Yajun Li*
Boil-Off Gas Two-Stage Compression
Mingyang Wen
and Recondensation Process at a Liquefied
Natural Gas Receiving Terminal
Due to ship unloading and the change of downstream gas consumption, the boil-
off gas (BOG) and liquefied natural gas outputs fluctuate constantly, causing diffi-
culties in both the design and operation of the BOG handling process. The high
energy consumption, instability, and inflexibility of the original process affect the
operation cost and running safety of the terminal to a large extent. To address
these problems, a two-stage compression and recondensation process is designed
and optimized, based on the original one. Compared with the original process
through dynamic simulation, the design process has better stability, benefiting
from lower operating pressure and smaller fluctuations of both the pressure and
the liquid level in the recondenser. In addition, the power and BOG emission are
remarkably reduced, which will soon bring great benefit and recovery of invest-
ment cost.
Keywords: Boil-off gas, Dynamic simulation, Energy consumption, Liquefied natural gas,
Two-stage process
Received: December 21, 2015; revised: June 17, 2016; accepted: August 9, 2016
DOI: 10.1002/ceat.201500751
1 Introduction liquid level exceeds the highest limit, this will lead to frequent
vibrations in the system, seriously damaging the equipment
Due to unavoidable heat leakage, the heat released from the and threatening the safety of the LNG receiving terminal.
equipment, and the volume replacement caused by the lique- Therefore, a BOG two-stage compression and recondensa-
fied natural gas (LNG) output, boil-off gas (BOG) is constantly tion process based on making full use of the original process
generated from the LNG storage tank [1]. Affected by climate, was designed to address the problems mentioned above. Then,
seasons, unloading, and various downstream consumers, LNG a dynamic simulation model for the two-stage process was built
and BOG fluctuations always occur in all LNG terminals. Espe- to optimize the operating parameters in order to reduce the
cially in unloading, the amount of BOG would be several times total energy consumption, under the operation principles of
as much as that in non-unloading [2, 3]. Fig. 1 shows the fluc- safety and stability.
tuations of both the LNG output and the BOG in an unloading
day: The BOG decreases with increasing LNG output, and vice
versa. The maximum and minimum LNG outputs are approxi- 2 Problems in the Original Process
mately 780 and 400 t h1, respectively. If there is a carrier of the LNG Receiving Terminal
unloading, the maximum BOG would reach approximately
16.9 t h1, while the minimum is only 5 t h1. As the core equipment in the BOG handling system, the recon-
The BOG handling process uses subcooled LNG to recon- denser is used for BOG liquefaction and as the buffer vessel for
dense the compressed BOG at high pressure. It is the most the high-pressure pump (HP). Compared with the other equip-
complex and important process in LNG receiving terminals, ment, the recondenser has the most complex control system in
the stability of which is heavily affected by the fluctuations of the terminal. The original recondenser control system is shown
both the LNG output and the BOG. For the early constructed in Fig. 2.
LNG receiving terminals (such as the Montoir de Bretagne ter-
minal in France, the Dahej terminal in India, and the Da-Peng
terminal in China), the capacities of the BOG handling systems
are insufficient to deal with the present fluctuations [4, 5]. Prof. Yajun Li, Mingyang Wen
Especially, the recondenser of the Da-Peng terminal in China is liyajun@scut.edu.cn, lutherwen@fox mail.com
too small to handle the existing amount of over 13.38 t h1 of SHAW Engineering Building, South China University of Technology,
BOG. As a result, when the LNG output and BOG fluctuate, it Wushan RD, Tianhe District, Guangzhou 510640, Guangdong Prov-
is difficult to control the liquid level of the recondenser. If the ince, China.
