Calendario de Utilizacion de Recursos

Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

MANO DE OBRA
00 09741 SERVICIO DE MONTAJE, INSTALACION, PUESTA EN MARCHA Y GLB 1.00 125,000.00 125,000.00 26,223.78 26,223.78 26,223.78 26,223.78 20,104.88 -
01 06901 CAPACITADOR DIA 4.00 90.00 360.00 - - - - - -
47 00006 CAPATAZ HH 2,829.44 23.08 65,303.48 5,637.90 2,801.20 3,839.78 3,725.93 11,717.37 13,510.89
47 00086 TOPOGRAFO HH 1,314.29 20.10 26,417.23 10,587.08 391.29 - 2,255.29 4,362.96 5,202.08
47 00007 OPERARIO HH 12,022.50 20.10 241,652.25 17,053.54 13,826.86 13,349.39 31,236.61 80,292.93 52,092.86
47 00008 OFICIAL HH 9,702.17 16.50 160,085.81 11,223.34 10,588.68 8,955.49 13,663.81 45,320.00 35,565.52
47 00009 PEON HH 52,138.21 14.84 773,731.04 50,844.19 24,578.56 26,035.32 43,931.35 129,997.05 162,047.36
47 00112 OPERADOR DE EQUIPO LIVIANO HH 104.63 19.88 2,080.04 - 1,096.30 836.91 146.83 - -
MATERIALES
00 09720 ABRAZADERA DE PVC D=110mmX2" UND 4.00 26.00 104.00 - - - 104.00 - -
00 09804 ANILLO DE JEBE 110mm C-7.5 UND 67.58 4.90 331.14 14.70 - - 238.04 78.40 -
00 09701 ANILLO DE JEBE D=110mm UND 510.69 4.90 2,502.38 1,914.18 10.00 98.00 480.20 - -
00 09699 ANILLO DE JEBE D=90mm UND 48.00 4.10 196.80 - - - 196.80 - -
00 09733 CODO CACHIMBA 45 PVC D=160MM UF UND 556.00 38.58 21,450.48 - - - - - -
00 09721 GRIFO CONTRA INCENDIO FF/POSTE 2 BOCAS D=110mm UND 4.00 690.00 2,760.00 - - - 2,760.00 - -
00 07427 HIPOCLORADOR DE FLUJO DIFUSO UND 1.00 75.20 75.20 - - 75.20 - - -
00 09722 MARCO Y TAPA FF P/REGISTRO DE VALVULA(20x15CM) UND 44.00 36.00 1,584.00 - - - - 1,584.00 -
00 09738 OBRAS CIVILES: LOSAS DE CONCRETO, CERCO PERIMETRI GLB 1.00 150,000.00 150,000.00 - - - - 150,000.00 -
00 07150 SELLADOR DE POROS PARA MADERA GLN 51.05 45.35 2,315.12 316.29 778.46 701.01 519.36 - -
00 09734 SILLA TEE PVC PARA CONEXION DE DESAGUE, 200MX160MM PZA 556.00 87.81 48,822.36 - - - - - -
00 07406 TAPON 63MM PVC UND 9.00 6.00 54.00 - - - 54.00 - -
00 09711 TEE PVC ISO, D=90mmx90mm PZA 1.00 114.25 114.25 - - - 114.25 - -
00 07429 TRIPLAY LUPUNA DE 4'x8'x 19 mm. PLN 50.99 105.00 5,353.95 731.46 1,800.26 1,621.15 1,201.08 - -
00 09700 TUBERIA PVC - ISO, D=90mm, C-7.5, U.F. M 3.50 10.50 36.75 - - - 36.75 - -
00 09702 TUBERIA PVC-ISO, D=110mm, C-7.5, U.F. M 13.80 15.30 211.14 27.58 - - 183.56 - -

Pgina 1 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

00 09772 TUBERIA PVC-ISO, D=140mm, C-10, U.F. M 3.88 24.67 95.72 - - - - - -


00 09716 TUBERIA PVC-ISO, D=250mm, C-7.5, UF M 5.60 77.90 436.24 - - - 436.24 - -
00 09735 TUBERIA PVC-ISO-160MM S-25 UF M 2,926.69 18.61 54,465.70 - - - - - -
00 09719 UNION DE REPARACION PVC D=110mm, U.F. UND 70.00 58.10 4,067.00 232.40 - 581.00 3,253.60 - -
00 09717 UNION DE REPARACION PVC D=90mm, UF UND 24.00 43.20 1,036.80 - - - 1,036.80 - -
00 09715 VALVULA COMPUERTA FF D=90mm UND 12.00 348.67 4,184.04 - - - 4,184.04 - -
00 09718 VALVULA DE COMPUERTA FF, D=110mm UND 42.00 381.50 16,023.00 1,144.50 - 1,907.50 12,971.00 - -
01 06962 BOTIQUIN PARA LA OBRA SEM 2.00 1,500.00 3,000.00 3,000.00 - - - - -
01 04766 LUBRICANTE GLN 136.50 54.00 7,371.00 219.91 741.71 - 6,409.38 - -
01 07941 LUBRICANTE PARA TUBERIA DE PVC GLN 108.52 45.82 4,972.39 - - - 2,106.01 2,866.38 -
02 00629 ALAMBRE GALVANIZADO N 10 KG 96.00 5.15 494.40 - - 494.40 - - -
02 07213 ALAMBRE NEGRO # 8 KG 331.37 4.42 1,464.66 30.65 85.23 73.81 54.32 618.02 602.63
02 07207 ALAMBRE NEGRO # 16 KG 609.42 4.42 2,693.64 1,487.58 - - - 610.67 595.39
02 00022 CLAVOS C/C DE 2 1/2", 3", 4" KG 194.67 4.42 860.44 855.04 - - 5.40 - -
02 00019 CLAVOS C/C DE 3" KG 324.28 4.42 1,433.32 50.91 132.67 108.59 90.89 536.22 514.04
02 00118 CLAVOS PARA MADERA C/C 3" KG 13.28 4.42 58.70 2.31 18.80 11.43 26.16 - -
02 00603 PERNOS HEXAGONALES DE 3/4" x 3 1/2" PZA 9.00 5.50 49.50 49.50 - - - - -
03 06206 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 KG 11,532.38 3.00 34,597.14 16,900.98 - 54.00 456.00 8,701.99 8,484.17
03 02347 TAPA METALICA DE 0.60 x 0.60 UND 8.00 85.00 680.00 85.00 - 85.00 - 510.00 -
04 00033 ARENA FINA M3 986.97 65.00 64,153.05 66.90 94.24 198.30 236.00 226.67 387.02
04 00029 ARENA GRUESA M3 2,081.34 65.00 135,287.10 16,660.30 2,574.80 941.20 22,003.31 38,420.36 31,501.96
04 09763 ARENA LIMPIA M3 0.21 55.00 11.55 - - 11.55 - - -
04 08504 GRAVA DE 1" M3 0.19 50.00 9.50 - - 9.50 - - -
04 08503 GRAVA DE 1/2" M3 0.19 50.00 9.50 - - 9.50 - - -
04 07902 MATERIAL ZARANDEADO M3 80.00 55.00 4,400.00 - 4,400.00 - - - -
05 00002 AGUA M3 572.51 10.00 5,725.10 91.38 777.57 92.69 78.32 3,054.16 1,579.72

