ThyssenKrupp Industrial Solutions (India) Private Limited
thyssenkrupp Industries India
Erection Manual
For
Cooler Drum 3.0 x 17M
Index
1. Introduction and Pre-Requisites before actual Mechanical Erection
a. General Information related to project/Equipment
b. Safety Recommendations related to work
c. Transportation, Unloading and Storage and preservation details
d. Foundations
2. Mechanical Erection Instructions for Cooler
a. Reference Documents
i. Drawings
ii. List and Details of Tools and Tackles - with scope
iii. Fabrication Drawings of Temporary Erection Structure with MTO
iv. Resource and Machinery Requirement
b. Erection activities and sequence
i. Checking and Hand-Over of Foundations
ii. Support Roller Assembly Erection and Alignment
iii. Erection of Shell
iv. Grouting of Base-frames
v. Girth Gear Erection and Alignment
vi. Drive Assembly Erection and Alignment
vii. Guards Erection and Assembly
viii. Inlet Hood and Seal
ix. Outlet Hoods and Seal
x. Electrical Installation
xi. Lubrication System Installation
3. Erection schedule for cooler
4. Quality Assurance :
a. Protocols & ITP
b. WPS
c. Consumables specification with estimated qty
Cooler 3.0x17m will be dispatched in 2 parts, the details of which are as follows:
Cooler Drum
Process Parameters
Material : NPK / DAP
Bulk density : 895 - 1070 kg/m3
Feed Size : >2mm - 17-23%
: 2-4 mm - 61-74%
: >4 mm - 9-15%
Feed Moisture (Normal/Maximum) : 1.3-1.5% / 1.5%
Capacity (Normal) : 36-52 TPH
Capacity (Design) : 60 TPH
Duty per day : 24 Hrs
Product Moisture : 1.3-1.5 % / 1.5%
Equipment details
Cooler Drum Size : 3000 mm Dia. x 17000 mm Long
Slope : 4%
Shell Plate Thk : 16 mm Min
Cooler Drum Speed : 4.2 rpm
Riding Rings
Diameter : 3113 ID mm - 3395 OD mm
Width : 370 mm
Trunnion Rollers
Diameter : 840 mm
Width : 420 mm
Thrust Rollers
Diameter : 450 mm
Width : 200 mm
Ring Gear
Type : Spur teeth
No. of Teeth : 170
Module : 24
Face Width : 300 mm
Pinion
Type : Spur teeth
No. of Teeth : 23
Module : 24
Face Width : 330 mm
Drive System
Gearbox type : Helical
Main motor power : 132 kW,
Main motor speed : 1500 rpm
Drive arrangement : Girth gear & pinion
Speed control : Variable frequency drive
Covered Storage:-
All equipments / items like gear boxes, motors, couplings, lubrication system, crusher, roller
assembly, pinion drive assembly etc shall be stored in covered storage.
All machined components should be stored in covered storage area.
All machined surfaces should be protected against falling objects to avoid peel off of the tectyl
paint and well protected from water / moisture and dust ingress.
All Electrical & Instrumentation items and hydraulic systems and parts like and not limited to
measuring, sensing, weighing, analysers, power etc. shall be stored in covered areas.
In general the storage area must be dry, well aerated and ventilated, and shall be protected
against moisture, acids, and other chemical agents.
No material should be stacked on one above the other, except where crating of material is
possible however care should be taken so that there is no deformation on stacking.
No machined surface should be stacked on one above the other.
Since the materials are susceptible to mishandling, hence it is necessarily important that proper
care is adopted for handling and storage of equipments, preferably critical and sensitive parts be
stored in covered storage.
Note:
Any alterations, gas cutting, welding OEM must be consulted in writing.
While moving / transferring any material at site, proper lifting slings, ropes, tools and tackles
should be employed.
Items specifically mentioned above but not limited to shall be stored in proper manner to avoid
any damage, pilferages, etc.
Please refer below sketch for the foundation details of cooler drum.
Tool box consist of steel scale (6 & 12), mechanical plumb, hack saw
frame with blade, Ring and D type spanners up to 46 mm, Allen key set,
35 box spanners with ratchet up to 46 mm, spirit level, flat and smooth files, 5 Nos.
hammer, cutting flair, nose flair, circlip flair, screw driver, slide wrench,
Persian blue etc.