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 19
CAPACITY CONTROL
High Level
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 20
merged so that heat exchange will be greatly reduced. What is Aikhorin et al. [7] have made contributions to the patents of
worse, the recondenser is so small that there is not enough time the recondensation process. Jung et al. [8] studied the effects of
and space for the BOG and subcooled LNG to conduct suffi- BOG handling system operation on the HP, based on BOG pre-
cient heat and mass exchange. Therefore, the BOG cannot be diction under normal operation and unloading. Contreras and
completely recondensed, and part of it flows reversely to the Ferrer [9] performed a dynamic simulation for a Spanish LNG
HP suction tank along the VENT Line. This part of the BOG receiving terminal and verified the reliability of the system.
forces the tank liquid level to drop so that the HP cannot be Shin et al. [10] optimized the compressor operation for energy
completely submerged. Consequently, cavitation occurs and conservation, based on the dynamic performance of the LNG
causes the vibration of the recondensation system. Secondly, storage tank pressure. Lee et al. [11] and Park et al. [12], using
when the LNG output declines and part of the HP are turned dynamic simulation technology, optimized the unloading oper-
off, the LNG from the stopped HP will fill the VENT Line and ation and the LNG recirculation flow rate to reduce the BOG
then go into the horizontal section of the balance vent line. At as well as the system energy consumption. They also suggested
last, mixing flow of two different phases (both LNG and BOG) an energy-efficient concept design of a BOG handling system,
in the VENT Line can cause the system vibration of low fre- which utilizes the LNG cryogenic energy to intercool the BOG
quency. compressor [13]. Li et al. [4] and Li and Chen [14] opti-
With the development of this early constructed terminal in mized the control system of a BOG handling system and
China, the LNG output has increased gradually. However, the then verified the reliability of the proposed control system
problems caused by the limited BOG handling capacity and the through dynamic simulation. However, few designs and opti-
undersized recondenser, such as BOG emission, unstable liquid mizations have been helpful to eliminate the vibration of the
levels, and system vibration, have threatened the operation BOG handling system.
safety. So it is necessary to increase the recondenser volume of
the BOG handling system to eliminate the safety risks and
improve the process reliability. 3.1 Design of the BOG Two-Stage Process
BOG
C1 C2
1-stage 2-stage to pipe line
S2
...
S3 HP
S4
LP
LNG tank
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 21
3.2 Thermodynamics Feasibility Analysis The BOG and LNG output fluctuate frequently. If the BOG
of the BOG Two-Stage Process increases and the LNG output decreases at the same time, the
BOG handling system operation will become more difficult.
Fig. 4 is the pressure-enthalpy chart of the designed two-stage Thus, a maximum BOG rate of 16.9 t h1 and a minimum LNG
process. As shown in the chart, the paths ck and jd represent output of 400 t h1 are taken as the two-stage process design
the first-stage and second-stage BOG compression, respective- conditions, in order to guarantee that the system can run well
ly. Paths ab, il, and ef separately stand for the LNG pressuriza- under any working conditions.
tion through the LP, MP, and HP. The paths fg, hk, and bd According to the operating parameters of the Da-Peng ter-
indicate the regasification in the ORV, the first-stage reconden- minal, the LNG storage tank operating pressure is 16 kPaG and
sation in BR1 and the second-stage recondensation in BR2, the liquid level is 20 m high. The pressure of the output pipe-
respectively. In the BOG enthalpy change process, the com- line network is maintained at 8.99 MPa. In the recondenser, the
pressor energy consumption mostly happens in the first-stage operating pressure and the liquid level are separately set at
compression (path ck), because the flow of BOG in the second- 885 kPa and 3.5 m, to keep it in the best mode. These operating
stage compression (path jd) becomes smaller after the first- parameters will be used in the dynamic simulation models.