Pgina 2 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

05 01393 GRAVA DE 3/4" M3 1.64 55.00 90.20 90.20 - - - - -


05 08014 GRAVA DE 3/8" M3 1.54 55.00 84.70 84.70 - - - - -
05 00350 MATERIAL CLASIFICADO PARA BASE M3 126.92 45.00 5,711.40 - - - - - 2,855.70
05 07916 PIEDRA CHANCADA 1/2" - 3/4" M3 1.24 67.80 84.07 - - - 84.07 - -
05 00099 PIEDRA CHANCADA DE 1/2" M3 96.05 67.80 6,512.19 54.90 2,452.61 1,548.90 1,361.38 377.12 -
05 00674 PIEDRA CHANCADA DE 3/4" M3 5.81 67.80 393.92 393.92 - - - - -
05 07005 PIEDRA GRANDE 8" M3 2.59 50.00 129.50 129.50 - - - - -
05 01399 PIEDRA MEDIANA DE 4" M3 1.03 45.00 46.35 46.35 - - - - -
05 02814 PIEDRA SELECCIONADA PARA EMPEDRADO M3 488.14 50.00 24,407.00 - - - - - 12,203.50
05 00030 PIEDRA ZARANDEADA DE 1/2'' Y 3/4'' M3 777.32 67.80 52,702.30 - - - - 26,685.12 26,017.18
10 09788 ABRAZADERA DE FP/TUBO DE 140MM PZA 65.48 22.50 1,473.30 - 484.66 - 35.02 953.62 -
10 07415 ANILLO DE JEBE A-7.5 DE 63MM UND 119.08 1.50 178.62 - - - 178.62 - -
10 06999 DUCHA PORTATIL MODULO UND 2.00 450.00 900.00 900.00 - - - - -
10 07403 LLAVE CORPORATION DE 1/2" UND 612.12 15.00 9,181.80 - 276.93 - 8,359.97 544.90 -
10 04822 PRUEBA DE RED DE DESAGUE, CALIDAD M 7,367.53 1.10 8,104.28 - - - - - -
21 07102 ACELERANTE DE FRAGUA PARA CONCRETO CHEMA 3 GLN 3.75 37.80 141.75 141.75 - - - - -
21 07493 ADITIVO CURADOR DE CONCRETO GLN 2.30 42.50 97.75 97.75 - - - - -
21 07495 ADITIVO PLASTIFICANTE/REDUCTOR DE AGUA GLN 2.30 19.80 45.54 45.54 - - - - -
21 02439 CAJA DE CONCRETO P/MEDIDOR 1/2" - 3/4" UND 556.00 42.00 23,352.00 - - - 23,352.00 - -
21 00003 CEMENTO PORTLAND TIPO IP (42.5KG) BOL 9,524.47 19.60 186,679.61 1,999.20 7,915.94 5,968.36 7,743.03 81,300.90 75,803.02
21 07917 TAPA DE CONCRETO 0.10x0.70x0.80 UND 26.00 80.88 2,102.88 - - 2,102.88 - - -
21 01487 TAPA DE CONCRETO ARMADO PARA BUZON, INC. MARCO UND 192.00 60.00 11,520.00 - - - - 6,200.00 5,320.00
21 07004 YESO EN BOLSA DE 25 KG BOL 379.42 12.70 4,818.63 1,858.95 21.96 - 274.01 530.08 632.03
26 07875 BISAGRA DE FIERRO 3" UND 8.05 4.10 33.01 33.01 - - - - -
26 02770 CERRADURA 2 GOLPES CON TIRADOR TIPO FORTE UND 3.00 41.72 125.16 125.16 - - - - -
27 02510 FULMINANTE UND 19,493.07 13.39 261,012.21 17,995.60 - - 29,166.01 38,084.41 3,253.80

Pgina 3 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

27 04762 GUIA O MECHA M 58,481.24 2.97 173,689.28 11,975.60 - - 19,409.22 25,344.12 2,165.20
28 02511 DINAMITA KG 19,493.06 6.36 123,975.86 8,548.40 - - 13,854.65 18,091.02 1,545.40
29 09775 ANILLO DE JEBE D=140mm UND 22.76 4.20 95.59 8.40 - - 87.19 - -
29 06997 BAO QUIMICO PORTATIL UND 2.00 2,203.39 4,406.78 4,406.78 - - - - -
29 07433 BOTIQUIN DE OBRA INSTALADO UND 5.00 53.39 266.95 266.95 - - - - -
29 06961 CAMILLA RIGIDA DE MADERA UND 1.00 500.00 500.00 500.00 - - - - -
29 04758 CINTA SEALADORA M 258.33 0.60 155.00 - - - - - -
29 07019 CONO DE SEGURIDAD REFLECTIVO UND 18.00 33.81 608.58 608.58 - - - - -
29 07439 CORDON PARA LIMITACION DE AREAS DE RIESGO M 250.00 2.20 550.00 550.00 - - - - -
29 06998 DETERGENTE QUIMICO KG 100.00 25.42 2,542.00 2,542.00 - - - - -
29 09193 EDUCACION SANITARIA UND 1.00 16,500.00 16,500.00 16,500.00 - - - - -
29 07456 ENSAYO DE DENSIDAD DE CAMPO UND 55.00 295.97 16,278.35 - 3,699.63 12,578.72 - - -
29 07435 EXTINTOR DE POLVO POLIVALENTE, SOPORTE Y COLOCACIO UND 5.00 133.47 667.35 667.35 - - - - -
29 06960 EXTINTOR DE POLVO QUIMICO SECO (PQS) 6 KG UND 2.00 350.00 700.00 700.00 - - - - -
29 09736 FORMACION DE JASS GLB 1.00 12,000.00 12,000.00 - - - - - -
29 07847 GIGANTOGRAFIA UND 1.00 59.32 59.32 59.32 - - - - -
29 00403 JUNTA INPER WATER STOP NEOPRENE 6" M 21.02 21.00 441.42 - 441.42 - - - -
29 06903 MITIGACION AMBIENTAL GLB 2.00 21,500.00 43,000.00 - - - - 21,500.00 -
29 09727 MITIGACION DE IMPACTO AMBIENTAL GLB 1.00 27,500.00 27,500.00 - - - - - 27,500.00
29 06959 SC SERVICIO DE CAPACITACION DE SEGURIDAD, SALUD y M glb 1.00 2,500.00 2,500.00 2,500.00 - - - - -
30 07101 ADITIVO DESMOLDANTE PARA ENCOFRADO GLN 68.05 95.59 6,504.90 887.57 2,188.61 1,969.62 1,459.10 - -
30 05747 ADITIVO IMPERMEABILIZANTE PARA MORTERO KG 154.66 30.50 4,717.13 804.20 1,868.75 1,800.43 243.75 - -
30 04811 ANILLO DE JEBE DN 200mm ALCANTARILLADO UND 1,294.12 5.75 7,441.19 - - - 7,441.19 - -
30 02420 ANILLO DE JEBE DN 90 mm UND 62.28 2.18 135.77 - - - 135.77 - -
30 07931 CINTA PLASTICA P/SEAL DE SEGURIDAD OBRA M 1,260.00 0.40 504.00 - - - 504.00 - -
30 02988 CINTA TEFLON UND 237.96 1.20 285.55 13.52 34.62 - 169.30 68.11 -

