CONFRONTED WITH the large n u m b e r of bridges t o be other unavoidable circumstances, this bridge h a d to be
constructed as part of the burgeoning highway program redesigned a n d no validation of the estimated savings
that is imposing an additional burden upon the already shown in Part 1 is possible.
overburdened fiscal capacity of all levels of government, Part 2 contains the results of letting to contract 12
it is an appropriate time for bridge engineers to examine bridges using this system. These results are compared
the factors underlying current bridge practice for the to costs for other steel stringer bridges of similar spans
purpose of determining what, if any, alterations of this using standards of the Oklahoma State Highway Depart-
practice are in order. This determination necessarily ment. T h e economies achieved exceeded the most op-
requires an evaluation of the trends and possibilities in timistic estimates of the Department.
bridge design, fabrication and erection.
Toward this end a thorough evaluation was made of
the current practice and future possibilities in bridge
design, fabrication, and erection from which the follow- BACKGROUND
ing conclusions were reached: T h e idea for the use of wide stringer spacings and a two-
way reinforced slab developed from the rather startling
(1) T h e use of wide stringer spacings with two-way
reduction in steel weight (and consequent costs) that
reinforced concrete decks will generally result
resulted from a reduction in the n u m b e r of stringers
in substantial savings in cost.
from 5 to 4 on an Oklahoma State Highway standard.
(2) Continuous spans, even when the spans are quite
T h e roadway width on this particular standard was
short, are generally more economical than simple
30 ft-0 in. I t was reasoned that, if a saving could be
spans.
realized by reducing the number of stringers from 5 to
In making this evaluation little attention was di- 4, would it not then be possible to achieve even more
rected to the design specifications, although it appears economy by supporting a 30 ft-0 in. roadway bridge
that some changes m a y be warranted, particularly in with 3 stringers?
the area of two-way slab design. I n addition no considera- It was proposed that for a 30 ft -0 in. roadway bridge
tion was given to bridges with spans of over 100 ft, a 13 ft-0 in. stringer spacing be used a n d that the con-
since by far the greatest majority of money spent on crete deck be reinforced in two directions to minimize t h e
bridges is spent on bridges with spans of less than 100 ft. necessary slab thickness. After considerable investigation,
However some of the principles that evolved would have and discussions between the consultant, T r e a t Engineer-
application for spans over 100 ft. ing Company (now Pearson-Chase & Associates), the
Part 1 of this paper will deal with design investiga- Oklahoma State Highway Department a n d the Bureau
tions for a 180 ft-0 in. portion of a bridge which has a of Public Roads, it was decided that the consultant could
total length of 822 ft-3 in. This portion of the design proceed with final designs and plans based on stringer
was selected because it embodies all of the design de- spacings varying between 12 a n d 15 ft, a n d using r e -
cisions that evolved from the evaluation of current bridge inforced concrete decks that were reinforced in two di-
practice. Unfortunately because of roadway changes and rections. Changes in roadway criteria eventually ruled
out the use of wide stringer spacings on some of the bridges
in the consultant's contract, so that only 14 bridges
Stanley Grossman is a Consulting Engineer, Norman, Okla. with stringer spacings varying between 12 ft-0 in. and
14 ft-6 in. were designed in this manner.
52
Fig. 7. Plan of bridge discussed in Part 7. Revision of roadway width caused this bridge to be redesigned using 8 ft-6 in. stringer spacing.
