer cover
The diverter switch oil compartment is lowered through
the cover aperture (= mounting flange) of the trans- 7 KHW 770-4
former. The tap-changer head is attached to the mount-
ing flange by means of bolts.
7,5
Then, the tap selector is fastened to the diverter switch
15
oil compartment (see section 4.3). 24
x1
5
=3
5
Proceed as follows: 60
0
0
74
2. Clean sealing surfaces of mounting flange and tap- 71
changer head.
650
3. Put an oil-proof gasket on the mounting flange of
60
20
NOTE
8 119/06 EN
4
Installation of the on-load tap-changer for cover attachment
NOTE
10 KHW 1098-4
rh-1098-4-0/1
1500
11 KHW 1102-4
119/06 EN 9
4
Installation of the on-load tap-changer for cover attachment
CAUTION
1V1 1V2
14 KHW 1088-4
3 4
10 119/06 EN
5
Installation of the on-load tap-changer into the bell-type tank
To install the on-load tap-changer into a transformer Lift the assembled on-load tap-changer, according to
with bell-type tank the on-load tap-changer must be section 4.1, into the supporting structure. Make sure
mounted onto a supporting structure. that the on-load tap-changer is in proper mounting
For this purpose, the OLTC is equipped with a sup- position and fasten it there safely.
porting flange at the diverter switch oil compartment
(= special design, section 16, dwg. 896 762).
Firstly, lift the on-load tap-changer into the supporting NOTE
structure and connect it to the tap winding. The OLTC
must be attached to the supporting structure in such a In the supporting structure the on-load tap-changer
way that it cannot be displaced. The supporting flange must be in an exactly vertical position. The on-load
is provided with through-holes which allow it to be fixed tap-changer must be mounted to the supporting
to the supporting structure. It is advisable to put spacer structure ensuring that it need not be lifted by more
blocks temporarily between supporting structure and than 5 to 20 mm to reach its final position after the
supporting flange and to remove them before the bell- bell-type cover is set up.
type cover is set up.
Once the bell-type cover is attached, lift the on-load tap- It is of advantage to install spacer blocks between
changer (with the diverter switch unit removed) by supporting structure and supporting flange in such a
means of the lifting traverse (see section 16, drawing way that the on-load tap-changer is in its final position
890 180) and fix it to the bell-type cover together with after the bell-type cover is set up. This measure helps
the top part of the head. to cut the tap leads to their correct lengths. Remove the
To attach the tap-changer head to the bell-type cover, spacer blocks after the leads have been connected.
we recommend using a mounting flange as described in To connect the tap winding and the tap-changer take-off
section 4.1. terminal follow the instructions according to section 6.
119/06 EN 11
5
Installation of the on-load tap-changer into the bell-type tank
5.3 Preparations
18 KHW 1103-4
rh-1103-4-0/1
16 KHW 762-4
19 KHW 1105-4
rh-1105-4-0/1
12 119/06 EN
5
Installation of the on-load tap-changer into the bell-type tank
21 KHW 1106-4
22 KHW 1110-4
rh-1110-4-0/1
20 KHWrh-1109-4-0/1
1109-4 23 KHW 1107-4
rh-1107-4-0/1
119/06 EN 13
5
Installation of the on-load tap-changer into the bell-type tank
CAUTION
24 KHW 1100-4
25 KHW 1108-4
14 119/06 EN
5
Installation of the on-load tap-changer into the bell-type tank
27 KHW 1101-4
rh-1101-4-0/1
28 KHW 1104-4
rh-1104-4-0/1
119/06 EN 15
6
Connection of tap winding and tap-changer take-off leads
CAUTION
3 1
expansion loops.
4 2
B10
31 KHW 1089-4
rh-1089-4-0/1
16 119/06 EN
6
Connection of tap winding and tap-changer take-off leads
34 KHW 1094-4
rh-1094-4-0/1
3 4
32 KHW 1099-4 35
rh-1099-4-0/1 KHW 1095-4
119/06 EN 17
7 Transformer ratio test
8 Drying procedure and filling with oil
We recommend to ratio-meter the transformer with a The dielectric properties of the on-load tap-changer can
low AC voltage before drying. only be guaranteed, if the on-load tap-changer is sub-
jected to a drying treatment according to the following
To operate the drive shaft in the tap-changer head a
instructions (8.1.1 or 8.1.2).
short tube of nominal width 25 mm with an insert
coupling bolt of 12 mm dia. together with a hand wheel
or a hand crank may be used. 8.1.1 Vacuum-drying process
In case of OLTC set 3 x R I 2002 ... 3600 all three tap- 8.1.1.1 Drying in the autoclave
changer heads have to be coupled by the horizontal
drive shafts (see section 10).
