Technical Seminar on Land Reclamation for our airport
Written by Ir LAU Chun-chung
This technical seminar was presented by Ir Daman Lee, General Manager of the Third Runway Division of the Hong Kong Airport Authority responsible for the reclamation works for the Three-Runway System Development of the Hong Kong Airport. Ir Lee first introduced to us about the background of the current Chek Lap Kok (CLK) airport. The airport, commenced operation in 1998, served 68.5 million passengers, handled 4.38 million tonnes of cargo and accommodated 406,000 air traffic movements in 2015. It is a leading international and regional aviation hub, situated over the former islands of Chek Lap Kok and Lam Chau encompassing an area of over 1,255 hectares, of which three-quarters were reclaimed land. The proposed expansion into the Three-Runway System involves land reclamation of approximately 650 hectares, including 270 hectares on contaminated mud pits, to accommodate the Third Runway Concourse with a floor area of around 283,000m2. Ir Lee then presented the history of reclamation works and the construction of the CLK airport with the fully dredged reclamation method. He listed out the different works and construction equipment involved such as trailer suction hopper dredger for the dredging and marine sand filling works. He also mentioned about the various types of ground improvements methods that were applied, including rolling surcharge and vibro-compaction to satisfy the residual settlement requirements. Ir Lee elaborated on the different site constraints for the proposed expansion that involves a completely non-dredge reclamation method. The major constraint was the environmental concern from the contaminated mud pits within the development footprint. He then explained the conventional methods of soft ground improvement, such as PVD and stone columns are not preferable for treating the contaminated mud pits as they would help the seepage of contaminated materials to the surface. Ir Lee introduced the Deep Cement Mixing (DCM) method, a process by which cement slurry is mixed into the ground to produce DCM column with improved strength by solidifying the contaminated mud. Ir Lee concluded the presentation with the oncoming challenges for the whole three-runway system development such as heavy constraint with the existing airport operation during construction. (347 words) The seminar is well attended by members Ir Kenneth Cheung (R) is presenting souvenir to Ir Daman Lee (L)