53
APRIL/1965
forcing steel quantities in the curbs and parapets since Perhaps the clearest approach to the comparison
they would be the same in both designs. For the piers, only presented in Table 1 is to combine the concrete and re-
the concrete and reinforcing steel quantities for the inforcing steel quantities from the slab and piers, since,
2 ft-6 in. diameter pier shafts, which directly support the more often than not, the unit price bids are the same
stringer at the interior reaction points, are included in the in both locations. Compared in this m a n n e r it becomes
table. T h e pier foundation quantities have been omitted apparent that for all of the items that are part of the two
from the comparison because the quantities in the two de- structures, except reinforcing steel, the cost is less for
signs are approximately equal. the 13 ft-0 in. stringer spacing. Including reinforcing
T h e quantities for the one-way slab design are based steel, the total difference between the two structures
on the use of 5 stringers spaced at 6 ft-9 in., a 6 ^ in. is $3,648, which results in a 12.8 percent saving for the
thick slab, and piers composed of 2 ft-6 in. wide by 13 ft-0 in. stringer spacing design on the affected items
4 ft-0 in. deep cap beams supported on 2 ft-6 in. diameter of the structure. This percent saving would be subject
shafts. to very little variation for bridges with spans of 60 ft
A noteworthy consideration that is illustrated in Table or less, whereas the item of additional earthwork re-
I is the matter of the additional earthwork required to quired to increase the structural depth can fluctuate
permit the use of a plate girder with a total depth of a considerably depending on the grades of the intersect-
little less than 42 in. compared to the 30 in. V\F section ing roadways. Occasionally, as in the bridge used as an
with cover plates. For many bridges with a structural example in this paper, there is more t h a n enough struc-
depth limitation the increased depth may not be avail- tural depth in a large portion of the bridge because the
able. However, where this limitation does not exist the grades of the intersecting roadways are controlled at
economic depth should be used, since dirt is relatively points away from the intersection. In such instances the
inexpensive and the reduction in the cost of the super- savings would be the above 12.8 percent of the affected
structure and piers usually more than offsets the addi- items. However, the situation more commonly encoun-
tional cost for the earthwork. In the portion of the bridge tered is one where some additional earthwork is nec-
presented in this paper there was an available structural essary, such as the situation hypothesized previously
depth of about 6 ft, which was more than enough to in this section, for which additional earthwork has been
provide an economical depth plate girder. Neverthe- calculated and shown in Table 1. This amount would
less, in order to obtain an idea of how much additional be about as much additional earthwork as would nor-
earthwork is involved in increasing the structural depth mally be required for a two lane bridge crossing another
I I in., as was done in using 39 in. plate girders in place highway. There would be infrequent cases, such as for
of 30 in. V\F beams, a set of conditions were hypothesized the bridge on the top level of a three level interchange
which would yield close to the maximum amount of where more earthwork than shown in Table 1 would be
additional earthwork that would be necessary to provide necessary, but generally the quantity will be less.
11 in. more structural depth. T h e design speed on the Therefore the savings on the affected items will usually
highway of which the bridge is a part was assumed to be be somewhere between 7 and 12.8 percent in favor of the
60 mph, the maximum grade 3 percent, and the mini- 13 ft-0 in. stringer spacing. Since the affected items
m u m vertical clearance 16 ft-0 in. T h e roadways cross- represent about 60 percent of the total cost of the bridge,
ing each other were assumed to be at the same level the savings as it applied to the total cost of the bridge
as the existing ground and therefore the increases in would be between 4.2 and 7.7 percent.
the roadway elevation would be made with embank- O n e of the factors that brought about the substantial
ment. T h e roadway width is 24 ft-0 in. and since it is a savings of structural steel in the 13 ft-0 in. stringer spacing
one way roadway there is a 10 ft-0 in. shoulder on the design was that composite design was economically
right and a 4 ft-0 in. shoulder on the left. feasible for this design while it was not for the 6 ft-9 in.
Wide stringer spacing will generally diminish the stringer spacing design. This indicates that wide stringer
exposed area of steel, thus reducing the painting costs spacing can bring the economy of composite design to
which are both an initial and a continuing cost. In more bridges than the conventional spacing.*
the example shown the cross-frames used with the plate T h e prices used in the table were obtained from local
girders contain 30 percent of the total exposed area of fabricators and contractors, and from current highway
steel while the W 7 diaphragms used with the rolled beams lettings.
contain less than 15 percent, which is the reason that
the two designs used in Table 1 have almost the same
exposed areas. In cases where both the wide and normal * At the time of this study (7967) shear conductors were more ex-
pensive than they are now (7965). The present practice of the
stringer spacing designs use plate girders or rolled beams
Oklahoma State Highway Department is to use shear connectors on
the reduction in painting will be consistent with the all steel stringer bridges. However, they are of greater value for a
reduction of steel weight. wide stringer spacing design than for the normal spacing design.