36 Emery wheel / paper, ribbon rough and smooth both As required
37 Scaffolding, pipes and clamps As required
38 Tarpaulin As required
39 Tube cutter / bender (die size as required) 2 Nos. Each
40 Chain wrench, pipe wrench 2 Nos.
41 Wire brush & Chipping hammer 10 Nos.
42 Pyrometer (200 degree centigrade max.) 2 Nos.
43 Diamond wheel with machine for concrete grinding 2 Nos.
Temporary fabricated support rollers with frame for drum erection and
44 10 Sets
rotation as per TKII drawing No. FRT-RD-00301-1/0
45 Welding Rectifier 650 Amperes 6 Nos. Min.
46 Brass and SS shims less than 1 mm As required
47 Buffing wheel 25 Nos.
48 All required lifting slings/ belts, D shackles, pulleys, bull dog grip etc. As required
Bunch of small slings for fixing pulleys, chain blocks and holding shell
49 As required
during dragging
Oil bath (site fabricated steel box) for coupling heating for assembly
50 1 No.
Size: 1100x1100x600mm
51 Burnt engine oil / used oil 600 Ltrs.
Special Tools & Tackles by TKII
1 Tensioning devices for Dryer and Cooler 1 Set
2 Shell erection wedges and clits for Dryer and Cooler 1 Set
3 Earthing clits for all drums 1 set
4 Slope measuring scale for each drum 1 No.
5 Hydraulic jack for drum lifting for maintenance for all drums 1 No per drum
6 Hydraulic button jacks for base frame adjustment for all drums 4 Nos per drum
Themechanicalcontractorshouldnowstarttheerectionactivities.Thecontractor Totalstation,
shouldfirstmarkallthecentrelinesatinlet,outlet&onallthepiers.Theelevation 1MillFitter, Centrepunch,Hammer,
Angle50x50x6
2 markshouldbetransferredatallthedesiredlocations.Thecoolercenters,thesupport 1Helperand Markingthread, 2days
100meter
rollerbearingcentersthestraightdistance&thediagonalshouldbechecked& 1Welder Pianowire,
marked. 50mtape
Slopemeasuringblock,
Masterlevel(.02mm/
Groutingofpadplateof25mmthkonwhichpackingplatesandtaperwadgeswillrest
Padplates25mmthkas 1MillFitterand mtraccuracy),Chipping
3 shouldbedone.Thelevelofthepadplateshouldbecheckedinboththeaxis.Use 3days
required 2Helper chisel,Hammer,
masterlevel&taperblockof4%slopeforleveling.
Daimondcuttergrinding
wheel
AnnexureI
Activityschedule,Resources&MachineryRequirmentforCooler
MaterialbyErection
Sr.No. Activities MaterialbyTKII Manpower Toolsrequired Duration
Contractor
Aftercompletingthepadplategrouting,thefoundationisreadyforsupportrollerbase
frameerection.Withsuitablecrane,Winch,chainblockserectallthebaseframesat
theirdesiredposition.Ensuretheorientationofbaseframebeforeloweringonthe
packingplates.Alignallthebaseframes.Thealignmentchecksareasbelow(asper
approvedITP)
a Baseframecentrewithrespecttocoolercentre
Solidpackingplates Plumb,
b Straightdistanceofbaseframecentreofpier1frominletworkingpoint.
asrequired Pianowire,
c Inclineddistanceofbaseframefrompier1topier2.
(1mmto25mm), 50mtape,
d Inclineddistanceofbaseframefrompier2toworkingpointatoutlet.
stainlesssteelshims 1Millfitter, Springbalance20kg,
e Diagonalfrominletworkingpointtobaseframeatpier1. Machinetaper
ofthickness0.05mm, 1Fitter, Autolevelwith
f Diagonalsofbaseframeatpier1topier2. wedges8xperroller
4 0.1mm,0.25mm, 2Helper, measuringscale, 7days
g Diagonalofbaseframeatpier2toworkingpointatoutlet. stationbaseframe
0.5mmand1mm,Steel 2Rigger, Slopemeasuringblock,
h Elevationofallthebaseframes.
forlockingthebase 1Welder Masterlevel,
i Baseframeslopetobecheckedbymasterlevelbyusingtaperblock.
frame GrindingmachineAG4,
Aftercheckingalltheaboveaprotocolshouldbemaintained&shouldbesignedbyall
j (Channel,Beam,Pipe), Fillerguage,
theconcerndepartments.