NOTE
When using an ED, 16.5 drive shaft revolutions of the
tap-changer drive shaft are required for one tap-change
operation. The diverter switch action can be heard When drying the transformer in the autoclave remove
distinctly. the tap-changer cover and store it outside the vacuum
autoclave.
To operate the change-over selector a higher torque is
necessary.
Heating up
The end positions shown on the connection diagram the on-load tap-changer in air of atmospheric
supplied with the delivery must never be overrun. It is pressure with a temperature rise of approx. 10 C/
therefore necessary to check the operating position hour to a final temperature of at most 110 C.
through the inspection glass in the tap-changer head
Preparatory drying
cover (fig. 36). Keep the number of tap-change opera-
in circulating air at 110 C max. applied to the on-
tions to a minimum as long as the on-load tap-changer
load tap-changer for a duration of 20 hours.
has not been immersed in oil. After the transformer ratio
test the on-load tap-changer has to be set back to the Vacuum drying
adjustment position in which it was delivered by MR. at a temperature of 110 C max. applied to the on-
The position is indicated in the connection diagram load tap-changer and a residual pressure of at most
delivered with the equipment. 10-3 bar for a duration of at least 50 hours.
18 119/06 EN
8
Drying procedure and filling with oil
NOTE NOTE
Before starting the drying procedure, open the When drying in the autoclave remove the tap-changer
kerosene drain plug (fig. 37) to drain the condensate head cover first and store it outside the vacuum
from the oil compartment. autoclave.
8 mm
8.1.3 Operating the OLTC
CAUTION
8 mm
The on-load tap-changer must not be operated before
the diverter switch oil compartment has been filled with
Coating oil and the tap selector has been completely immersed
37 KHW 831-4 in the transformer oil.
119/06 EN 19
8 Drying procedure and filling with oil
9 Pipe connections
9 Pipe connections
8.2 Filling with oil
20 119/06 EN
10
Mounting the motor drive unit, the bevel gear and the drive shaft
39 KHW 767-4
119/06 EN 21
10 Mounting the motor drive unit, the bevel gear and the drive shaft
11 Putting the OLTC into operation in the transformer factory
OLTCs 3 x R I 2002 ... 3600 Before applying voltage to the transformer check the
mechanical operation of on-load tap-changer and motor
The following procedure is also recommended for
drive.
OLTC R III 1200.
For these test operations the on-load tap-changer has
Due to the special arrangement of the tap-changer
to be run through the complete operating cycle.
phases in three columns, the horizontal drive shaft must
be mounted between the three tap-changer heads Make sure that in each operating position the indi-
above the tank cover. Since a swivelling of the upper cators of motor drive and on-load tap-changer (tap-
gear unit will initiate a switching action, make sure that changer head) read the same position.
the adjustment position of the diverter switch is re-
gained after the alignment of the gear units.
For this purpose proceed as follows: CAUTION
1. Check that the operating positions of all columns Misalignment between on-load tap-changer and
are identical (tap-changer head, inspection win motor drive unit exists, if on-load tap-changer and
dow). Each one of the one-phase OLTCs must be motor drive unit show different operating positions.
in the adjustment position. Misalignment of coupling between on-load tap-
2. Turn the upper gear unit of the tap-changer heads changer and motor drive unit leads to severe damage
into the desired installation position and fix them of on-load tap-changer and transformer, if operation
there (tighten thrust collars and tab-lock the is continued. The transformer must not be taken in
screws). operation.
Take note of the arrow on the drive shaft flange
Make sure that in both end positions the electrical and
below the punched serial number. The direction of
mechanical limit stops function automatically (see
the arrow indicates the rotation sense when crank-
Operating Instructions No. 138 for ED).
ing the motor drive clockwise and must be identical
on all gear units.
3. Operate the tap-changer poles separately by one
step by rotating the trunnions counter-clockwise 11.2 Final oil filling
until the diverter switch operates once.
Check coincidence of operating positions of all Fill up the on-load tap-changer completely with trans-
tap-changer heads. former oil via the oil conservator and evacuate.
4. Mount the horizontal drive shaft between the tap- Bleed the tap-changer head via the bleeder valve in
changer heads. the head cover (E1):
Remove screw cap M30/w.s. 36 (fig. 40), lift valve
5. Return the OLTC set, that is all tap-changer tappet by means of a screw driver.
poles together, into the adjustment position.The
adjustment position is reached by turning the drive Bleed the suction pipe (S) via the bleeder screw of
shaft in clockwise direction. the elbow: cap nut M16 (w.s. 22, max. torque 9 Nm),
slotted bleeder screw M6 (max. torque 2 Nm,
Check simultaneous operation of all diverter
fig. 41).
switches.
Check coincidence of position of all tap-
changer heads and the motor drive unit.