Table 1. 13 ft-0 in. Stringer Spacing with Two-Way Slab vs. 6 ft-9 in. Stringer Spacing with One-Way Slab
Structural Steel Erec- 334 man-hrs 6 . 5 0 / m a n - h r 2,171 465 man-hr 6.50/man-hr 3,023
tion
12 55 . 00 in place 660 20 50.00 in place 1,000
Bearings
Slab Reinforcing Steel 34,100 lbs 0.11/lb 3,751 27,660 lbs 0.11/lb 3,043
Slab Concrete 7 in. thick 124.8 cu yd 45.00/cuyd 5,616 63^ in. thick 115.9 cu yd 4 5 . 0 0 / c u . yd. 5,216
Pier Reinforcing Steel 2,880 lbs 0.11/lb 317 6,600 lbs 0 . 1 1 / l b 726
Pier Concrete 21.8 c u y d 42.00/cuyd 916 33 .1 cu yd 4 2 . 0 0 / c u yd 1,390
Additional Earthwork 4,720 cu yd| 0.35/cuyd 1,652
TOTAL $26,502 $28,495
Item Size Quantity Unit Cost Cost Size Quantity Unit Cost Cost
Structural Steel 39 in. pi. girder 87,840 lbs $0.13/lb. $11,419 39 in. pi. girder 106,640 lbs $ 0 . 1 2 7 5 / l b $13,597
Fabrication composite composite
Structural Steel 334 man-hrs 6.50/man-hr 2,171 240 man-hr 6 . 5 0 / m a n - h r 1,560
Erection
Bearings 12 5 5 . 0 0 in place 660 18 50.00 in place 900
Expansion De- 1 600.00 in place 600 2 575.00 in place 1,150
vices
TOTAL $14,850 $17,207
55
APRIL/1965
design presented in Table 1, plate girders using riveted but as the span lengths decrease the savings in expansion
connections would produce little, if any, total saving devices and bearings assume greater significance and,
compared to the conventional design. If, for example, as can be seen in the figures shown in Table 2, represent
the use of riveted connections increases the total cost a significant portion of the total savings brought about
for fabrication by 20 percent there would be a $288 by continuity.
saving in favor of the 6 ft-9 in. stringer spacing design. Continuous spans also substitute one line of dia-
If for some reason welded connections could not be used phragms or cross-frames for two lines at each pier be-
in this example, as mentioned in the preceding para- tween spans. Although the structural steel weight decreases
graph, savings could still be achieved with wide stringer in continuous spans, the fabrication cost remains about
spacing by using 36W 7 beams. However, without low the same and the erection cost increases. O n all but
cost, reliable welded flange-to-web and flange-to-flange the very short spans (40 ft or below) the savings in
connections there would even be certain continuous and structural steel weight more than pays for the added
simple span lengths for which wide stringer spacing and a erection costs. Because of this, continuous spans of less
two way slab could not produce an economical design. than 40 ft can only be justified on the basis of the savings
in expansion devices and bearings.
Continuity for Short Span BridgesUnlike wide To illustrate the cost reductions effected by continuity
stringer spacing with a two-way slab design, continuity the comparable quantities of a composite simple beam
for short span bridges has found some, although not solution are listed in Table 2 along with the like items
widespread, acceptance. For bridges with spans of be- from the proposed design. T o span 180 ft-0 in. bearing
tween 60 and 100 ft the use of continuity is not unusual, to bearing requires three simple spans of 59 ft-3 in. each,
particularly as the spans approach 100 ft. This was but aside from this slight change the other physical di-
economical practice in the past solely on the basis of mensions of the composite simple beam design are the
the saving in stringer steel, even with the use of relatively same as in the wide stringer, continuous design from
expensive riveted connections. Today, with less expensive Table 2, including the use of a plate girder built with a
welded connections, continuity effects an even greater 39 in. x % in. web plate. Therefore no reduction in
saving in short span bridges, and at the same time the earthwork exists in this example although generally
welded connections, particularly the splices, have im- there is a reduction since continuous spans usually re-
proved the appearance of the structure. It is because of quire shallower sections than simple spans.