stage recondensation. Compared with the original process With increasing BOG, more LNG is required for recondensa-
(path cD), the compressor energy consumption is reduced tion. After being mixed with the condensing LNG, the BOG will
greatly in the two-stage process, because the path kD is con- be liquefied to saturation and then subcooled by the bypass LNG
verted into the path jd, resulting in the decline of both the so that its pressure can guarantee PNPSH = PHP PS 200 kPa
enthalpy change and the BOG flow in compression. The two- to avoid cavitation in the HP [11]. PNPSH is the HP safe net
stage process can reduce the system energy consumption, as it positive suction head (NPSH); PS is the LNG saturation pres-
has a lower recondensing pressure and as BR1 of the process sure. T (K) is the temperature at the pump suction side. PS can
plays a role as an intercooler between C1 and C2. The new BR1 be calculated by the Antoine equation of regression:
not only increases the recondenser volume to eliminate the
safety risks of system vibration, but it is also used as a buffering lnPs 13:6 1012=T (2)
vessel to keep the BR2 operating pressure and HP suction pres-
sure stable. In addition, the MP is placed after BR1, which can In the original process, theoretically, handling 13 t h1 BOG
also reduce the impact caused by fluctuation of both the recon- requires 72.7 t h1 condensing LNG, in order to reach the satu-
densing pressure and the liquid level on the HP. rated temperature of 148.8 K. Then, 17.7 t h1 bypass LNG will
be needed to decrease the temperature to 143.4 K, to ensure the
PNPSH. Totally, 90.4 t h1 LNG is required. However, the practi-
3.3 Operation Feasibility Analysis of the BOG cally required LNG in Da-Peng is actually 167.5 t h1, which
Two-Stage Process greatly deviates from the theoretical value. This is because the
recondenser of the original process is so small that the BOG
Under the current working conditions, it is still unknown fails to contact with the LNG adequately, leading to a decline of
whether the designed BOG two-stage process can meet the sta- heat exchange per unit time and requiring more LNG.
ble operation and other limited conditions, or not. It is neces- If the volume of the recondenser increases, it will contribute
sary to analyze the feasibility of the two-stage process. to increasing the heat exchange efficiency and bringing the
required LNG value closer to the theoretical value,
10 decreasing the demand of required LNG. For this
f g
purpose, the two-stage process with the new added
BR1 is adopted. Theoretically, 118.3 t h1 LNG will
T= -50
T= -10
T= 30
b l e d D
1
4 Parameter Optimization of the
T= -130
BOG Two-Stage Compression
h i j k and Recondensation Process
4.1 Boundary Conditions for Process
Optimization
a c According to Sect. 3, the recondenser operating
0.1
-5200 -5000 -4800 -4600 -4400 -4200 -4000 pressure can be decreased, but there are some
boundary conditions of the process that restrict the
Enthalpy (kJ/kg)
optimization. To keep good efficiency of the HP
Figure 4. P-H chart of the two-stage process. and to reduce the system energy consumption, it is
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 22
suggested to optimize the BR1 operating pressure. With tion to further study and analyze the dynamic performance
decreasing recondenser operating pressure, more LNG is for operation improvement and system optimization. Using
needed for recondensation, as shown in Fig. 5. The figure indi- the Soave-Redlich-Kwong (SRK) thermodynamic package
cates that more than 400 t h1 LNG will be required for recon- [16], the model for the BOG handling system was built and
densation if the recondenser operating pressure is below then the operating parameters were studied through the
390 kPa. Hence, the operating pressure of BR1 actually should dynamic performance of the two-stage process by using the
be higher than 390 kPa. DYNSIM (Invensys Systems, Inc., Lake Forest, CA, USA)
simulation software. Furthermore, the BR1 operating pressure
was optimized.
400
With decreasing operating pressure of BR1, the liquid levels
380
and pressures of the two recondensers showed the dynamic
360
Mass of Required LNG
340
performance as illustrated in Fig. 6. The figure shows that the
320
BR1 operating pressure decreases from 435 to 430 kPa, starting
from 300 s. After about 350 s with a slight fluctuation, the pres-
(t/hr)
300
280
sures and liquid levels of the two recondensers return to a sta-
260
ble value. At last, PMP stays at 465.9 kPa and the MP safe pres-
240
sure stays at 465.3 kPa, which means that there is enough
220
NPSH. At 1500 s, the BR1 operating pressure continues to
200 decrease from 430 to 425 kPa. Although the pressures and liq-
180 uid levels of both recondensers can return to a stable value, the
160 PMP of 460.9 kPa is smaller than the MP safe pressure of
390 400 410 420 430 440 450 460 470 480 490 500 466.5 kPa, which means that there is not enough NPSH to
Operating pressure of BR1 guarantee the long-term operation safety of the MP. Therefore,
(kPa) to maintain the operation safety and to reduce the energy con-
sumption, the operating pressure of the new recondenser
Figure 5. Required LNG versus operating pressure of BR1.
should be set at 430 kPa.