GP2groutingmaterial Verniercalliper
k Afterallthechecksaredonethebaseframeshouldbetemporarylocked.
Ensurethefoundationboltsseating&theboltshouldremainverticalbeforereleasing
l forpocketgrouting.Theirshouldbeatleast4/5threadsabovethenutoffoundation
bolts.
Releasethefoundationforpocketgrouting.Propercuringshouldbedoneondaily
m
basis.Curingtimeshouldbe7days.
1Millfitter,
Torquetighteningofallthefoundationbolts.Anydifferenceobservedinelevation
1Fitter,
aftertoquetighteningmustbecorrected.Allthechecksmentionedinpointnumber4 Steelrod8mmthk, Suitablecapacitytorque
5 1Helper,
toberepeated&finalprotocoltobemade.Lockallthepackingplateswitheachother 100meters wrenchandsockets
1Rigger,
bysuitablesteelrod.
1Welder
Erectthesupportingrollerassemblyontothebaseframewithexactorientation& Crane,Winch,Chain
align.Duringalignmentcheckthefollowingpoints.(AsperapprovedITPandformats) block5tons,1''Sling,
Manilarope,Plumb,
a Rollercentrewithrespecttocoolercentre
Pianowire,50mtape,
b Floatingbearingcentretofixedbearingcentre
Autolevelwith
c Axialgapbetweenbearinghousingandbearingouterraceonfloatingside Molycot/Disel, 1Millfitter,
measuringscale,slope
d Dialreadingofbearings.[Axialalignment] Petrol, 1Fitter,
6 measuringblock,Master 6days
e Supportrollercentrewithbaseframecentre. Cleaningcolth, 2Rigger,
level,Grindingmachine
f Rollerslopetocheckedbymasterlevelbyusingtaperblock. Lubricant, 1Welder
AG4,Fillerguage,
g Torquetighteningofholdingdownbolts.
Vernier,Dialguage,
h Measurementofbearingclearances.
Torquewrench,Bearing
i Fillthebearingwithrequiredlubricant.
lockingspanner,Tool
j Makeaprotocolofalltheabovereadingsdulysignedbyalltheconcerndepartments. box
AnnexureI
Activityschedule,Resources&MachineryRequirmentforCooler
MaterialbyErection
Sr.No. Activities MaterialbyTKII Manpower Toolsrequired Duration
Contractor
Fabricationoftemporarystructureinside&outsidethebuildingforhandling,aligning
Plumb,50mtape,
&weldingofthecoolerdrum. Steelforstructure,
Grindingmachine
a Railtobefixedonthetopofstructureforslidingthecooler. Erectionsaddles, 1Fitter,6Rigger,2
7 AG4,Waterlevel,1''sling, 10days
Temperorysupport Welder,2Helper
ErectionsaddlesandTemporarysupportingrollerassemblyshouldbemadereadyfor chainblocks5,2tons,
b rollers,Rail150m
weldingofdryerdrum4nos. Manilarope100meters
Groundassemblyoftyreoncoolershell.Markthecentrelineoftyre&chairplateson
outletcoolerdrumfromtheedge.Placetheoutletcoolerdrumonatemporary Steelframe,Support
structurealongwithsaddle.Fixthechairplatesasperthepositionsmarked&tack roller,Scapfolding,
weldwithcoolerdrum.Insertthetyreontothedrum&slideittoitsrequiredposition. Gratings,Axialalignment Axialalignmentbrackets 6Rigger,2Helper, Crane,
8 2days
Fixthetyreretainingring&lockittemporarywithstoppers.Fixtheaxialalignment 1Millfitter,1Welder 1''sling
brackets,Wooden
bracketsalongwithjackbolt&weldittothedrum,Taketheairgapreadings&makea sleppers
protocol.