these two factors, coupled with the reduction of design The piers are excluded from the comparison in Table 2,
time and effort brought about by the use of electronic since both designs would use three single shafts at each
digital computers, that bridge designers are gradually pier. Actually in the simple beam solution the shafts
putting continuity to use on bridges with spans of less would have to be at least 3 ft-0 in. in diameter at the
than 60 ft. T h e latter trend should become widespread top in order to allow for the placement of two bearings
with the realization that in many cases the savings there. The cost of the additional concrete would be in-
in expansion devices and bearings will be almost as consequential since the labor costs would be almost iden-
significant as the savings in stringer steel. This has been tical for both size shafts and therefore the only increase
especially true in recent years with the advent of the in cost is for the added concrete at the price for the ma-
improved, b u t more expensive, finger-type expansion terial alone, which is about $15 per cubic yard.
joint with the necessary troughs and downspouting T h e percent savings effected by continuity in short
to prevent water from damaging the bearings.* span bridges would remain approximately as indicated
in Table 2 for spans of 60 ft and less; however, the pro-
T h e Economy of ContinuityFor the same span portion of the saving attributed to bearings and ex-
lengths and total length of bridge, continuous spans pansion devices would increase as the span lengths de-
generally require fewer expansion devices and, for the creased. For instance, if instead of three 60 ft-0 in. spans
same stringer spacing, slightly more than half as many there were three 40 ft-0 in. spans, both the total and the
bearings as compared to simple spans. This is a con- percentage structural steel savings diminish compared
sideration that probably has not received too much to the 60 ft-0 in. span design while the total and per-
emphasis, with most of the attention in the continuous centage savings stay the same for the bearings and ex-
to simple span comparison being directed toward the pansion devices. Therefore the combined effect is to
weight saving in the stringers. For bridges with spans increase the porportion of the total saving attributed to
of over about 60 ft the latter justifies the most attention, bearings and expansion devices. *
Current Oklahoma State Highway Department practice is to use a * The use of neoprene bearings and expansion joints has tended to re-
neoprene compression seal type joint which somewhat minimizes duce the above benefits due to continuity on the shorter spans.
this advantage.
56
APRIL/1965
in excess of the maximum of 12.5 percent predicted in and $0.96 respectively and again substantiate the thesis
Part 1. An explanation of this deviation can probably that significant savings can be realized by employing
be found in two factorsthe unexpectedly low unit bid wide stringer spacings and continuity instead of 7 ft-0 in.
prices and a difference in the methods employed in stringer spacings and simple spans. Although, as pointed
arriving at the two percentages. T h e low unit bid prices out previously, a savings percentage of the total bridge
lowered the denominator of the percentage fraction cost is not an accurate indicator, it is of some interest
without proportionately lowering the numerator. As for to note that the totals shown for Bridges 1 and 2
the percentage determination methods, Part 1 was represent, respectively, 59 and 63 percent of the total
concerned with two separate comparisonswide stringer bridge cost. O n this basis the percent savings, measured
spacing and continuitywhile in Table 3 these two against the total cost of a bridge using 7 ft-0 in. stringer
considerations are dealt with at the same time. As a spacing and simple spans, is 9.9 percent for Bridge 1
result of this method difference, more additional earth- and 11 percent for Bridge 2.