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 23
0 600 1200 1800 2400 cess will fluctuate greatly. The liquid level can
reach 85 % of the recondenser height. This will
435 seriously impair the heat exchange in the
Pressure of BR1
430
original process recovers so slowly that it is
insufficient to meet the greater fluctuations in
425 the future.
5.01
5.2 Dynamic Performance of the BOG
Level of BR1
Two-Stage Process
5.00
(m)
465
output decreases at the same rate, it only takes
57 min to decrease from 780 to 400 t h1. Dur-
460 ing operation, the pressure amplitude is less
than 200 kPa so that it can ensure the safety of
0 600 1200 1800 2400 both the MP and the HP.
Time(s) It is apparent that the dynamic performance
Figure 6. Dynamic performance with decreasing pressure of BR1.
of the two-stage process is much better than
that of the original process. All the fluctuations
in the recondensers can be kept in the safe
Fig. 7 b shows the dynamic performance of the LNG output range, especially eliminating the large fluctuation of the BR2
decrease. The LNG output decreases from 780 to 730 t h1. The liquid level. The process parameters of the recondensers can re-
recondenser pressure can be kept in the safe range. But the turn to the setting values in a short time, which means that the
maximum liquid level is 5.46 m, i.e. 85.3 % of the recondenser system is more flexible and stable.
height. The original process needs 20 min to return to a stable
state.
Obviously, when the LNG output and BOG rate change, the
liquid level and pressure of the recondenser in the original pro-
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 24
Flowrate of BOG 0 600 1200 1800 2400 3000 0 300 600 900 1200 1500 1800 2100
Flowrate of LNG
14 780
12
(t/h)
(t/h)
10 760
8 740
6
4 720
Level of Recondensor Recondensor
Pressure of
920
1000
(kPa)
(kPa)
950 900
900 880
850
800 860
5.5 5.5
5.0 5.0
(m)
(m)
4.5 4.5
4.0 4.0
3.5 3.5
3.0 3.0
0 600 1200 1800 2400 3000 0 300 600 900 1200 1500 1800 2100
Time(s) Time(s)
6 Energy Consumption Comparison consumption of the BOG compressor is reduced by 324 kW,
between the Two-Stage Process which accounts for 25.3 % of the compressor part. What is
more, compared with the BOG handling capacity of the origi-
and the Original Process nal process, the two-stage process increases its capacity from
13.38 to 16.9 t h1 BOG and recovers 3.52 t h1 BOG from the
6.1 Energy Consumption Comparison under emissions in unloading.
the Designed Conditions
The total energy consumption of the BOG handling system 6.2 Energy Consumption Comparison of the LNG
consists of the LP energy consumption (SWLP), the MP energy
Receiving Terminal
consumption (SWMP), the HP energy consumption (SWHP),
and the compressor energy consumption (WC1, WC2). The
The LNG output and BOG are fluctuating all the time in the
energy consumption of the original process (Es1) and the one
LNG receiving terminal, so that the energy consumption of the
of the two-stage process (Es2) are shown as Eqs. (3) and (4),
BOG handling system is also changing with them. Under the
respectively.
conditions of an unloading day as shown in Fig. 1, a remark-
X X able energy-saving effect and BOG emission reduction achieved
Es1 WLP WHP WC1 (3)
by the two-stage process can be noticed in Fig. 10. It shows that
the energy consumption of the two-stage process is always less
X X X than that of the original process, on account of the decline of
Es2 WLP WHP WMP WC1 WC2 (4) the BOG compressor energy consumption. Therefore, the larg-
er the BOG handling amount, the larger is the energy conserva-
The energy consumption comparison between the two pro- tion of the two-stage process. In the figure, the area under the
cesses under the designed working conditions is shown in curve represents the total energy consumption of the process
Tab. 1. Clearly, the two-stage process can save remarkable during an unloading day. The area between two curves stands
amounts of energy. The total energy consumption of the origi- for the amount of energy conservation achieved by the two-
nal process is 4450 kW while that of the two-stage process is stage process. In an unloading day, 2645 kWh is saved in the
4175 kW. When using the two-stage process, 275 kW is saved, unloading operation (4:0017:00 h) and 458 kWh is saved in
making up 6.2 % of the total energy consumption. The energy the non-unloading operation (1:003:00 h and 18:0024:00 h)
Table 1. Comparison of energy consumption between the original process and the two-stage process.