Keeptheoutletcoolerdrumalongwiththeassembledtyreonstructureoutsidethe Crane,10tonschain
8Rigger,1Welder,
9 building.Dragtheassemblyinsidethebuildingtillitreachestheworkingpoint.To block2nos,2''sling, 1day
1Millfitter
avoidsleepingoftheshelloppositesideholdingarrangementtobeprovided. Manilarope100mtr
Groundassemblyoftyreoncoolershell.Markthecentrelineoftyre&chairplateson
Steelframe,Support
inletcoolerdrumfromtheedge.Placetheinletcoolerdrumonatemporarystructure
roller,Scapfolding,
alongwithsaddle.Fixthechairplatesasperthepositionsmarked&tackweldwith 6Rigger,2Helper, Crane,
10 Gratings,Axialalignment Axialalignmentbrackets 2days
coolerdrum.Insertthetyreontothedrum&slideittoitsrequiredposition.Fixthe 1Millfitter,1Welder 1''sling
brackets,Wooden
tyreretainingring&lockittemporarystoppers.Fixtheaxialalignmentbracketsalong
sleppers
withjackbolt&weldittothedrum,Taketheairgapreadings&makeaprotocol.
Keeptheinletcoolerdrumalongwiththeassembledtyreonstructureoutsidethe Crane,10tonschain
8Rigger,1Welder,
11 building.Dragtheassemblyinsidethebuildingtillitreachestheoutletshell.Toavoid block2nos,2''sling, 1day
1Millfitter
sleepingoftheshelloppositesideholdingarrangementtobeprovided. Manilarope100mtr
Temperorysupport 8Rigger,1Welder,
12 Insertthetemperoroysupportrollers4setsbelowtheshell. 2days
rollerswithframe 1Millfitter,4Helper
1Fiter,1Helper,
13 Fix&weldtheerectonaidsinside&outsidethedrumoneveryjoint. Scaffolding,Gratings Shelljoiningbrackets 4days
2Welder
Alignthecompletecoolerwiththehelpoferectionaids&weldthelockplatesatevery 1MillFitter,2Welder,4 Pianowire,Steelscale,
14 Gratings Lockplates 7days
joint. Rigger,2Helper Fittertoolbox
Makethepointerarrangementfortakingthepolarreadings.Makeaalignment Steelforpointer 1Fitter,1Welder, Steelscale,
15 1day
protocol. alignment 1Helper Fittertoolbox
AnnexureI
Activityschedule,Resources&MachineryRequirmentforCooler
MaterialbyErection
Sr.No. Activities MaterialbyTKII Manpower Toolsrequired Duration
Contractor
Weldingofshelljoints.Followingproceduretobefollowedforwelding.
a Weldersshouldhavevalidcertificate.
b Weldersshouldgiveatestsample.
c Allweldingjointshouldstartatatime.
d Electrodesshouldbebakedinovenforatleastfor4hoursat300degreecentigrade.
Weldingelectrodes
Everyweldershouldcarryaportableovenhavingaheatingcapacityof100/120degree
e 7018,
centigrade. Agencyforweldtest
Weldingrectifier650
Dependingontheplatethicknessthejointshouldbepreheatedtorequired certify,
amps8nos.,
f temperaturebyheatingtorch.Preheatingshouldbedoneatleast3inchesonboth Testplates300X1502
Mainoven1no,
sidesofthejoint. no.foreachweld,
8Welders, portableoven8nos.,
16 g Stitchweldingshouldbedonebeforetheweldingstarts. 7018electrodes, 10days
6Helper thermochalkor
h Theoutsideweldingshouldbecarriedoutat3Gposition. Scapfolding,
pyrometer,
Tarpolineateveryjoint,
i Rootweldingshouldstartafterpreheatingtheshelltotherequiredtemperature. DPkit10nos.,
Ultrasonictesting
Heatingtorch8nos.,
j Aftercompletionofrootwelding,backgouging&grindingtobedone. agency
Grindingmachine
k CarryouttheDPtestofrootwelding.
AG7/58nos.
l AftercompletionofDPtestfillup&finalweldingtobedone.
m Duringfinalweldingcutalltheerectionaids&stiffeners&grindit.
n Backgougefrominside&grindit.
o CarryouttheDPtestfrominside.
p Completetheinsideweldingatflatposition.
q Carryouttheultrasonictest100%.