work is required in Table 1 than in Table 3, reducing Finger type expansion devices were used on the
the net savings in Table 1 as compared to Table 3. bridges shown in Table 4; and, as discussed previously,
Actually a more meaningful number than a percent with the use of neoprene compression seal type expansion
saving would be a per square foot difference in cost joints the per square foot cost difference between the
between solutions. This figure can be developed without two systems would now be less. However, it is also well to
considering the percentage of the total bridge cost that
the involved items represent. T h e latter percentage is
subject to wide variation, depending a great deal upon
the type of foundation supporting the bridge. As can be Table 3
seen from Table 3 the per square foot cost difference is
$1.58 in favor of wide stringer spacing and continuity. 3-60 ft simple beam spans30 ft roadway
However, as pointed out earlier, the Oklahoma State 5 stringers @ 7 ft-0 in.; 63^ in. thick floor
Highway Department is now using the neoprene com- Unit
pression seal type expansion joint. Since Table 3 quan- Quantity Price Amount
tities are based on the use of the finger type joint, the
S t r u c t u r a l Steel
per square foot cost difference would not now be as (36 in. V\F) 172,270 lbs $ 0.135 $23,256
much as $1.58. Slab Reinforcing Steel 31,050 lbs 0.10 3,105
In the second comparison, as shown in Table 4, two Slab Concrete 111.1 c u y d 42.00 4,666
of the bridges let to contract are compared to an example Pier Reinforcing Steel 6,600 lbs 0.10 660
Pier Concrete 33.1 cu yd 42.00 1,390
bridge which uses 7 ft-0 in. stringer spacing and is
composed of simple spans of comparable length to the TOTAL $33,077
former two. T h e quantities include the pier footings and Area = 180(30)
Cost per sq ft =
the curbs and parapets, except that in the example = 5400 sq ft 5,400
bridge only one curb and parapet was included. T h e
latter was done because the roadway width of the
3-60 ft continuous plate girder spans30 ft roadway
example bridge was about one-half of the width of the 3 stringers @ 13 ft-0 in.; 7 in. thick floor
other two bridges. If both parapets were included in the
example bridge it would disproportionately increase the Unit
per square foot costs of this bridge for comparison with Quantity Price Amount
the other two bridges. No quantities for the abutments "Structural Steel (39
are included. Additional earthwork was not considered a in. PL Girder) 92,720 lbs $ 0.150 $13,908
significant factor in the second comparison because Slab Reinforcing Steel 34,100 lbs 0.10 3,410
Slab Concrete 124.8 cu yd 42.00 5,242
there was only a slight difference in the required struc-
Pier Reinforcing Steel 2,880 lbs 0.10 288
tural depths for the three bridges. Except for structural Pier Concrete 21.8 cu yd 42.00 916
steel, the unit prices used on the example bridge were Additional Earthwork 2,360 cu yd 0.35 826
the same as those used for Bridges 1 and 2. Since the TOTAL $24,590
unit price for simple span steel is usually lower than con-
Area = (180) (30) $24,590
tinuous span steel, the unit price was assumed to be Cost per sq ft = ' _ = $4.55
= 5,400 sq. ft 5,400
$0.01 lower for the example bridge. All three bridges
$1.58
use W7 stringers. Percent savings on affected items = 25.8 percent
$6.13
T h e most obvious fact to be noted in Table 4 is the
a
per square foot cost difference between Bridges 1 This quantity includes the weight of the bearings and the
and 2 and the Example Bridge. These figures are $0.92 expansion devices.
58
$52,162
Area = 61(188.25) Cost per sq ft 1.54
= 11.483 sq ft TT^83~
CONCLUSIONS
T h e magnitude of the design problem presented is not
EXAMPLE BRIDGE great, and perhaps it is for this reason that little attention
30 ft-0 in. roadway
has been given to optimizing and aesthetically improving
40 ft-0 in.; 50 ft-0 in.; 40 ft-0 in. simple spans
7 ft-0 in. stringer spacing the design of short span highway bridges. However, the
magnitude of the cost of all such bridges to be built in
Unit the United States suggests that efforts be directed toward
Quantity Price Amount improving their design.
A thorough evaluation of current practice and future
Structural Steel 94,830 lbs $ 0.125 $11,854
Class " A " Concrete 33 .1 cu yd 42.00 1,390 possibilities in bridge design and construction led to the
Class " A " Concrete following conclusions:
Pier Bases 18.6 cu yd 40.00 744
Class " A A " Concrete 102.6 c u y d 42.00 4,309 (1) The use of wide stringer spacings with two-way
Reinforcing Steel 31,750 lbs 0.10 3,157 reinforced concrete decks will generally result
TOTAL $21,454 in substantial savings in cost.
(2) Continuous spans, even when the spans are quite
$21,454
Area = 30(130) Cost per sq ft = $5.50 short, are generally more economical than simple
= 3,900 sq ft "3^900~
spans.