Pgina 4 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

30 00266 CORDEL M 5,779.50 0.20 1,155.90 571.99 6.76 - 84.31 163.10 194.47
30 01368 CURADOR PARA CONCRETO KG 12.31 4.85 59.70 59.70 - - - - -
30 01203 IGAS NEGRO KG 4.00 17.50 70.00 - - 70.00 - - -
30 09771 IGOL DENSO SIKA KG 5.10 4.20 21.42 - - 21.42 - - -
30 07844 IGOL IMPRIMANTE KG 1.38 4.20 5.80 - - 5.80 - - -
30 00395 IMPERMEABILIZANTE LIQUIDO PARA CONCRETO GLN 0.61 30.50 18.61 18.61 - - - - -
30 00144 LIJAR UND 14.16 1.50 21.24 3.84 - 17.40 - - -
30 04341 PEGAMENTO PARA PVC GLN 372.91 99.80 37,216.42 14.73 - 0.50 1,115.48 1,129.46 -
30 04759 SEAL PREVENTIVA UND 5.00 30.00 150.00 - - - - - -
30 07919 SOLDADURA CELLOCORD P 3/32" KG 9.73 16.00 155.68 - - 91.15 64.53 - -
32 00343 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 5,000.00 5,000.00 - - - - - -
32 09569 TRANSPORTE (IDA + VUELTA) CAMION VOLQUETE 15 M3 GLB 1.00 4,000.00 4,000.00 - - - - - -
32 09817 TRANSPORTE (IDA + VUELTA) CARGADOR FRONTAL S/LLANTAS GLB 1.00 7,500.00 7,500.00 - - - - - -
32 09568 TRANSPORTE (IDA + VUELTA) COMPRESORA NEUMATICA 87 H GLB 1.00 2,500.00 2,500.00 - - - - - -
32 09818 TRANSPORTE (IDA + VUELTA) RETROEXCAVADOR S/LLANTAS 5 GLB 1.00 7,500.00 7,500.00 - - - - - -
32 01853 TRANSPORTE DE MATERIALES GLB 1.00 7,500.00 7,500.00 - - - - - -
32 09570 TRANSPORTE DE MATERIALES AREQUIPA - CAYARANI KG 184,037.80 0.15 27,605.67 - - - - - -
32 09571 TRANSPORTE DE MATERIALES AREQUIPA - OBRA KG 184,037.80 0.05 9,201.89 9,201.89 - - - - -
34 07336 ACEITE PARA MOTOR SAE - 30 GAL 0.83 64.07 53.18 36.02 8.79 7.15 1.22 - -
34 07428 GASOLINA 84 OCTANOS GLN 58.15 12.80 744.32 41.64 251.00 204.85 35.52 - -
38 00005 HORMIGON M3 16.87 45.00 759.15 270.34 102.15 114.21 272.45 - -
39 07991 AGUA PARA LA OBRA MES 6.00 180.00 1,080.00 1,080.00 - - - - -
39 08035 ANILLO C-10 DN=90 MM UND 7.00 2.18 15.26 - - - 15.26 - -
39 09806 ANILLO C-7.5 DN=90 MM UND 37.00 2.18 80.66 - - - 80.66 - -
39 09802 ANILLO DN=75 MM C-7.5 UND 194.96 2.50 487.40 - - - 487.40 - -
39 07989 CAJA DE PROTECCION DE LLAVE CORPORATION UND 556.00 32.00 17,792.00 - - - 17,792.00 - -

Pgina 5 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

39 01644 HIPOCLORITO DE CALCIO AL 70% KG 400.69 25.00 10,017.25 - 2,596.25 2,125.00 187.61 5,108.39 -
39 01154 LIJA AL AGUA PARA METAL HJA 3.56 1.80 6.41 - - 6.41 - - -
39 01852 PRUEBAS DE CALIDAD DE CONCRETO ROTURA UND 15.00 25.00 375.00 - - 375.00 - - -
39 08013 REGILLA DE BRONCE DE 2" UND 1.00 3.80 3.80 3.80 - - - - -
39 07984 SELLADOR DE UNIONES ROSCADAS GLN 6.95 50.00 347.50 - - - 347.50 - -
39 07001 SERVICIO ENERGIA ELECTRICA MES 6.00 150.00 900.00 900.00 - - - - -
39 08040 TAPON PVC 90mm CLASE 10 PZA 7.00 42.80 299.60 - - - 299.60 - -
39 06900 UTILES DE ESCRITORIO EST 1.00 250.00 250.00 - - - - - -
43 00025 LIJA PARA MADERA UND 1.07 1.46 1.56 0.90 - 0.66 - - -
43 07930 MADERA ENCOFRADO P2 464.97 3.27 1,520.45 - - - 1,520.45 - -
43 00020 MADERA TORNILLO P2 12,091.84 5.31 64,207.67 6,554.21 4,245.46 2,856.34 3,186.51 22,588.46 21,590.68
43 00274 REGLA DE MADERA P2 2.93 5.31 15.56 6.90 - 8.66 - - -
43 04760 SOPORTES PARA SEAL P2 33.75 2.00 67.50 - - - - - -
44 07841 ESTACA DE ACERO UND 1,917.78 1.80 3,452.00 824.40 30.41 - 379.39 733.96 875.12
44 07933 LETRERO INFORMATIVO UND 20.00 50.00 1,000.00 - - - 1,000.00 - -
44 07216 PUNTAL DE EUCALIPTO 3"X13' PZA 21.82 12.80 279.30 - 139.11 83.49 56.70 - -
44 01018 TRIPLAY LUPUNA 6mm x 4' x 8' UND 50.00 48.30 2,415.00 2,415.00 - - - - -
44 01417 TRIPLAY LUPUNA DE 4'x8'x 4 mm PLN 3.00 35.00 105.00 105.00 - - - - -
46 07445 CINTA DE SEALIZACION REFLEXIVA RLL 6.00 34.66 207.96 207.96 - - - - -
46 07918 MALLA GALVANIZADA 2"x2" N8 M 59.45 4.50 267.53 - - 267.53 - - -
47 09610 CAPACITACION JUNTA ADMINISTRADORA DE AGUA Y SANEAM GLB 1.00 7,500.00 7,500.00 7,500.00 - - - - -
47 07898 PRUEBA DE PROCTOR EN CAMPO UND 40.00 92.50 3,700.00 - - - - - 3,700.00
47 07440 SISTEMA DE ENTIBADO DISCONTINUO UND 25.00 35.00 875.00 875.00 - - - - -
50 01795 MARCO F.FDO. DIAMETRO 1.20 m UND 192.00 120.00 23,040.00 - - - - 12,400.00 10,640.00
50 07988 MARCO Y TAPA DE FIERRO FUNDIDO UND 556.00 38.00 21,128.00 - - - 21,128.00 - -
50 01566 TAPA DE INSPECCION 0.60x0.60 m PZA 6.00 55.00 330.00 - - - 330.00 - -