Makethepointerarrangementfortakingthepolarreadingsafterwelding.Makethe Steelforpointer 1Fitter,1Welder, Steelscale,
17 1day
protocol. alignment 1Helper Fittertoolbox
Afterultrasonictestlowerthecooleronmainsupportingrollers.Coolertobelowered 8Rigger,1MillFitter,
18 Fittertoolbox 2days
bydraggingthetemperorysupportrolleroutside. 1Welder,1Helper
1Millfitter,2Rigger,
19 Erectandpositionthethruster. Chainblocks5/2tons 2days
2Helper
Postioningoftyresshouldstartafterloweringthecooleronthemainsupportrollers. Weldingelectrodes
7018,Weldingrectifier
a Alignthetyreatpier1&2makeaprotocol.
650amps,Mainoven1
1Millfitter,1Fitter,4
b Checktheairgap&recordit. Scapfolding&gratings, no,Portableoven,
20 Axialalignmentbrackets Welder,2Helper, 7days
thermochalkor
2Rigger
pyrometer,Heating
Aligntheretainingringonbothsides[uphill&downhill]&weldthestoppers.Before torch10nos.,Dialguage,
c
weldingpreheatingofstoppersshouldbedone. Fillerguage
Slopemeasuringblock,
Masterlevel(.02mm/
Groutingofpadplateof25mmthkonwhichpackingplatesandtaperwadgeswillrest
1MillFitterand mtraccuracy),Chipping
25 shouldbedoneondrivefoundation.Thelevelofthepadplateshouldbecheckedin Solidpackingplates 3days
2Helper chisel,Hammer,
boththeaxis.Usemasterlevel&taperblockof4%slopeforleveling.
Daimondcuttergrinding
wheel
Crane,Winch,Chain
26 Erectthedrivebaseframe. 2Rigger,2Helper block5tons, 1day
1''Sling,Manilarope
Assemblyofpinionbearingsonpinionshaft.
a Checktheshaft&bearingsurface.
b Fitadaptorsleevandbearingsontheshaft.
c Tightthelocknut. 1MillFitter,1Fitter, Fillerguage,Vernier,
27 Lubricant 2day
d Assemblethebearingonthepinionshaftmeasuretheclearances. 2Helper,1Welder Torquewrench
e Assembletheplummerblockanditssealingarrangement.
f Fixthecoupling.
g Fillthebearingwithrequiredlubricant.
AnnexureI
Activityschedule,Resources&MachineryRequirmentforCooler
MaterialbyErection
Sr.No. Activities MaterialbyTKII Manpower Toolsrequired Duration
Contractor
Erectthepinionshaftassemblyonthepinionbaseframe.
a Alignthepinionassemblywithgirthgear.Checkthefollowing.
b Checkthebacklash,rootclearance&contact
c Checkthepinioncentrewithrespecttocoolercentre
28
d Checkdistancebetweenfixedbearing&floatingbearing.
e Checkelevationofbaseframe.
f Checkslopeofbaseframe.
g Afterallthechecksaredonethebaseframeshouldbetemporarylocked.
Erectthemaingearbox Solidpackingplates Plumb,
a Fixtheinput&outputcouplings asrequired Pianowire,
b Alignthegearbox&checkthefollowing. (1mmto25mm), 50mtape,
c Maingearboxoutputshaftcentrewithrespecttopinionbearingcenters. stainlesssteelshims 1Millfitter, Springbalance20kg,
29
d Elevationofgearboxshouldbecheckedatall4corners. ofthickness0.05mm, 1Fitter, Autolevelwith
Machinetaper
e Couplingtocouplingstraight&diagonaldistance. 0.1mm,0.25mm, 2Helper, measuringscale, 15days
wedges12x
f Masterlevelofgearbox. 0.5mmand1mm,Steel 2Rigger, Slopemeasuringblock,
g Torquetighteningofgearboxholdingdownbolts. forlockingthebase 1Welder Masterlevel,
Erectthemainmotor frame GrindingmachineAG4,
a Radial&axialalignment. (Channel,Beam,Pipe), Fillerguage,
b Couplinggap. GP2groutingmaterial Verniercalliper
30
c Torquetighteningofmotorholdingdownbolts.
d Fixthecouplingonauxiliarygearbox&motor.
e Erect&aligntheauxiliarydrive&releaseitpocketgrouting.
