Overall Project Completion Phases Milestones

PreComm./
Commissioning Dossiers
for Systems/
RFC for Subsystems
Subsystems PAC

RFHO Startup &


Onshore Comm. Offshore Comm. RFSU FFD RFO
FAT MC Pre Com Per Performance
/OTPs /OTPs Per System RFSU CERT CERT Test
sub-System
Lube oil flushing
Function Tests Design conformity checks Cold loop checks N2 leak testing Final inst. functional testing Introduce process
at Vendor workshop reinstatement Static/de-energised tests Energisation & hot tests Final electrical functional testing fluids & systematically
or run tests, lubricant supply etc.. Uncoupled motor checks Hot loop checks Final control/safety systems tests bring facilities
hydrotests, etc.. Piping flush, drying Inst./elect. functional tests Complete N2 leak testing into stable operation.
Leak tests, All "A" punch to be cleared Pipework flushing Motor run-in Repeat onshore testing Facilities satisfy
Continuity tests Pipework chem. cleaning Control & safety systems tests Continuous operation of ALL utility job specification,
of instruments, Vessel checks & cleaning N2 runs of VRU's (recip.) and support systems free of deficiencies,
Mech. & Electrical Gross leak tests Inerting for preservation etc.. equipt. & docs. Furnished
components Lubricant & chemical loading OTP (Provisional) NO "A"/"B" punch carryover to company
etc.. Piping pressure tests etc.. and All "C" punch to be cleared
All "A" punch to be cleared Pump alignment All "A"& "B" punch to be cleared
"B" punch to be recatogrized Instrument calibration and NO "A"/"B" punch carryover
as "A" and cleared during MC etc.. to Offshore
All "A" punch to be cleared

Platform Gas-in / Ramp-up &


Before gas in Energisation HC/After gas in
pressurisation Stabilzation
for startup
Onshore Offshore
Construction & QA/QC PreCommissioning Field Operations
Commissioning Commissioning

RESPONSIBILITY: EPC RESPONSIBILITY: EPC/PMT


Note: This flowchart is only an overview. Details are to be refered to in commissioning strategy and execution plan
mpletion Phases Milestones

FAC

Warranty
Period

HC/After gas in

Field Operations

RESPONSIBILITY: EPC/PMT