Pgina 6 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

51 07434 CARTEL INDICATIVO DE RIESGO CON SOPORTE METALICO UND 11.00 313.56 3,449.16 3,449.16 - - - - -
51 07444 CARTEL PARA SEALES OBLIGATORIAS EN OBRA (30x60) UND 6.00 77.97 467.82 467.82 - - - - -
52 07441 CARTEL PARA ROTULAR AREAS DE TRABAJO (0.45x0.60m UND 6.00 86.44 518.64 518.64 - - - - -
52 07442 CARTEL PARA SEALES DE ADVERTENCIA DE OBRA (30x60) UND 6.00 77.97 467.82 467.82 - - - - -
52 07443 CARTEL PARA SEALES DE PROHIBICION (30x60) UND 6.00 77.97 467.82 467.82 - - - - -
53 00132 PETROLEO DIESEL # 2 GLN 350.41 11.15 3,907.07 - 1,142.36 - 82.55 2,247.71 217.22
54 07044 IMPRIMANTE MAGESTAD 25Kg KG 6.90 27.50 189.75 108.96 - 80.79 - - -
54 08077 PINTURA ANTICORROSIVA GLN 2.96 40.00 118.40 3.99 - 60.57 53.84 - -
54 07846 PINTURA BASE KG 1.00 8.50 8.50 8.50 - - - - -
54 07053 PINTURA BASE IMPRIMANTE PARA MUROS X5KG BLS 17.21 27.50 473.28 74.29 - 398.99 - - -
54 00027 PINTURA ESMALTE GLN 2.19 45.00 98.55 22.35 - 49.14 27.06 - -
54 00606 PINTURA ESMALTE SINTETICO GLN 2.58 25.00 64.50 - - 30.85 33.65 - -
54 01536 PINTURA LATEX SUPERMATE GLN 5.73 54.00 309.42 100.12 - 209.30 - - -
56 03734 CALAMINA FORMATO DE 1.80x0.80 e=0.24mm PLN 80.00 26.50 2,120.00 2,120.00 - - - - -
56 08001 TAPA METALICA 1.30 X 1.15 m UND 2.00 110.00 220.00 110.00 - 110.00 - - -
56 09776 UNION DE REPARACION PVC D=140mm, U.F. UND 2.00 65.80 131.60 131.60 - - - - -
61 09809 ABRAZADERA DE FP/TUBO DE 75MM PZA 6.00 15.80 94.80 - - - 94.80 - -
62 09766 CONCRETO F'C=210 KG/CM2 M3 0.88 340.00 299.20 - - 136.00 163.20 - -
65 08137 CODO HIERRO DUCTIL LUFLEX 63mmx90 UND 1.00 70.20 70.20 - - - 70.20 - -
65 01637 CODO DE Fo GALV UR 3" UND 5.00 65.80 329.00 - - - - - -
65 08072 NIPLE ACERO DN=110MM M 1.20 100.58 120.70 - - - 120.70 - -
65 09770 NIPLE PASAMURO DE ACERO DN= 110 L= 200 mm. M 50.00 155.00 7,750.00 310.00 - - 6,820.00 620.00 -
65 09779 NIPLE PASAMURO DE ACERO DN= 140 L= 200 mm. M 2.00 185.60 371.20 371.20 - - - - -
65 08058 TEE ACERO SCH40 BB 63MM UND 6.00 249.76 1,498.56 - - - 1,498.56 - -
65 01605 TEE DE Fo. GALVANIZADO DE 3" UND 1.00 62.40 62.40 62.40 - - - - -
65 07920 TUB. FIERRO NEGRO DE 2" x 6.4m UND 3.20 75.50 241.60 - - 241.60 - - -