Ensurethefoundationboltsseating&theboltshouldremainverticalbeforerealizing
31
forpocketgrouting.Theirshouldbeatleast4/5threadsabovethenut.
Releasethefoundationforpocketgrouting.Propercuringshouldbedoneondaily
32
bases.Curingtimeshouldbe7days.
AnnexureI
Activityschedule,Resources&MachineryRequirmentforCooler
MaterialbyErection
Sr.No. Activities MaterialbyTKII Manpower Toolsrequired Duration
Contractor
Aftercuringfulltightenedthefoundationbolts.Anydeviationobservedshouldbe
33
corrected.Alltheabovepointstoberechecked&readingsshouldberecorded.
Note
Allrequiredtools,tacklesandconsumables(likeelectrodes,oxygen,acetylene,grinding
1
wheels,oiletc.)requiredforerectionworktobesuppliedbyerectioncontractor.
SpecialtoolsandtackleswillbesuppliedbyTKIIasperlistmentionaboveinpointno.
2
2.a.ii.
thyssenkrupp Industries India
After providing all the above details all the concern department should sign the protocol.
2. The mechanical contractor should now start the erection activities. The contractor should
first mark all the centre lines at inlet, outlet & on all the piers. The elevation mark should
be transferred at all the desired locations. The cooler centers, the support roller bearing
centers the straight distance & the diagonal should be checked & marked. [Refer sketch
no.1]
[Sketch no. 1]
3. Grouting of pad plate of 25 mm thk on which packing plates and taper wedges will rest
should be done. The level of the pad plate should be checked in both the axis. Use master
level & taper block of 4 % slope for leveling.
4. After completing the pad plate grouting, the foundation is ready for support roller base
frame erection. With suitable crane, Winch, chain blocks erect all the base frames at their
desired position & elevation by giving solid placing plates & machine taper wedges.
Ensure the orientation of base frame before lowering on the packing plates. Align all the
base frames. The alignment checks are as below (as per approved ITP)
a) Base frame centre with respect to cooler centre
b) Straight distance of base frame centre of pier 1 from inlet working point.
c) Inclined distance of base frame from pier 1 to pier 2.
d) Incline distance of base frame 2 to working point at outlet.
e) Diagonal from inlet working point to base frame at pier 1.
f) Diagonals of base frame at pier1 to pier 2.
g) Diagonal of base frame 2 to working point at outlet
h) Elevation of all the base frames.
i) Base frame slope to be checked by master level by using taper block.
j) After checking all the above a protocol should be maintained & should be signed
by all the concern departments.
k) After all the checks are done the base frame should be temporary locked.
l) Ensure the foundation bolts seating & the bolt should remain vertical before
realizing for pocket grouting. There should be at least 4/5 threads above the nut.
m) Release the foundation for pocket grouting. Proper curing should be done on daily
bases. Curing time should be 7 days.
5. Torque tightening of all the foundation bolts. Any difference observed in elevation after
toque tightening must be corrected. All the checks mentioned in point number 4 to be
repeated & final protocol to be made. Lock all the packing plates with each other by
suitable steel rod.
6. Erect the supporting roller assembly on to the base frame with exact orientation & align.
During alignment check the following points. (As per approved ITP and formats)
a) Roller centre with respect to cooler centre
b) Floating bearing centre to fixed bearing centre
c) Axial gap between bearing housing & bearing outer race on floating side only.
d) Dial reading of bearings. [Axial alignment]
11. Keep the inlet cooler drum along with the assembled tyre on structure outside the
building. Slide the assembly inside the building till it reaches the middle shell. Repeat the
above procedure.
12. Insert the temporary support rollers (TKII Drawing No. FRT-RD-00301-1/0) 4 sets below
the shell. ( 2nos.below each drum shell)
13. Fix & weld the erection aids inside & outside the drum on every joint.
14. Align the complete cooler with the help of erection aids & weld the lock plates at every
joint.