6. Mount the vertical drive shaft.
CAUTION CAUTION
The supervisory control must be installed according Make sure that the suction pipe has been bled
to the connection diagram of the relevant motor drive completely. The insulation capability of the on-load
unit. Incorrect installation will cause damage of both tap-changer to ground is otherwise significally
on-load tap-changer and transformer in case of impaired.
malfunction.
22 119/06 EN
11
Putting the OLTC into operation in the transformer factory
40 KHW 773-4
41 KHW 811-4
42 KHW 811-4
119/06 EN 23
12 Transport to the operating site
13 Putting into service at the operating site
If the transformer is to be transported without the motor Before putting the transformer into service, operational
drive unit, set the motor drive to the adjustment position tests of on-load tap-changer and motor drive have to be
and uncouple. performed according to section 11.1. At the same time
check the function of the protective relay. Loop in
signaling contact for undershooting the minimum oil
CAUTION level in the on-load tap-changer oil conservator in the
on-load tap-changer tripping circuit.
Do not operate the motor drive unit while the on-load
tap-changer is uncoupled.
NOTE
To remount the motor drive unit follow the instructions
according to section 10.1 and 10.3. The protective relay has to be inserted into the trip-
ping circuit of the circuit breakers so that energiza-
tion of the protective relay switches off the trans-
former immediately (see Operating Instructions
NOTE No. 59 for protective relay RS 2001).
24 119/06 EN
Supervision during service, failures 14
WARNING
119/06 EN 25
15
Inspections
15 Inspections
NOTE
26 119/06 EN
15
Inspections
CAUTION
Standard values for oil testing according to CIGRE report 12-13 (1982) applying to transformer oil at service
temperature:
First inspection and further inspections: after 7 years or the number of operations indicated in Table II, depending on
what is reached first.
119/06 EN 27
15 Inspections
16 Appendix
Table III Inspection intervals for one-phase OLTCs type R with Um 245 kV and used in autotransformers
or for the regulation at line end of winding of the transformer.
First inspection: after 2 years or 20,000 operations, depending on what is reached first.
Next inspections: without MR filter plant after every 4 years, with MR filter plant (combination filter) after
every 6 years or the number of operations indicated in table III whatever is reached first.
16 APPENDIX
28 119/06 EN
16
Appendix
Flat
surface
Protective
relay
Take-off
terminal
119/06 EN 29
16
Appendix
30 119/06 EN
16
Appendix
width of
gasket
Detail at A
Connection flange
for Q, S, R
16
Thickness
119/06 EN 31
16
Appendix
3 thick
Marks to be pounded
32 119/06 EN
16
Appendix
Lifting device
O-Ring 44.2 - 5.7
Suction pipe
Transformer cover
Gasket
Level traverse
Supporting flange
Level traverse
Z = Guiding pin
119/06 EN 33
16
Appendix
Sheet steel
St 37-2 DIN 17 100
34 119/06 EN
16
Appendix
119/06 EN 35
16
Appendix
Cable gland
Inspection PG 16
window
Identification label
Gasket
Gasket
The arrow must always point towards the oil pipe leading Plan view of test push buttons
to the oil conservator of the transformer. (cover removed)
Key of variants
Contact positions
Variant Relay designation1) Reed Arrangement of terminals Design
contact In service Off
0.65 - NO
Standard design
1 1.2 - NO A
3.0 - NO
4.8 - NO
0.65 - NC
2 1.2 - NC B
3.0 - NC
4.8 - NC
0.65 - CO
3 1.2 - CO C
3.0 - CO
Special design against surcharge
4.8 - CO
0.65 - 2NO
4 1.2 - 2NO 2A
3.0 - 2NO
4.8 - 2NO
0.65 - 2NC
5 1.2 - 2NC 2B
3.0 - 2NC
4.8 - 2NC
0.65 - NO + NC
6 1.2 - NO + NC 1A &1B
3.0 - NO + NC
4.8 - NO + NC
1)
NO - normally open, NC - normally closed, CO - change-over contact
The protective relay is to be connected in such a way that if it is energized, the power transformer is switched off immediately by the corresponding
circuit breakers.
36 119/06 EN
16
Appendix
Vertical guard
plate with
spacing ring Handcrank
Attachment of
protective housing
The cover can be opened
to the left or to the right
depending on the arrange-
ment of the hinge pins.
ca. 690 if opened 130
ca. 864 if opened 180
Aperture of fixing holes on protective housing Aperture in protective housing for cables
(rear view) (underside view)
119/06 EN 37
16
Appendix
Attachment of protective
housing
Aperture of fixing holes on protective housing Aperture in protective housing for cables
(rear view) (underside view)
38 119/06 EN
16
Appendix
119/06 EN 39
Maschinenfabrik Reinhausen GmbH Telefon: (+49) 9 41 / 40 90-0
Postfach 12 03 60 Telefax: (+49) 9 41 / 40 90-111
www.reinhausen.com
D-93025 Regensburg Telex: 65881