Pgina 7 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

65 09764 TUBERIA DE FIERRO GALVANIZADO 3/4" M 193.20 13.50 2,608.20 - - 1,247.40 1,360.80 - -
65 08004 TUBERIA PVC SAP ESPIGA CAMPANA 3" C-10 M 12.41 12.05 149.54 149.54 - - - - -
65 08003 TUBERIA PVC SAP ESPIGA CAMPANA 63MM C-10 M 1.03 6.99 7.20 7.20 - - - - -
65 01641 UNION UNIVERSAL DE Fo. GALV. DE 3" UND 2.00 12.70 25.40 25.40 - - - - -
66 02493 ANILLO ALCANT. 3.5 D = 160 mm UND 1,112.00 8.40 9,340.80 - - - - - -
66 02483 LUBRICANTE PARA PVC GLN 5.03 42.02 211.36 - - - - - -
68 09754 CANASTILLA DE BRONCE DE 4" UND 2.00 125.40 250.80 125.40 - 125.40 - - -
68 09780 CANASTILLA DE BRONCE DE 5" UND 1.00 130.50 130.50 130.50 - - - - -
68 00766 SUMIDERO DE BRONCE 2" UND 5.00 8.00 40.00 - - 40.00 - - -
68 08062 SUMIDERO DE BRONCE DN=50MM UND 6.00 22.00 132.00 - - - 132.00 - -
69 07987 TUBO C.S.N. DIAM. 4" X 1M C/ANILLO UND 1,390.00 30.00 41,700.00 - - - 41,700.00 - -
71 07990 ABRAZADERA DE FF C/EMPAQUE DE GOMA 4" C/SALIDA A 1/2 UND 556.00 29.00 16,124.00 - - - 16,124.00 - -
71 09762 CLAPETA DE CAMPANA ACERO DN=110MM UND 5.00 95.50 477.50 - - 477.50 - - -
71 09552 CODO HIERRO DUCTIL LUFLEX 63mm x11.25 UND 1.00 58.31 58.31 - - - 58.31 - -
71 09550 CODO HIERRO DUCTIL LUFLEX 63mm x45 UND 1.00 68.04 68.04 - - - 68.04 - -
71 09783 CODO FF 140MM x 11.25 UND 1.00 122.50 122.50 - - - 122.50 - -
71 09784 CODO FF 140MM x 22.5 UND 6.00 145.20 871.20 - - - 871.20 - -
71 09785 CODO FF 140MM x 45 UND 1.00 153.07 153.07 - - - 153.07 - -
71 09773 CODO FF 140MM x 90 UND 5.00 122.50 612.50 612.50 - - - - -
71 09551 CODO HIERRO DUCTIL LUFLEX 63mm x22.5 UND 3.00 65.50 196.50 - - - 196.50 - -
71 09813 CRUZ HIERRO F. DUCTIL DN 110 X 110 mm C/EMBONE A PVC UND 5.00 200.90 1,004.50 - - - 1,004.50 - -
71 06964 CRUZ HIERRO F. DUCTIL DN 75 X 75 mm C/EMBONE A PVC UND 18.00 153.90 2,770.20 - - - 2,770.20 - -
71 09811 CRUZ HIERRO F. DUCTIL DN 90 X 90 mm C/EMBONE A PVC UND 19.00 175.80 3,340.20 - - - 3,340.20 - -
71 09761 NIPLE A SCH 20 DN=110MM L=450MM UND 5.00 180.00 900.00 - - 900.00 - - -
71 08068 NIPLE B/UN SOLO LADO AS N20 DN=110MM UND 6.00 100.58 603.48 - - - 603.48 - -
71 09760 NIPLE BRIDA UN SOLO LADO A SCH 20 DN=110M L=300MM UND 5.00 165.00 825.00 - - 825.00 - - -

Pgina 8 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

71 09757 NIPLE BRIDA UN SOLO LADO A SCH 20 DN=110M L=350MM UND 5.00 234.00 1,170.00 - - 1,170.00 - - -
71 09758 NIPLE PASAMURO BRIDADO A SCH 20 DN=110MM L=550MM UND 5.00 145.00 725.00 - - 725.00 - - -
71 09759 NIPLE PASAMURO BRIDADO A SCH 20 DN=110MM L=750MM UND 5.00 234.00 1,170.00 - - 1,170.00 - - -
71 09786 REDUCCION 140MM @ 110MM FF UND 1.00 135.40 135.40 - - - 135.40 - -
71 09815 REDUCCION UF 110MM @ 63MM FF UND 2.00 55.50 111.00 - - - 111.00 - -
71 09814 REDUCCION UF 110MM @ 75MM FF UND 2.00 65.80 131.60 - - - 131.60 - -
71 08093 REDUCCION UF 110MM @ 90MM FF UND 11.00 75.37 829.07 - - - 829.07 - -
71 09812 REDUCCION UF 90MM @ 63MM FF UND 2.00 85.20 170.40 - - - 170.40 - -
71 09816 TEE FF HIERRO DUCTIL 90 x90MM UND 7.00 135.20 946.40 - - - 946.40 - -
71 08125 TEE HIERRO DUCTIL 75mm UND 16.00 153.90 2,462.40 - - - 2,462.40 - -
71 09774 TEE DE FF 140 mmx110mm PZA 1.00 148.80 148.80 148.80 - - - - -
71 09756 TRANSICION ACERO-PVC D=110MM UND 10.00 165.00 1,650.00 - - 1,650.00 - - -
71 08133 TRANSICION ACERO-PVC D=75MM UND 1.20 119.21 143.05 - - - 143.05 - -
71 07662 UNION TIPO DRESSER BRIDADA 4" und 5.00 175.00 875.00 - - 875.00 - - -
71 09768 UNION TIPO DRESSER BRIDADA DN 110MM UND 6.00 175.00 1,050.00 - - - 1,050.00 - -
71 09807 VALVULA COMPUERTA FF D=75mm UND 10.00 335.00 3,350.00 - - - 3,350.00 - -
71 09777 VALVULA DE COMPUERTA FF, D=140mm UND 1.00 435.00 435.00 435.00 - - - - -
72 02981 ADAPTADOR 4" TUBO PVC CLASE 10 UND 9.00 5.20 46.80 46.80 - - - - -
72 08122 CODO HIERRO DUCTIL LUFLEX 75mmx45 UND 1.00 79.04 79.04 - - - 79.04 - -
72 08005 CODO CPVC 2" x 90 UND 2.00 4.02 8.04 8.04 - - - - -
72 08006 CODO CPVC 3" x 90 UND 2.00 10.85 21.70 21.70 - - - - -
72 08087 CODO FF 110MM x 90 UND 37.00 103.19 3,818.03 619.14 - 515.95 1,857.42 825.52 -
72 08090 CODO FF 110mmx11.25 UND 78.00 81.41 6,349.98 6,349.98 - - - - -
72 08089 CODO FF 110mmx22.5 UND 58.00 87.07 5,050.06 5,050.06 - - - - -
72 08088 CODO FF 110mmx45 UND 18.00 88.63 1,595.34 1,595.34 - - - - -
72 08124 CODO HIERRO DUCTIL LUFLEX 75mmx11.25 UND 4.00 58.31 233.24 - - - 233.24 - -