15. Make the pointer arrangement for taking the polar readings. Make an alignment protocol.
16. Welding of shell joints. Following procedure to be followed for welding.
a. Welders should have valid certificate.
b. Welders should give a test sample.
c. All welding joint should start at a time.
d. Electrodes should be baked in oven for at least for 4 hours at 300 degree
centigrade.
e. Every welder should carry a portable oven having a heating capacity of 100/120
degree centigrade.
f. Depending on the plate thickness the joint should be pre-heated to required
temperature by heating torch. Preheating should be done at least 3 inches on
both sides of the joint.
g. Stitch welding should be done before the welding starts.
h. The outside welding should be carried out at 3G position.
i. Root welding should start after preheating the shell to the required temperature.
j. After completion of root welding, back gouging & grinding to be done.
k. Carry out the DP test of root welding.
l. After completion of DP test fill up & final welding to be done.
m. During final welding cut all the erection aids & stiffeners & grind it.
n. Back gouge from inside & grind it.
o. Carry out the DP test from inside.
p. Complete the inside welding at flat position.
q. Carry out the ultrasonic test 100%.
17. Make the pointer arrangement for taking the polar readings after welding. Make the
protocol.
18. After ultrasonic test lower the cooler on main supporting rollers. Cooler to be lowered by
dragging the temporary support roller outside.
19. Erect & position the thruster.
20. Positioning of tyres should start after lowering the cooler on the main support rollers.
a. Align the tyre at pier 1 & 2 make a protocol.
b. Check the air gap & record it.
c. Align the retaining ring on both sides [uphill & downhill] & weld the stoppers.
Before welding, preheating of stoppers should be done.
21. Fix and weld the lifters at shell welding joint and spider positions.
22. Remove the inside temporary supporting structure.
23. Shift the gear below the cooler.
24. Assemble the bridge plates, shims & pre stressing shims with gear. Torque tightened the
bolts of bridge plates.
a. Erect the bottom half of girth gear along with the bridge plate assembly.
b. Arrangement for rotating the cooler should be made.
c. Rotate the cooler such that the bottom half of gear should remain on top. Take
care of unbalancing.
d. Erect the other half of gear.
e. Check the joint gap & ensure it is zero by checking with filler gauge.
f. Weld the alignment fixtures on cooler [Axial & Radial]
g. Align the gear Axial & radial & make a protocol.
h. Weld the u clamps with the cooler. Before welding pre heat the shell.
i. After welding recheck axial & radial alignment & make protocol.
j. Remove the pre stressing shims & torque tightened the bolts.
25. Grouting of pad plate of 25 mm thk on which packing plates and taper wedges will rest
should be done on drive foundation. The level of the pad plate should be checked in both
the axis. Use master level & taper block of 4 % slope for leveling.
26. Erect the drive base frame.
27. Assembly of pinion bearings on pinion shaft.
a. Check the shaft & bearing surface.
b. Fit adaptor sleeve and bearings on the shaft.
c. Tight the lock nut.
d. Assemble the bearing on the pinion shaft measure the clearances.
e. Assemble the plummer block and its sealing arrangement.
4. Quality Assurance :
a. Protocols & ITP
2. ITP:
For commented site ITP, please refer annexure II.
2. ITP
For Site ITP, refer annexure II
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
Page 1 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
2 INSTALLATION
Levelling of base frames across the drum 100% checking by auto level. Levelling
2.15 PIN LI-CQA-204-F-02 P W W R
centreline. accuracy of 0.1 mm/ mtr.
Page 2 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
Levelling of base frames across the drum 100% checking by auto level. Levelling
2.35 PIN LI-CQA-204-F-02 P W W W
centreline. accuracy of 0.04 mm/ mtr.