59
APRIL/1965
Conclusion (1) stems from the idea that both from fied as the spans increase in length. In the area of re-
the standpoint of fabrication and erection it is desirable search, the A A S H O specifications with regard to the
to have the fewest possible n u m b e r of stringers support- design of two-way slabs should be closely examined.
ing the roadway. By doing this, less steel and labor are Comparing it to other acceptable methods of analysis,
required in fabrication and there are fewer units to erect. it appears that the A A S H O method may be over-
T o implement this idea for application to short span conservative. Another area of research that deserves
bridges, stringers are required that are larger than those some attention is wheel distribution factors for spans over
used with conventional spacing, and a two-way rein- 12 ft. Most of the research that has been done in arriving
forced concrete deck is needed to prevent the additional at the present distribution factors was directed toward
cost of the deck from greatly reducing the savings in spacings of 6 ft to 9 ft which is the range for what has
structural steel. T h e larger stringers are now economi- been the normal stringer spacing. T h e Oklahoma State
cally possible because of low cost, reliable welded flange- Highway Department is presently formulating plans to
to-web and flange-to-flange connections for plate girders instrument some of the wide stringer spacing bridges
and welded cover plate connections for rolled beams. now under construction. Their goal is to gather and
For many span lengths for which V\F beams are used evaluate data in the two areas just mentioned, and it is
with conventional stringer spacing, plate girders are hoped that improved design criteria will be developed.
required with wide stringer spacing, and because the A development that will inevitably have impact on
larger stringers are used, composite design was not eco- design using wide stringer spacings is the hybrid girder.
nomically feasible in the 6 ft-9 in. stringer spacing design Essentially, the structural steel reduction that results
while it contributed greatly to the savings in the 13 ft- from the use of wide stringer spacing evolves from the
0 in. stringer spacing design. elimination of inefficiently stressed girder webs. T h e
T h e basis for conclusion (2) lies not only in the sav- virtue of the hybrid girder lies in the use of inexpensive,
ings in structural steel but in the savings in bearings and carbon steel in the webs and high strength steel in the
expansion devices. T h e latter is significant for short flanges where it functions efficiently. T h e two ideas
span bridges where the savings for these items amount mutually complement and serve each other. However,
to an increasingly larger portion of the total savings as deflection criteria becomes an important consideration
the span lengths decrease. T h e use of welded connections in the use of both ideas. This criteria influenced the
has contributed greatly toward effecting savings in member selection for the two-way slab bridges already
continuous spans because of the splices and the frequent let to contract. It is also likely that the design of hybrid
changes in flange thickness. For the latter welding is girders will be controlled by deflection. Since the
particularly important, since riveted or bolted flange modulus of elasticity is not increased along with the
connections would increase the structural steel costs to allowable stress for high strength steels, deeper girders
a point where continuity would not be economical for will be required than would have been had stress alone
most short span bridges. In addition, welded splices have controlled.
made continuous span bridges more aesthetically Finally, it should be recognized that the design and
palatable. plan preparation for a bridge using a two-way slab is
As a result of wide stringer spacing a savings of more time consuming than for a one-way slab. For
between 4.2 and 7.7 percent can be realized in the total instance for the bridge shown in Fig. 1, six sheets were
cost of short span bridges and this added to a 4.8 percent necessary to show the two-way slab details. Only two
saving effected by continuity brings about a savings of sheets are necessary for the same bridge with a deck
between 9 and 12.5 percent, when wide stringer spacing reinforced in one direction.
and continuity are used instead of conventional stringer
spacing and simple beam spans. Considering the fact
that the Bureau of Public Roads estimates that there will ACKNOWLEDGMENT
be almost 10,000 short span bridges in just the new inter- T h e author wishes to thank Mr. Marion Hefley, Bridge
state highway system, the latter savings are quite signif- Design Engineer, Oklahoma State Highway Depart-
icant. ment, for providing much of the cost data used in this
T h e results of two lettings of short span bridges paper, as well as for his review of the text.
employing wide stringer spacing and continuity sub- Appreciation is also expressed to T r e a t Engineering
stantiate the foregoing conclusions. Company, with whom the author was formerly associated,
Future investigations into the use of wide stringer and its successor firm, Pearson-Chase & Associates, for
spacings should consider spacings greater than 15 ft-0 in. their encouragement and support in developing the ideas
It appears likely that wider stringer spacings are justi- presented in this paper.