Pgina 9 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

72 08123 CODO HIERRO DUCTIL LUFLEX 75mmx22.5 UND 11.00 73.75 811.25 - - - 811.25 - -
72 08121 CODO HIERRO DUCTIL LUFLEX 75mmx90 UND 5.00 83.38 416.90 - - - 416.90 - -
72 08038 CODO HIERRO DUCTIL LUFLEX 90mmx11.25 UND 2.00 69.32 138.64 - - - 138.64 - -
72 08037 CODO HIERRO DUCTIL LUFLEX 90mmx22.5 UND 1.00 80.00 80.00 - - - 80.00 - -
72 08034 CODO HIERRO DUCTIL LUFLEX 90mmx90 UND 5.00 88.90 444.50 - - - 444.50 - -
72 09781 CONO DE REBOSE 3" UND 1.00 45.80 45.80 45.80 - - - - -
72 09778 NIPLE PVC 5" PZA 2.00 54.80 109.60 109.60 - - - - -
72 09755 NIPLE PVC DN=110M PZA 3.00 42.20 126.60 126.60 - - - - -
72 09752 NIPLE PVC SAP C. ROSCA DE 4" UND 2.00 8.50 17.00 17.00 - - - - -
72 08126 REDUCCION PVC 75MM A 63MM NTP ISO 4422 UND 8.00 75.37 602.96 - - - 602.96 - -
72 09810 TAPON 75MM PVC UND 6.00 12.50 75.00 - - - 75.00 - -
72 08075 TEE FF HIERRO DUCTIL 110MMx110MM UND 16.00 157.97 2,527.52 157.97 - 789.85 1,579.70 - -
72 09767 TEE ACERO SCH40 BB 110MM UND 6.00 157.97 947.82 - - - 947.82 - -
72 08007 TEE PVC DE 2" UND 1.00 6.95 6.95 6.95 - - - - -
72 09808 TEE PVC ISO, D=75mmx75mm PZA 5.00 105.00 525.00 - - - 525.00 - -
72 09803 TUBERIA PVC AGUA U.F. CLASE 7.5, ISO 4422 DN 110MM x 6M M 728.68 15.31 11,156.09 - - - 11,156.09 - -
72 09799 TUBERIA PVC AGUA U.F. CLASE 7.5, ISO 4422 DN 63MM x 6M M 391.05 5.18 2,025.64 - - - 2,025.64 - -
72 09801 TUBERIA PVC AGUA U.F. CLASE 7.5, ISO 4422 DN 75MM x 6M M 3,062.28 7.29 22,324.02 - - - 22,324.02 - -
72 08047 TUBERIA PVC AGUA U.F., CLASE 10 ISO 4422 DN 110mm x 6m M 3,644.41 18.20 66,328.26 64,465.98 1,862.28 - - - -
72 09800 TUBERIA PVC AGUA UF CLASE 7.5, ISO 4422 DN 90MM x 6M M 2,770.30 10.36 28,700.31 - - - 28,700.31 - -
72 07985 TUBERIA PVC CLASE 10 CR DE 1/2" X 5M M 1,433.24 4.50 6,449.58 - - - 6,449.58 - -
72 04812 TUBERIA PVC ISO-4422 S-25 DE 200mm UND 1,290.18 27.81 35,879.91 - - - 35,879.91 - -
72 09782 TUBERIA PVC U.F. CLASE 7.5 ISO 4422 DN 140MMM x 6M M 255.20 24.76 6,318.75 - - - 6,318.75 - -
72 01086 TUBO PVC - SAL 2'' (3m) M 2.03 2.00 4.06 - - 4.06 - - -
72 07986 UNION SIMPLE PVC SAP CLASE 10 CR DE 1/2" UND 278.00 2.50 695.00 - - - 695.00 - -
72 09753 UNION UNIVERSAL PVC SAP DE 4" UND 2.00 52.30 104.60 104.60 - - - - -

Pgina 10 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

77 05105 LLAVE DE PASO PVC 1/2" (INC.TUER-NIPLE) UND 556.00 13.00 7,228.00 - - - 7,228.00 - -
77 01571 VALVULA COMPUERTA DE BRONCE DE 3" UND 2.00 226.57 453.14 453.14 - - - - -
77 08136 VALVULA DE AIRE BB FF DE 75MM UND 6.00 455.00 2,730.00 - - - 2,730.00 - -
77 08060 VALVULA DE AIRE BB FF DE110MM UND 6.00 455.00 2,730.00 - - - 2,730.00 - -
77 09563 VALVULA REDUCTORA DE PRESION INC. ACCESORIOS UND 10.00 1,100.00 11,000.00 - - - 11,000.00 - -
EQUIPO
00 09743 EQUIPOS DE MONITOREO PORTATILES GLB 1.00 40,000.00 40,000.00 - - - - 40,000.00 -
00 09739 SUMINISTRO DE EQUIPOS QUE CONFORMAN LA PTAR 100M3/ GLB 1.00 225,000.00 225,000.00 - - - - 225,000.00 -
00 09740 TANQUES DE FIBRA DE VIDRIO QUE CONFORMAN LA PTRA 10 GLB 1.00 135,000.00 135,000.00 - - - - 135,000.00 -
00 09742 TRANSPORTE DE PERSONAL Y MATERIALES A OBRA GLB 1.00 35,000.00 35,000.00 - - - - 35,000.00 -
29 07167 BOTAS DE CUERO CON PUNTA DE ACERO PAR 80.00 51.61 4,128.80 - - - - - -
29 07009 BOTAS DE JEBE PAR 80.00 21.36 1,708.80 - - - - - -
29 07010 CASCO DE SEGURIDAD UND 80.00 5.76 460.80 - - - - - -
29 07011 CHALECOS DE SEGURIDAD CON LINEAS REFLEXIVAS UND 80.00 18.64 1,491.20 - - - - - -
29 07436 CINTURON DE SEGURIDAD UND 80.00 38.14 3,051.20 - - - - - -
29 07012 GUANTE DE JEBE PAR 80.00 8.05 644.00 - - - - - -
29 07013 GUANTES DE CUERO PAR 80.00 6.95 556.00 - - - - - -
29 07168 LENTES DE PROTECCION CONTRA RAYOS UV UND 80.00 3.56 284.80 - - - - - -
29 07437 MASCARA ANTIGAS DOBLE FILTRO UND 80.00 60.59 4,847.20 - - - - - -
29 07438 OVEROL DE TRABAJO UND 80.00 51.61 4,128.80 - - - - - -
29 07169 PROTECTORES DE OIDO UND 80.00 3.14 251.20 - - - - - -
29 07170 RESPIRADORES ANTIPOLVO DE OBRA UND 80.00 8.05 644.00 - - - - - -
37 00942 BALDE PRUEBA-TAPON -ABRAZ. Y ACCESORIOS HM 35.08 6.00 210.48 - 69.24 - 5.00 136.24 -
37 00004 HERRAMIENTAS MANUALES %MO 40,198.10 2,664.21 1,905.34 1,908.99 2,410.32 8,305.04 8,010.62
48 03181 CAMION CISTERNA 4X2 (AGUA) 2,000 GAL. HM 33.32 120.00 3,998.40 - 1,315.32 - 95.05 2,588.03 -
48 03748 CAMION VOLQUETE 15 M3. HM 1,305.75 120.00 156,690.00 - - - - 29,100.65 54,417.14