KN.03en
100% dimensional checking. Measurement
2.41 Elevation Vs02_Supporting_Rollers P W W W
within +/-1 mm
(Alignment)
KN.03en
Centre to centre distance between rollers 100% dimensional checking. Measurement
2.42 Vs02_Supporting_Rollers P W W W
at same pier (Both uphill and downhill) within +/-0.5 mm
(Alignment)
100% dimensional checking. Measurement
2.43 Diagonal between rollers at same pier PIN LI-CQA-204-F-03 P W NA W
within +/-1 mm
2.71 Shell Checking (Before positioning) Orientation As per approved drawing P W W RAN
Page 3 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
Dimensional check (Diameter) at 8 - 12
places at shell ends. Measurement within +/-
KN.07en
3.7 mm for dryer
Concentricity Vs02_Concentricity_drum_cy P W W RAN
+/- 3.0 mm for cooler
linder
+/- 3.3 mm for granulator
+/- 2.2 mm for coater
Weld Joint checking / Preparation As per approved drawing PIN LI-CQA-202-F-04 P W W RAN
Page 4 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
KN.01en
Longitudinal measurement. Acceptable
Overall Dimension Vs02_drum_Shell_Section_L P W W RAN
tolerance +/- 5 mm.
engths
2.72 Shell Fit up Joint Gap Asper drawing PIN LI-CQA-202-F-04 P W W RAN
PIN LI-CQA-213-F-01
Establishment of WPS/PQR Approval of WPS/PQR ASME Sec IX - latest edition. P H NA R
PIN LI-CQA-213-F-02
Check welders certification and witness ASME Sec IX - latest edition. / approved
Welder Qualification PIN LI-CQA-213-F-03 P H NA R
tests WPS/PQR
Shell Joint NDT 100% DPT after back chipping ASME section VIII PIN LI-CQA-214-F-01 P R NA R
2.8 Tyre
Page 5 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
2.83 Retainer Block Welding Visual inspection as per ASME section VIII Inspection Report P W NA R
Page 6 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
KN.06en
Tyre / Roller Contact 80 % Contact by visual inspection Vs00_Contact_Situation_at_ P W W RAN
Rollers
b Torque tightening of bolts Torque value as per drawing Torque Tighteneing Record P RAN W R
d Torque Tightening of Gear Joining Bolts Torque value as per drawing Torque Tighteneing Record P RAN W R
Page 7 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
e Torque Tightening of Gear Joining Bolts Torque Value as per drawing Torque Tighteneing Record P RAN W R
Levelling of base frames across the drum 100% checking by auto level. Levelling PIN LI-CQA-204-F-10
d P W W R
centreline. accuracy of 0.1 mm/ mtr.
Page 8 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
Levelling of base frames across the drum 100% checking by auto level. Levelling PIN LI-CQA-204-F-10
d P W W W
centreline. accuracy of 0.04 mm/ mtr.
KN.08en Vs03_Girth_Gear -
As per drawing. Measured at 8 - 12 for dryer and cooler
a Root Clearance and Backlash P W W R
locations TM.10en Vs04_Girth gear -
for granulator and coater
KN.08en Vs03_Girth_Gear -
for dryer and cooler
b Contact with Gear Blue matching with 70-80% contact. P W W R
TM.10en Vs04_Girth gear -
for granulator and coater
Pinion Teeth Temperature (During pre +/- 2 degrees celsius across entire tooth TM.03en Vs01_Meshing_-
P W W R
commissioning trial run) flank. _Temperature
PIN LI-CQA-204-F-10
a Base Frame As per pinion base frame P W W R
Completed final alignment (as above sr. As above. Sr. no. 2 and final
As above (sr. no. 2) P H NA R
no. 2) grouting clearance in writing
Full Grouting of base plates and
3
foundation bolts
Cleanliness of foundations and type of
As per drawing and specification PIN LI-CQA-100-F-13 P W NA RAN
grout material
Page 9 of 10
CLIENT LOGO CONTRACTOR LOGO
Annexure II
CONTRACT NO DOCUMENT NO
STANDARD ITP FOR ROTARY DRUM ERECTION
Responsibilities
Sl. no. Activity Description Check / Inspection Acceptance Criteria Verifying Records Remarks
Contractor TKIS-India TKII PMC / Client
4 QC documents Check completeness & correctness As per drawing and specification QC dossier P H NA R
Legend:
P - Perform
H - Hold point ( further sequential work shall commence only after clearance from TKIS-India/TPI/PMC/Client - as applicable)
R - Review & approve
RAN - Random witness
W - Witness & approve
Page 10 of 10
thyssenkrupp Industries India
4. Quality Assurance :
b. WPS
4. Quality Assurance :
c. Consumables specification with estimated qty
- Electrode : E7018
- Approx. qty: 300 Kgs