LP HP C1 C2 MP Total
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 25
0 200 400 600 800 1000 1200 45.8 kW, on average. Thus, the energy con-
servation of a non-unloading day is about
16
1099.2 kWh. Accordingly, compared with
the original process, 581,550 kWh power
of Compressor1
BOG Flowrate
12
can be saved and BOG emission can be
reduced by 2878.2 t a1 in the two-stage
(t/h)
8
process. According to the industrial elec-
tricity price of 0.123 $ kWh1 and a natural
4
gas price of 0.483 $ Nm3 in China, about
460
$ 2.01 million can be saved annually when
the two-stage process is adopted. There will
Pressure of BR1
440
trates the investment cost. Overall, the ad-
430 ditional capital cost of the two-stage pro-
cess is $ 6.86 million. It will take 3.4 years
420
to recover the investment cost.
5.08
6.3 Operation Safety
Level of BR1
Receiving Terminal
4
shown above, the BR2 liquid level can be
(t/h)
1050
more BOG as soon as possible so that it
1000
(kPa)
3.65
(m)
3.60 7 Conclusion
3.55
A BOG two-stage compression and recon-
3.50
densation process was designed based on
0 200 400 600 800 1000 1200 the original process and optimized through
Time(s) dynamic simulation; in the two-stage pro-
Figure 8. Dynamic performance of the two-stage process with increasing BOG load. cess, the safety risks of system vibration
can be eliminated, better operation stability
when using the two-stage process, which is 3103 kWh in total. can be provided and energy consumption can be reduced. The
The figure bars indicate the amount of BOG saved by the two- advantages of the two-stage process are summarized as follows:
stage process, which is 31.98 t in total in an unloading day. The recondenser liquid level can be kept in the best range of
The unloading happens approximately 90 times a year in the 5060 % and the recondenser pressure can remain in the safe
Da-Peng terminal. In the unloading day, the energy conserva- range to ensure the safe NPSH of both the MP and HP,
tion value of the non-unloading operation per unit time is which eliminates the safety risks. Both the liquid level and
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 26
780
770
(t/h)
760
750
740
730
432
Pressure of BR1
430
(kPa)
428
426
5.12
Level of BR1
5.08
(m)
5.04
5.00
886.0
Pressure of BR2
885.5
(kPa)
885.0
884.5
884.0
3.512
Level of BR2
3.508
(m)
3.504
3.500
Figure 9. Dynamic performance
0 300 600 900 1200 1500 of the two-stage process with
Time(s) decreasing LNG output.
Table 2. Investment cost of the two-stage process. the pressure of the recondenser are able to return to the set-
ting value more quickly than in the original process. The
Newly added equipment Characteristic Cost [$ million] two-stage process has a better dynamic performance and
BOG compressor 430 kPa, 2.97 operation stability.
10.2 t h1 There will be remarkable energy conservation. Especially, the
energy consumption of the BOG compressor can be
Recondenser 49 m3 1.90 decreased by 25.3 % under the designed working conditions.
Four medium-pressure pumps 420 m3h1, 1.00 The two-stage process can save 581 550 kWh power and
120 m reduce the BOG emissions by 2878.2 t per year. These effects
can save about $ 2.01 million annually. The additional capital
Pipelines and accessories 0.99
cost of the two-stage process is only $ 6.86 million, requiring
Total cost [$ million] 6.86 3.4 years to recover the investment.
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com
Research Article 27
4.0
7500
3.5
7000
3.0
Energy Consumption
6500
6000 2.5
Saved BOG
(kW)
(t/h)
5500 2.0
5000 1.5
Figure 10. Comparison
of energy consumption
4500 between the two pro-
1.0
cesses and the amount
4000 of BOG conservation
0.5 in an unloading day;
3500 two-stage operat-
0.0 ing mode; original
0 2 4 6 8 10 12 14 16 18 20 22 24 operating mode;
Time(h) saved BOG.
Chem. Eng. Technol. 2017, 40, No. 1, 1827 2017 WILEY-VCH Verlag GmbH & Co. KGaA, Weinheim www.cet-journal.com