Pgina 11 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

48 01579 CIZALLA P/CORTE DE FIERRO HM 197.24 0.50 98.62 98.62 - - - - -


48 07922 EQUIPO DE PINTURA HE 32.00 7.50 240.00 - - 240.00 - - -
48 07921 EQUIPO DE SOLDAR HE 53.49 9.80 524.20 - - 414.33 109.87 - -
48 07003 ESTACION TOTAL INC. PRISMA Y RADIO HM 350.14 12.50 4,376.75 4,374.94 1.81 - - - -
48 00430 MEZCLADORA DE CONCRETO DE 9 -11P3 HM 55.46 9.00 499.14 86.13 231.21 154.40 27.40 - -
48 01488 MOLDE METALICO PARA BUZON UND 972.76 8.73 8,492.19 - - - - 4,570.45 3,921.74
48 07532 NIVEL TOPOGRAFICO INC. MIRAS HM 85.32 6.50 554.58 101.22 20.52 - 63.23 122.32 145.85
48 06884 TECLE -TRIPODE INC. CADENA PARA 5 TON HM 106.40 5.00 532.00 136.00 - 20.00 24.00 352.00 -
48 04881 VARIOS (% MATERIALES) %MT 2.50 - - - - - -
49 06902 CAMIONETA RURAL 4x4 135 HP 5 PASAJEROS DIA 4.00 120.00 480.00 - - - - - -
49 00090 CARGADOR S/LLANTAS 100-115 HP 2-2.25 YD3 HM 348.49 140.00 48,788.60 - - - - 16,999.73 31,788.87
49 08389 COMPACTADOR VIBRAT.TIPO PLANCHA 5.8 HP HM 2,618.22 18.34 48,018.15 - - - - - 15,542.35
49 00113 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 5.16 6.00 30.96 - 18.18 7.76 5.02 - -
49 00108 COMPRESORA NEUMATICA 87 HP 250-330 PCM HM 550.01 77.42 42,581.77 3,735.21 - - 8,396.55 5,685.25 921.60
49 02515 MARTILLO NEUMATICO 29 KG C/BARRENO-ACCS HM 1,100.26 6.50 7,151.69 627.20 - - 1,407.94 956.65 154.80
49 00031 MEZCLADORA DE CONC. (TAMBOR) 11 P3, 22 HP HM 496.67 14.50 7,201.72 - - - - 2,220.50 3,565.61
49 00268 PLANCHA COMPACTADORA VIBRAT. 4.0 HP HM 3,140.08 12.50 39,251.00 19.40 5,155.66 4,251.96 667.90 10,212.89 12,033.36
49 01357 RETROEXCAVADOR S/LLANTAS 58 HP 1 YD3. HM 1,519.97 190.00 288,794.30 21,596.74 - - 42,510.67 77,792.60 126,629.96
49 00267 TEODOLITO Y MIRA HM 469.63 8.00 3,757.04 700.99 25.96 - 442.63 856.29 1,020.98
49 00032 VIBRADOR A GASOLINA 1 3/4", 4HP HM 301.41 8.50 2,561.99 - - - - 1,301.66 1,260.33
49 07525 VIBRADOR DE CONCRETO 4 HP 1.50" HM 4.89 8.00 39.12 39.12 - - - - -
49 00122 VIBRADOR DE CONCRETO 4 HP 2.40" HM 41.85 6.00 251.10 - 132.34 101.04 17.72 - -
49 00927 WINCHE - 2 BALDES, 3.6 HP HM 0.84 18.50 15.54 - 3.14 11.10 1.30 - -

4,809,898.27 401,452.65 131,530.26 139,562.17 640,221.27 1,381,296.83 777,606.15


GASTOS GENERALES 10 % 480,989.83 40,145.27 13,153.03 13,956.22 64,022.13 138,129.68 77,760.62
UTILIDAD 7% 336,692.88 28,101.69 9,207.12 9,769.35 44,815.49 96,690.78 54,432.43

Pgina 12 de 26
Calendario de Utilizacion de Recursos
Obra : "MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO E INSTALACION DE PTAR PARA EL C.P. DE ACHOMA"
Ubicacion : ACHOMA - CAYLLOMA - AREQUIPA
Costo A : Oct - 2016 Cliente : MUNICIPALIDAD DISTRITAL DE ACHOMA
PLAZO DE EJECUCION

Cod Descripcion Unid Cantidad Precio Parcial 30 Das 30 Das 30 Das 30 Das 30 Das 30 Das

SUB TOTAL 5,627,580.98 469,699.60 153,890.41 163,287.74 749,058.89 1,616,117.29 909,799.20


IGV (IMPUESTO DE LEY) 18 % 1,012,964.58 84,545.93 27,700.27 29,391.79 134,830.60 290,901.11 163,763.86
PRESUPUESTO TOTAL DE EJECUCION 6,640,545.56 554,245.53 181,590.68 192,679.53 883,889.49 1,907,018.40 1,073,563.06
GASTOS SUPERVISION 5% 240,494.91 20,072.63 6,576.51 6,978.11 32,011.06 69,064.84 38,880.31
GASTOS LIQUIDACION 0.5 % 24,049.49 2,007.26 657.65 697.81 3,201.11 6,906.48 3,888.03
EXPEDIENTE TECNICO 90,000.00 90,000.00
EDUCACION SANITARIA 18,000.00
PRESUPUESTO TOTAL DE INVERSION 7,013,089.96 585,339.52 191,778.19 203,489.14 933,477.00 2,014,004.95 1,133,791.53
TOTAL ACUMULADO 585,339.52 777,117.71 980,606.85 1,914,083.85 3,928,088.80 5,061,880.33
PORCENTAJE DE AVANCE 8.35% 2.73% 2.90% 13.31% 28.72% 16.17%
PORCENTAJE ACUMULADO 8.35% 11.08% 13.98% 27.29% 56.01% 72.18%

Pgina 13 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias

- - - 125,000.00
- 360.00 - 360.00
6,325.39 7,347.20 10,397.82 65,303.48
3,618.53 - - 26,417.23
20,194.10 13,605.96 - 241,652.25
20,738.17 14,030.80 - 160,085.81
112,813.21 103,660.07 119,823.93 773,731.04
- - - 2,080.04

- - - 104.00
- - - 331.14
- - - 2,502.38
- - - 196.80
9,384.59 12,065.89 - 21,450.48
- - - 2,760.00
- - - 75.20
- - - 1,584.00
- - - 150,000.00
- - - 2,315.12
21,359.78 27,462.58 - 48,822.36
- - - 54.00
- - - 114.25
- - - 5,353.95
- - - 36.75
- - - 211.14

Pgina 14 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - -
- - - 436.24
23,828.74 30,636.96 - 54,465.70
- - - 4,067.00
- - - 1,036.80
- - - 4,184.04
- - - 16,023.00
- - - 3,000.00
- - - 7,371.00
- - - 4,972.39
- - - 494.40
- - - 1,464.66
- - - 2,693.64
- - - 860.44
- - - 1,433.32
- - - 58.70
- - - 49.50
- - - 34,597.14
- - - 680.00
27,465.36 35,478.56 - 64,153.05
21,986.97 1,198.20 - 135,287.10
- - - 11.55
- - - 9.50
- - - 9.50
- - - 4,400.00
- 51.26 - 5,725.10

Pgina 15 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - 90.20
- - - 84.70
- 2,855.70 - 5,711.40
- - - 84.07
313.81 403.47 - 6,512.19
- - - 393.92
- - - 129.50
- - - 46.35
- 12,203.50 - 24,407.00
- - - 52,702.30
- - - 1,473.30
- - - 178.62
- - - 900.00
- - - 9,181.80
- 8,104.28 - 8,104.28
- - - 141.75
- - - 97.75
- - - 45.54
- - - 23,352.00
1,430.31 4,518.85 - 186,679.61
- - - 2,102.88
- - - 11,520.00
904.24 597.36 - 4,818.63
- - - 33.01
- - - 125.16
155,804.54 16,707.85 - 261,012.21

Pgina 16 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
103,677.11 11,118.03 - 173,689.28
74,000.95 7,935.44 - 123,975.86
- - - 95.59
- - - 4,406.78
- - - 266.95
- - - 500.00
155.00 - - 155.00
- - - 608.58
- - - 550.00
- - - 2,542.00
- - - 16,500.00
- - - 16,278.35
- - - 667.35
- - - 700.00
- 12,000.00 - 12,000.00
- - - 59.32
- - - 441.42
21,500.00 - - 43,000.00
- - - 27,500.00
- - - 2,500.00
- - - 6,504.90
- - - 4,717.13
- - - 7,441.19
- - - 135.77
- - - 504.00
- - - 285.55

Pgina 17 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
135.27 - - 1,155.90
- - - 59.70
- - - 70.00
- - - 21.42
- - - 5.80
- - - 18.61
- - - 21.24
15,293.36 19,662.89 - 37,216.42
150.00 - - 150.00
- - - 155.68
- 5,000.00 - 5,000.00
- - - -
- - - -
- - - -
- - - -
- 7,500.00 - 7,500.00
- - - -
- - - 9,201.89
- - - 53.18
92.45 118.86 - 744.32
- - - 759.15
- - - 1,080.00
- - - 15.26
- - - 80.66
- - - 487.40
- - - 17,792.00

Pgina 18 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - 10,017.25
- - - 6.41
- - - 375.00
- - - 3.80
- - - 347.50
- - - 900.00
- - - 299.60
- 250.00 - 250.00
- - - 1.56
- - - 1,520.45
3,186.01 - - 64,207.67
- - - 15.56
67.50 - - 67.50
608.72 - - 3,452.00
- - - 1,000.00
- - - 279.30
- - - 2,415.00
- - - 105.00
- - - 207.96
- - - 267.53
- - - 7,500.00
- - - 3,700.00
- - - 875.00
- - - 23,040.00
- - - 21,128.00
- - - 330.00

Pgina 19 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - 3,449.16
- - - 467.82
- - - 518.64
- - - 467.82
- - - 467.82
- 217.23 - 3,907.07
- - - 189.75
- - - 118.40
- - - 8.50
- - - 473.28
- - - 98.55
- - - 64.50
- - - 309.42
- - - 2,120.00
- - - 220.00
- - - 131.60
- - - 94.80
- - - 299.20
- - - 70.20
- - - -
- - - 120.70
- - - 7,750.00
- - - 371.20
- - - 1,498.56
- - - 62.40
- - - 241.60

Pgina 20 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - 2,608.20
- - - 149.54
- - - 7.20
- - - 25.40
4,086.60 5,254.20 - 9,340.80
92.47 118.89 - 211.36
- - - 250.80
- - - 130.50
- - - 40.00
- - - 132.00
- - - 41,700.00
- - - 16,124.00
- - - 477.50
- - - 58.31
- - - 68.04
- - - 122.50
- - - 871.20
- - - 153.07
- - - 612.50
- - - 196.50
- - - 1,004.50
- - - 2,770.20
- - - 3,340.20
- - - 900.00
- - - 603.48
- - - 825.00

Pgina 21 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - 1,170.00
- - - 725.00
- - - 1,170.00
- - - 135.40
- - - 111.00
- - - 131.60
- - - 829.07
- - - 170.40
- - - 946.40
- - - 2,462.40
- - - 148.80
- - - 1,650.00
- - - 143.05
- - - 875.00
- - - 1,050.00
- - - 3,350.00
- - - 435.00
- - - 46.80
- - - 79.04
- - - 8.04
- - - 21.70
- - - 3,818.03
- - - 6,349.98
- - - 5,050.06
- - - 1,595.34
- - - 233.24

Pgina 22 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - 811.25
- - - 416.90
- - - 138.64
- - - 80.00
- - - 444.50
- - - 45.80
- - - 109.60
- - - 126.60
- - - 17.00
- - - 602.96
- - - 75.00
- - - 2,527.52
- - - 947.82
- - - 6.95
- - - 525.00
- - - 11,156.09
- - - 2,025.64
- - - 22,324.02
- - - 66,328.26
- - - 28,700.31
- - - 6,449.58
- - - 35,879.91
- - - 6,318.75
- - - 4.06
- - - 695.00
- - - 104.60

Pgina 23 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - 7,228.00
- - - 453.14
- - - 2,730.00
- - - 2,730.00
- - - 11,000.00

- - - 40,000.00
- - - 225,000.00
- - - 135,000.00
- - - 35,000.00
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - -
- - - 210.48
4,290.05 6,111.76 4,591.77 40,198.10
- - - 3,998.40
- - 73,172.21 156,690.00

Pgina 24 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
- - - 98.62
- - - 240.00
- - - 524.20
- - - 4,376.75
- - - 499.14
- - - 8,492.19
101.44 - - 554.58
- - - 532.00
- 2.50 - 2.50
- 480.00 - 480.00
- - - 48,788.60
7,738.35 14,005.81 10,731.64 48,018.15
- - - 30.96
21,722.45 2,120.71 - 42,581.77
3,648.74 356.36 - 7,151.69
- 1,415.61 - 7,201.72
1,520.31 5,389.52 - 39,251.00
20,264.33 - - 288,794.30
710.19 - - 3,757.04
- - - 2,561.99
- - - 39.12
- - - 251.10
- - - 15.54

719,945.16 396,255.42 222,028.36 4,809,898.27


71,994.52 39,625.54 22,202.82 480,989.83
50,396.16 27,737.88 15,541.98 336,692.88

Pgina 25 de 26
Municipalidad Distrital de Achoma

e Utilizacion de Recursos

PLAZO DE EJECUCION
TOTAL
30 Das 30 Das 30 Das
270 Dias
842,335.84 463,618.85 259,773.16 5,627,580.98
151,620.45 83,451.39 46,759.18 1,012,964.58
993,956.29 547,070.24 306,532.34 6,640,545.56
35,997.26 19,812.77 11,101.42 240,494.91
3,599.73 1,981.28 1,110.14 24,049.49
90,000.00
18,000.00 18,000.00
1,049,718.70 577,761.69 323,729.24 7,013,089.96
6,111,599.03 6,689,360.72 7,013,089.96
14.97% 8.24% 4.61%
87.15% 95.39% 100.00%